Title: Chapter 16 Materials Requirements Planning
1Chapter 16Materials Requirements Planning
- Material Requirements Planning (MRP)
- Bill of Material
- MRP Logic and Calculations
- Lot Sizes, Safety Stock and Time Fences
- MRP II
- MRP Management Issues
2Material Requirements PlanningDefined
- Materials requirements planning (MRP) is the
logic for determining the number of parts,
components, and materials needed to produce a
product. - MRP provides time scheduling information
specifying when each of the materials, parts, and
components should be ordered or produced. -
3Material Requirements Planning System
- Based on a master production schedule, a material
requirements planning system - Creates schedules identifying the specific parts
and materials required to produce end items. - Determines exact unit numbers needed.
- Determines the dates when orders for those
materials should be released, based on lead
times.
44
Firm orders from known customers
Forecasts of demand from random customers
Aggregate product plan
Material planning (MRP)
5MRP InputBill-of-Material
- List of components quantities needed to make
product - Provides product structure (tree)
- Parents
- Children
- Shows low-level coding
- Lowest level in structure item occurs
- Top level is 0 next level is 1 etc.
6Bill-of-Material Product Structure Tree
Bicycle(1)
Bicycle(1)
P/N 1000
P/N 1000
Handle Bars (1)
Frame Assy (1)
Handle Bars (1)
Frame Assy (1)
P/N 1001
P/N 1002
P/N 1001
P/N 1002
Wheels (2)
Frame (1)
Wheels (2)
Frame (1)
P/N 1003
P/N 1004
P/N 1003
P/N 1004
7Product Structure Thinking Challenge
- The demand for product A is 50. How many of each
component is needed to satisfy demand?
A
A
B(2)
C(3)
B(2)
C(3)
E(1)
E(3)
F(2)
E(1)
E(3)
F(2)
D(2)
D(2)
G(1)
D(2)
D(2)
G(1)
8Product Structure Solution
50
A
A
B(2)
C(3)
B(2)
C(3)
E(1)
E(3)
F(2)
E(1)
E(3)
F(2)
D(2)
D(2)
G(1)
D(2)
D(2)
G(1)
9Lead Times Product Structure
Handle Bars
2 wk.
Lead time
1 wk.
Frame
2 wk.
Bicycle
1 wk.
3 wk.
Frame Assy
Wheels
Time (weeks)
10MRP Scheduling Terminology
- Gross Requirements demand for an item from
- independent demand
- independent demand
- dependent demand
11MRP Scheduling Terminology
- Scheduled receipts orders that have already
been released (i.e., an open order) and that are
scheduled to arrive at the beginning of the
period. - Projected available balance (On-hand) amount of
inventory at the beginning of a period
12MRP Scheduling Terminology
- Net requirements -
- Planned order receipt -
- Planned order release -
13MRP Formulas
- NRt GRt - OHt SRt (0 if negative)
- OHt OHt-1 SRt-1 POReceiptt-1 GRt-1 SS
14MRP Example - One items complete recordStarting
information
Lead time 3 lot policy lot-for-lot (LFL)
on-hand 20 units safety stock 0 units.
15Low Level Coding
A
Level 0
B
C
Level 1
Level 2
D
C
E
E
Level 3
16Low Level Coding - How to
- Place each item at same level - it simplifies the
calculations
After
Before
A
A
Level 0
B
C
B
Level 1
Level 2
D
C
E
D
C
E
E
Level 3
17An MRP Example
Requirements include 95 units (80 firm orders and
15 forecast) of X in week 10 plus the following
spares
18(No Transcript)
19Lot Sizing in MRP Programs
- We need to reflect restrictions which may exist
in actual practice - Lot-for-lot (L4L)
- Economic order quantity (EOQ)
- Least total cost (LTC)
- Least unit cost (LUC)
- Fixed quantity
- Minimums
- Multiples
20Lot Size Effects
20
Lead Time 3 Lot Size 5 units (or Multiples)
On-Hand 20 Units Safety Stock 0 Units.
21Using Safety Stock
20 - 2
18
Lead time 3 lot policy lot-for-lot (LFL)
on-hand 20 units safety stock 2 units.
22MRP Thinking Challenge
- A master schedule calls for 50 units of F in week
6, 60 in week 8. On-hand levels are F 0, G
20, H 60. Another 20 units of G are
scheduled to be received in week 4. Order
quantities are lot-for-lot except for H, which
has a lot size of 50 or multiples of 50.
F(1)
LT 2
G(1)
H(1)
LT 1
LT 2
H(4)
LT 2
23Product F Solution
24Component G Solution
25Component H Solution
26Another MRP Example
An end item (A) is assembled from 1 sub-component
C, 2 part Ds, and 1 sub-component B Each
sub-component C is assembled from 1 part D and 1
part E Each sub-component B is assembled from 1
part C and 2 part Es The master production
schedule calls for 250 units of A in week 6, 140
in week 8, and 200 in week 9. The following
information is available from the inventory
status file
27MRP Input Master Production Schedule (MPS)
- Time-phased plan specifying how many and when the
firm plans to build each end item.
MPS (Specific End Items)
28Types of Time Fences
- Frozen
- No schedule changes allowed within this window.
- Moderately Firm
- Specific changes allowed within product groups as
long as parts are available. - Flexible
- Significant variation allowed as long as overall
capacity requirements remain at the same levels.
29Example of Time Fences
30MRP InputInventory Records File
- Each inventory item carried as a separate file
- Status according to time buckets.
- Pegging
- Identify each parent item that created demand.
31MRP OutputsPrimary MRP Reports
- Planned orders to be released at a future time.
- Order release notices to execute the planned
orders. - Changes in due dates of open orders due to
rescheduling. - Cancellations or suspensions of open orders due
to cancellation or suspension of orders on the
master production schedule. - Inventory status data.
32Closed Loop MRP
Production Planning Master Production
Scheduling Material Requirements
Planning Capacity Requirements Planning
33Manufacturing Resource Planning (MRP II)
- Goal Plan and monitor all resources of a
manufacturing firm (closed loop) - manufacturing
- marketing
- finance
- engineering
- Simulate the manufacturing system
34MRP Management Issues
- System Accuracy
-
- System nervousness
-
- Integration with Just-in-Time (JIT)
-
-
-
-