Title: Concrete Formwork
1Concrete Formwork Shoring Systems
2Table of Contents
Concrete Construction
- Vertical formwork systems (wall column systems)
- Horizontal shoring systems (flying systems
stationary systems) - Factors Affecting Formwork Shoring Designs
3Concrete Construction
Objectives Goals
- Develop an understanding of the current formwork
shoring systems available today, - Review typical applications and rental costs for
each system, - Learn the factors that govern formwork shoring
designs decisions that contractors face, - Be able to use this knowledge in evaluating
formwork systems to fit the project.
4Factors Affecting Formwork System Selection
- Safety Accident Prevention!!
- Structure Type Design
- Floor to Floor Heights changes
- Column wall layout
- P/T slab or Conventionally reinforced
- Construction Joint locations
- Drop Caps, Slab breaks
- Existing constraints (Adjacent Buildings)
- Number of uses of form system
- Crane size location
- Schedule (Very Important)
- Manpower - Skill Level
- Productivity Cycling of equipment
5Factors Affecting Formwork System Selection
- Risk
- Formwork Supplier
- History with similar projects
- Engineering expertise
- Support services
- Knowledge of support personnel
- Location
- Buy vs. Rent
- Duration of project
- Future usage
- Return on investment
- Maintenance expense on owned equipment
- Storage expense
6Vertical Formwork Systems
7Vertical Formwork Systems
8Vertical Formwork SystemsWood Forming System
9Vertical Formwork SystemsHandset Forming System
- Application Walls Columns
- 50 more productive than
- snap tie wall systems
- Aluminum Frame with a 5/8
- plywood face
- Pour Pressures 1,200 psf
- Ties on 2 x 2 spacings
- Cost 0.85 to 1.00/sf per month
10Vertical Formwork Systems
Handset Forming System
- Panel widths vary from 1 to 30
- Panel heights 3, 4, 5, 6 8
11Vertical Formwork Systems
Hand-Set Forming System
- Quick Pre-assembly
- Moveable by Hand
- Hinges Carts Available
- Braced with 2 x 4s
12Vertical Formwork Systems
Crane Set Forming System
Power Plants
Commercial Building
Bridges
Tunnels
13Vertical Formwork Systems Crane-Set Forming
System
- Application Walls Columns
- Large Gang Wall Application
- Steel Frame with a 3/4
- plywood face Wt. 14 psf
- Pour Pressures 1,500 psf
- Ties on 4 x 4 spacing
- Cost 0.90 to 1.10/sf per month
- European Systems 1.45 to
- 1.65/sf per mo.
14Aluma Gang Wall Forms
Vertical Formwork System
- Form Design Aluma Beam with a
- 55 Kip Aluminum Strongback
- Plywood Face Typically 3/4
- Pour Pressures Up to 1520 psf
- Taper Ties on 6 x 6 Spacing
- Weight 10 Lbs per SF
- Cost 0.65 to 0.75/sf per month
15Aluma Gang Wall Forms
Vertical Formwork System
16Roll Back Jump Forms
Vertical Formwork System
- Problem
- Multi-lift Wall Construction
- Elevator Cores
- Safe Access for Rebar,
- Formwork Concrete
- Placing Operations
- Solution
- Rollback Jump Form
17Roll Back Jump Forms
Vertical Formwork System
- Standard Aluma Gang
- supported on Roll back Bracket
- Provides an 8 wide work deck
18Roll Back Jump Forms
Vertical Formwork System
- Form Rolls back 30 to allow
- access to rebar form Face.
30
19Roll Back Jump Forms
Vertical Formwork System
Standard Williams Type Insert
1 1/4 Landing Bolt support the Roll Back
Bracket
20Elevator Core Form
Vertical Formwork System
- Exterior Roll back panels Interior Cores are
Crane Raised
21Horizontal Shoring Systems
22Hand-Set Shoring Systems Applications
Horizontal Shoring Systems
Horizontal Formwork for Cast in Place Concrete
Re-shoring
23Hand-Set Shoring Systems Applications
Horizontal Shoring Systems
Parking Garages
Truss Table Shoring
24Aluma Frame Shoring System
Horizontal Shoring Systems
- Hand-Set Shoring is rated by the capacity per leg
- 15 kips per leg
- Light weight 6 x 6 frame weighs 44 lbs.
- Cost Varies based on
- Slab thickness (controls beam spacings)
- Shore Heights (Frame stacks)
- H 10 0.35 to 0.45/sf
- H 10 to 15 Say 0.55/sf
25Aluma Frame Shoring System
Horizontal Shoring Systems
- Widest, Strongest Lightest shoring frame on the
market - 15 kips per leg
- Light weight 6 x 6 frame weighs 44 lbs.
- Frame Heights of 8 tall available
26Parking Garage
Horizontal Shoring Systems
Uses Aluma Beam Tables for Deck Support
Uses Aluma Frames to support the beams
27Parking Garage
Horizontal Shoring Systems
Step 1 Beam supports beam sides are
pre-assembled
Step 2 Deck Panels are Pre-Assembled
28Parking Garage
Horizontal Shoring Systems
Step 3 Set Shoring Frames in place then
add pre-assembled Beam Forms
Step 4 Set Pre-Assembled Beam panels
in place
29Parking Garage
Horizontal Shoring Systems
Inserts are added to Deck Panels to allow the
stripping of the beam sides and shoring
30Parking Garage
Horizontal Shoring Systems
Step 5 Cross braces are removed and the Aluma
Frame legs are folding up to facilitate strip and
moving
16
Allows access to move system through set-up
equipment
Step 6 A forklift lowers the forms and
moves to the next pour
31Parking Garage
Horizontal Shoring Systems
Casters allow forms to easily move through project
32Parking Garage
Horizontal Shoring Systems
Questions?
33Aluma Deck
Horizontal Shoring Systems
Application Faster cycle times on flat slab
structures.
2 x 6 Aluminum Deck panels, shore points are on
a 6 x 8 grid
- Cost Varies based on
- Building Geometry (affects post spacing)
- Shore Heights
- Generally 1.10 to 1.25/sf per month
34Aluma Deck
Horizontal Shoring Systems
- Drop Heads for Stripping
- Deck removal one day after the pour and prior to
post-tensioning - Reduced cycle time
- Beam Hangers for column capitals
35Aluma Truss
Horizontal Shoring Systems
Application Used to speed construction on
multi-level building.
1st Floor shoring Trusses are supported on
hand-set Shore X Frames
- Cost Varies based on
- Slab thickness (controls beam spacings)
- Shore Heights (Truss configurations)
- Generally 0.55 to 0.65/sf per month
36Aluma Truss
Horizontal Shoring Systems
- Extension legs Jacks
- 12 18
- 18 24
- 24 30
37Horizontal Shoring Systems
Column Hung
38Horizontal Shoring Systems
Column Hung
- Cost Varies based on
- Slab thickness (controls truss joist spacing)
- Column Spacing
- Generally 0.75 to 1.00/sf per month
39Horizontal Shoring Systems
Column Hung
40Horizontal Shoring Systems
Column Hung
41Horizontal Shoring Systems
Column Hung
- Column Hung Advantages
- No Reshoring
- Stock Floors before you
- fly tables to speed interior
- finishes
- Exterior can Follow closely
42Factors Affecting Formwork System Selection
- Safety Accident Prevention!!
- Structure Type Design
- Floor to Floor Heights changes
- Column wall layout
- P/T slab or Conventionally reinforced
- Construction Joint locations
- Drop Caps, Slab breaks
- Existing constraints (Adjacent Buildings)
- Number of uses of form system
- Crane size location
- Schedule (Very Important)
- Manpower - Skill Level
- Productivity Cycling of equipment
43Factors Affecting Formwork System Selection
- Risk
- Formwork Supplier
- History with similar projects
- Engineering expertise
- Support services
- Knowledge of support personnel
- Location
- Buy vs. Rent
- Duration of project
- Future usage
- Return on investment
- Maintenance expense on owned equipment
- Storage expense
44Horizontal Shoring Systems
Questions?
45Thank you for attending!!
For more information on Aluma Systems please log
onto our website at
www.aluma.com