Title: Alaska Natural Gas Development Authority
1Alaska Natural Gas Development Authority
IN-STATE GAS TAKE-OFF POINTS
Before the Legislative Budget Audit Committee
-and- Senate Resources Committee In
Anchorage, Alaska, on September 1-2, 2004
2Gas Take-Off Points Along the Gas Line
- Provide Gas for
- Electric Power Plants
- Propane Distribution Centers
- Piped Gas Distribution Systems
- Stand Alone Facility Design
- Combined TAPS Pump Station Compressor Station
- Gas Spur Line to Cook Inlet Area
3PROPANE ONLY Plant Configuration
Gas Pipeline (assume 2000 PSIG 28 degrees F)
Reinjected gas liquids
Raw feed gas
Dehydration
Recompression
After-cooling chilling
Expander compressors
Expanders heat exchange
Liquid pump
Residue gas
C4
N2, CO2, C1, C2 some C3
De-ethanizer tower
PROPANE STORAGE
C3 with some C2 C4
C3, C4 some C2
De-propanizer tower
4UTILITY GAS PROPANE Plant
Gas Pipeline (assume 2000 PSIG 28 degrees F)
Raw feed gas
ELECTRIC POWER PLANT and/or LOCAL GAS
DISTRIBUTION
Reinjected gas liquids
Dehydration
Expanders heat exchange
Expander compressors
Liquid pump
Residue gas
C4
N2, CO2, C1, C2 some C3
De-ethanizer tower
PROPANE STORAGE
C3 with some C2 C4
C3, C4 some C2
De-propanizer tower
5Local Access Take-Off Facility for Natural Gas /
Propane
- 10 mmscfpd gas take-off (very small facility)
- Fuel North Poles new 60 mega-watt power plant
- Fairbanks potential gas demand is two to three
times this size - Supply combined TAPS PS Compressor Station
twice over - Supply a major mine development
- Propane available is 4,000 gal/day (80 recovery)
- Design uses off-the-shelf skid-mounted equipment
- Installed cost is 10.5 million
- Facility cost-of-service
- 50 to 75 cents /gal propane
- 30 cents / mmbtu of gas
6Availability of numerous physical take-off
points for modest volumes
- Gas fired power generation facilities along the
line key to interior Alaskan and Canadian
communities energy needs and cost - Many synergies with compressor station facility
TAPS pump stations for gas take-off - Industrial and spur line take-off points should
be defined before open season - All gas line project proposals must include
simple standardized design for gas take-off,
propane separation, and gas re-injection (also
hook-in)
7Potential Take-Off Locations for Natural Gas /
Propane
- Galbraith Lake
- Coldfoot
- Yukon River
- Fairbanks
- North Pole
- Delta
- Tok
- Glennallen (spur line)
- Palmer (spur line)
- Valdez
- Canadian Highway
- Beaver Creek
- Haines Junction
- Whitehorse
Associated with Compressor Station
8Alaska gas tariffs proportioned for actual
transportation distance
- Having gas physically available in Alaska doesnt
mean much if the tariff within Alaska (set by
FERC, not RCA) includes lost downstream revenues
as a cost charged against gas taken-off in Alaska - Communities and industries should enjoy the
tariff advantage of being located closer to
Alaskas North Slope gas supply in return for
public right-of-way - In-State tariff design can be included in fiscal
terms of Stranded Gas Act contract and/or grant
of ROW
9Spur Line to Cook Inlet Area
- High pressure (2,500 psi) gasline (24 inch diam)
from Glennallen to Palmer (140 miles) can
supply todays 0.5 bcfpd and costs 300 million - ANGDA building the gas spur line as a State
gas transmission utility with low-interest-rate
debt-financing can reduce the cost of service
to 0.15 / mmbtu - Connection and routing dependent on others
decisions on larger North Slope gas projects
(going to Delta doubles cost) - ANGDA will file a State ROW lease application
10- Alaska Natural Gas
- Development Authority
- Homepage is http//146.63.35.79/
- Harold Heinze
- 411 W. 4th Ave, Anchorage 99508
- 257 1347
- Fax (907) 646 - 5005
- hheinze_at_jpo.doi.gov