THE CAPITAL BUDGETING DECISION - PowerPoint PPT Presentation

1 / 31
About This Presentation
Title:

THE CAPITAL BUDGETING DECISION

Description:

CE usually require initial cash outflows in hope of future benefits or cash inflows ... factors such as better corporate image, fairer treatment of employee, etc ... – PowerPoint PPT presentation

Number of Views:42
Avg rating:3.0/5.0
Slides: 32
Provided by: johnn80
Category:

less

Transcript and Presenter's Notes

Title: THE CAPITAL BUDGETING DECISION


1
CHAPTER 12
  • THE CAPITAL BUDGETING DECISION

2
Capital Expenditures Decision
  • CE usually require initial cash outflows in hope
    of future benefits or cash inflows
  • Examples new plant construction, acquisition of
    business, purchase of new machine, etc.
  • Projects often last for more than a year
  • The longer the time horizon, the greater the
    uncertainty

3
Areas of Uncertainty in CE Decision
  • Expected cash flows
  • Product life
  • Interest rates
  • Economic conditions
  • Technological change

4
Capital Budgeting
  • To see if the CE is economically acceptable - if
    it creates or adds value to the firm
  • To examine the CE from an investment perspective
  • The basic concept is to determine if it makes
    sense to commit to an initial cash outflows in
    order to receive future cash inflows

5
Example - Project A
6
Project A cont
7
Project Evaluation
  • Discount Rate Cost of Capital
  • Positive NPV indicates that the yield or rate of
    return on the project exceeds the cost of capital
    (thus add value to the firm)
  • Project is financially acceptable when the PV of
    the total cash inflows greater than the PV of the
    total cash outflows ( ve NPV)

8
Example - Project B
9
Project B cont
10
Project B cont
  • Both projects A and B require an initial capital
    outflow of 10000
  • Both of them will generate a total return of
    12000 in the next three years
  • However, project A has a positive NPV while
    project B has a negative NPV
  • Why?

11
Cash Flows of Project A B
  • Project A
  • Yr 0 -10,000
  • Yr 1 5,000
  • Yr 2 5,000
  • Yr 3 2,000
  • Project B
  • Yr 0 -10,000
  • Yr 1 2,000
  • Yr 2 5,000
  • Yr 3 5,000

12
Reasons
  • For Project A, the cash inflows mainly occur at
    the first two years
  • For Project B, the cash inflows mainly come in at
    the last two years
  • Due to the time value of money, money received
    earlier has higher value than that received later
  • Hence, Project B is not acceptable -(negative NPV)

13
Flexibility of NPV - Using various discount rates
across time
  • The longer the time horizon, the higher the risk
  • Sometimes, we may have to use a higher discount
    rate for income in the latest year
  • Instead of 10, we may use 12 to discount the
    latest cash inflow at the end of third year
  • NPV method provides such a flexibility

14
Flexibility of NPV allow reversal of cash flows
  • NPV method can be applied to any type of cash
    flows even cash flows with reversal
  • Cash flows with reversal means that there are
    more than one cash outflows
  • Example a 2-year project with cash flows
  • Yr 0 Initial cash outflow (-1000)
  • Yr 1 Cash inflow (5000)
  • Yr 2 Another cash outflow (-3000)

15
Profitability Index
  • It is a variation of the NPV method
  • Profitability index (PI)
  • PV of cash inflows/PV of cash outflows
  • If PI gt 1, PV of cash inflows is greater than PV
    of cash outflows. That is NPV gt 0
  • Hence project with PI gt 1 is financially viable

16
Another method - IRR
  • IRR Internal Rate of Return
  • The IRR is the discount rate at which the PV of
    cash inflows PV of the cash outflows
  • I.E., IRR is the discount rate which makes the
    NPV 0
  • Project is financially acceptable when the IRR is
    greater than the cost of capital

17
IRR of Project A
18
IRR of Project B
19
Project Evaluation
  • Project A has an IRR of 11.16 which is higher
    than the cost of capital, 10. Hence project A is
    financially acceptable.
  • Project B has an IRR of 8.53 which is lower than
    the cost of capital, 10. Hence project B is
    financially not acceptable.

20
Why bother to use IRR?
  • Since both NPV and IRR generate similar results,
    why bother to use IRR
  • Yield derived from IRR may be more comprehensible
    than the absolute value derived from NPV
  • In fact, we use IRR when we cannot use the cost
    of capital (the risk of the project differs from
    the risk of the firm)

21
Limitations of IRR method
  • A single discount rate (the IRR) throughout the
    project life inability to account for cash
    flows of different risk levels
  • Possibly unrealistic to assume reinvestment of
    the generated cash inflow at the IRR
  • Inapplicable when more than one reversal of cash
    flows exists will generate multiple IRRs in
    that case

22
Graphical Illustration of NPV and IRR
  • See Examples Below

23
Cash Flows of Investment AB
  • Investment A
  • Yr 0 -10000
  • Yr 1 5000
  • Yr 2 5000
  • Yr 3 2000
  • Investment B
  • Yr 0 -10000
  • Yr 1 1500
  • Yr 2 2000
  • Yr 3 2500
  • Yr 4 5000
  • Yr 5 5000

24
NPV Profile NPVs at different Discounting rate
INV. B
INV. A
25
Cash Flows of Investment B C
  • Investment B
  • Yr 0 -10000
  • Yr 1 1500
  • Yr 2 2000
  • Yr 3 2500
  • Yr 4 5000
  • Yr 5 5000
  • Investment C
  • Yr 0 -10000
  • Yr 1 9000
  • Yr 2 3000
  • Yr 3 1200

26
NPV Profile with crossover
NPV
6000
Crossover point
INV.B
4000
2000
INV.C
IRR 14.33
0
15
20
5
10
IRR 22.49
Discount Rate
27
Where are we?
  • How to raise capital?
  • We have learned the three ways of raising
    long-term capital for a firm. What are they?
  • How to use the capital to generate more money?
  • Underlying principle to generate an investment
    return that is greater than cost of capital
  • The lowest required rate of return cost of
    capital

28
Project Valuation
  • Similar to the valuation of financial
    instruments, we must assess the fair market value
    for any capital expenditure project.
  • The highest price we pay is the present value of
    expected cash flows (derived from the project)
    discounted at the rate equivalent to the cost of
    capital
  • Basic concept lowest rate of return highest
    price to be paid

29
Cash Flows Determination
  • Net of tax i.e. after tax net cash flow
  • Gross of all financing costs (they have been
    reflected in the discount rate)
  • Shortfalls
  • - Future projection may base on extrapolation
  • - Bias built into the cash flows estimation
  • - Over/under estimate of the inflation
  • - Neglect other qualitative factors such as
    better corporate image, fairer treatment of
    employee, etc

30
Capital Rationing
  • Management, for some reasons, may impose a dollar
    constraint in certain kind of investment
  • Projects become mutually exclusive
  • Project is selected based on the amount of
    benefit generated by the project
  • That is, projects with the greatest NPV or the
    highest IRR

31
Table 12-7Capital rationing
Net Total
Present Project Investment Investment Value
  • Capital A 2,000,000 400,000 rationing
    B 2,000,000 380,000
  • solution C 1,000,000 5M
    150,000
  • Best D 1,000,000 100,000
  • solution E 800,000 6.8M 40,000
  • F 800,000 (30,000.)
Write a Comment
User Comments (0)
About PowerShow.com