Title: What is capital budgeting?
1What is capital budgeting?
- Analysis of potential projects.
- Long-term decisions involve large expenditures.
- Very important to firms future.
2Steps in Capital Budgeting
- Estimate cash flows (inflows outflows).
- Assess risk of cash flows.
- Determine r WACC for project.
- Evaluate cash flows.
3What is the difference between independent and
mutually exclusive projects?
- Projects are
- independent, if the cash flows of one are
unaffected by the acceptance of the other. - mutually exclusive, if the cash flows of one can
be adversely impacted by the acceptance of the
other.
4What is the payback period?
The number of years required to recover a
projects cost, or how long does it take to get
the businesss money back?
5Payback for Franchise L(Long Most CFs in out
years)
2.4
0
1
2
3
10
80
60
-100
CFt
100
Cumulative
-100
-90
-30
50
0
PaybackL
2 30/80 2.375 years
6Franchise S (Short CFs come quickly)
1.6
0
1
2
3
70
20
50
-100
CFt
100
Cumulative
-100
-30
20
40
0
PaybackS
1 30/50 1.6 years
7Strengths of Payback
1. Provides an indication of a projects risk and
liquidity. 2. Easy to calculate and understand.
Weaknesses of Payback
1. Ignores the TVM. 2. Ignores CFs occurring
after the payback period.
8Discounted Payback Uses discounted rather than
raw CFs.
0
1
2
3
10
10
80
60
CFt
-100
PVCFt
-100
9.09
49.59
60.11
Cumulative
-100
-90.91
-41.32
18.79
Discounted payback
2 41.32/60.11 2.7 yrs
Recover invest. cap. costs in 2.7 yrs.
9NPV Sum of the PVs of inflows and outflows.
Cost often is CF0 and is negative.
10Whats Franchise Ls NPV?
Project L
0
1
2
3
10
10
80
60
-100.00
9.09
49.59
60.11
18.79 NPVL
NPVS 19.98.
11Calculator Solution
Enter in CFLO for L
-100 10 60 80 10
CF0
CF1
CF2
CF3
NPV
I
18.78 NPVL
12Rationale for the NPV Method
NPV PV inflows - Cost Net gain in
wealth. Accept project if NPV gt 0. Choose
between mutually exclusive projects on basis
of higher NPV. Adds most value.
13Using NPV method, which franchise(s) should be
accepted?
- If Franchise S and L are mutually exclusive,
accept S because NPVs gt NPVL . - If S L are independent, accept both NPV gt 0.
14Internal Rate of Return IRR
0
1
2
3
CF0
CF1
CF2
CF3
Cost
Inflows
IRR is the discount rate that forces PV inflows
cost. This is the same as forcing NPV 0.
15NPV Enter r, solve for NPV.
IRR Enter NPV 0, solve for IRR.
16Whats Franchise Ls IRR?
0
1
2
3
IRR ?
10
80
60
-100.00
PV1
PV2
PV3
0 NPV
Enter CFs in CFLO, then press IRR
IRRL 18.13.
IRRS 23.56.
17Find IRR if CFs are constant
0
1
2
3
IRR ?
40
40
40
-100
INPUTS
3 -100 40 0 9.70
OUTPUT
Or, with CFLO, enter CFs and press IRR 9.70.
18Rationale for the IRR Method
If IRR gt WACC, then the projects rate of return
is greater than its cost-- some return is left
over to boost stockholders returns. Example WAC
C 10, IRR 15. Profitable.
19Decisions on Projects S and L per IRR
- If S and L are independent, accept both. IRRs gt
r 10. - If S and L are mutually exclusive, accept S
because IRRS gt IRRL .
20Construct NPV Profiles
Enter CFs in CFLO and find NPVL and NPVS at
different discount rates
NPVL 50 33 19 7
NPVS 40 29 20 12 5
r 0 5 10 15 20
(4)
21NPV ()
r 0 5 10 15 20
NPVL 50 33 19 7 (4)
NPVS 40 29 20 12 5
Crossover Point 8.7
S
IRRS 23.6
L
Discount Rate ()
IRRL 18.1
22NPV and IRR always lead to the same accept/reject
decision for independent projects
NPV ()
r gt IRR and NPV lt 0. Reject.
IRR gt r and NPV gt 0 Accept.
r ()
IRR
23Mutually Exclusive Projects
NPV
r lt 8.7 NPVLgt NPVS , IRRS gt IRRL CONFLICT
L
r gt 8.7 NPVSgt NPVL , IRRS gt IRRL NO CONFLICT
IRRS
S
r 8.7 r
IRRL
24To Find the Crossover Rate
1. Find cash flow differences between the
projects. See data at beginning of the
case. 2. Enter these differences in CFLO
register, then press IRR. Crossover rate
8.68, rounded to 8.7. 3. Can subtract S from L
or vice versa, but better to have first CF
negative. 4. If profiles dont cross, one project
dominates the other.
25Two Reasons NPV Profiles Cross
1. Size (scale) differences. Smaller project
frees up funds at t 0 for investment. The
higher the opportunity cost, the more valuable
these funds, so high r favors small
projects. 2. Timing differences. Project with
faster payback provides more CF in early years
for reinvestment. If r is high, early CF
especially good, NPVS gt NPVL.
26Reinvestment Rate Assumptions
- NPV assumes reinvest at r (opportunity cost of
capital). - IRR assumes reinvest at IRR.
- Reinvest at opportunity cost, r, is more
realistic, so NPV method is best. NPV should be
used to choose between mutually exclusive
projects.
27Managers like rates--prefer IRR to NPV
comparisons. Can we give them a better IRR?
Yes, MIRR is the discount rate which causes the
PV of a projects terminal value (TV) to equal
the PV of costs. TV is found by compounding
inflows at WACC.
Thus, MIRR assumes cash inflows are reinvested at
WACC.
28MIRR for Franchise L (r 10)
0
1
2
3
10
10.0
80.0
60.0
-100.0
10
66.0 12.1
10
MIRR 16.5
158.1
-100.0
TV inflows
PV outflows
MIRRL 16.5
29To find TV with 10B, enter in CFLO
CF0 0, CF1 10, CF2 60, CF3 80
I 10
NPV 118.78 PV of inflows.
Enter PV -118.78, N 3, I 10, PMT 0. Press
FV 158.10 FV of inflows.
Enter FV 158.10, PV -100, PMT 0, N
3. Press I 16.50 MIRR.
30Why use MIRR versus IRR?
MIRR correctly assumes reinvestment at
opportunity cost WACC. MIRR also avoids the
problem of multiple IRRs. Managers like rate of
return comparisons, and MIRR is better for this
than IRR.
31Normal Cash Flow Project
Cost (negative CF) followed by a series of
positive cash inflows. One change of signs.
Nonnormal Cash Flow Project
Two or more changes of signs. Most common Cost
(negative CF), then string of positive CFs, then
cost to close project. Nuclear power plant, strip
mine.
32Inflow () or Outflow (-) in Year
0
1
2
3
4
5
N
NN
-
N
-
-
NN
-
-
-
N
-
-
-
N
-
-
-
NN
33Pavilion Project NPV and IRR?
0
1
2
r 10
5,000
-5,000
-800
Enter CFs in CFLO, enter I 10.
NPV -386.78
IRR ERROR. Why?
34We got IRR ERROR because there are 2 IRRs.
Nonnormal CFs--two sign changes. Heres a
picture
NPV Profile
NPV
IRR2 400
450
0
r
400
100
IRR1 25
-800
35Logic of Multiple IRRs
1. At very low discount rates, the PV of CF2 is
large negative, so NPV lt 0. 2. At very high
discount rates, the PV of both CF1 and CF2 are
low, so CF0 dominates and again NPV lt 0. 3. In
between, the discount rate hits CF2 harder than
CF1, so NPV gt 0. 4. Result 2 IRRs.
36Could find IRR with calculator 1. Enter CFs as
before. 2. Enter a guess as to IRR by storing
the guess. Try 10 10 STO IRR 25
lower IRR Now guess large IRR, say,
200 200 STO IRR 400 upper IRR
37When there are nonnormal CFs and more than one
IRR, use MIRR
0
1
2
-800,000
5,000,000
-5,000,000
PV outflows _at_ 10 -4,932,231.40.
TV inflows _at_ 10 5,500,000.00.
MIRR 5.6
38Accept Project P?
NO. Reject because MIRR 5.6 lt r 10. Also,
if MIRR lt r, NPV will be negative NPV
-386,777.
39S and L are mutually exclusive and will be
repeated. r 10. Which is better? (000s)
0
1
2
3
4
Project S (100) Project L (100)
60 33.5
60 33.5
33.5
33.5
40 S L CF0 -100,000
-100,000 CF1 60,000 33,500 Nj
2 4 I 10 10 NPV 4,132
6,190
NPVL gt NPVS. But is L better? Cant say yet.
Need to perform common life analysis.
41- Note that Project S could be repeated after 2
years to generate additional profits. - Can use either replacement chain or equivalent
annual annuity analysis to make decision.
42Franchise S with Replication
Replacement Chain Approach (000s)
0
1
2
3
4
Franchise S (100) (100)
60 60
60 (100) (40)
60 60
60 60
NPV 7,547.
43Or, use NPVs
0
1
2
3
4
4,132 3,415 7,547
4,132
10
Compare to Franchise L NPV 6,190.
44If the cost to repeat S in two years rises to
105,000, which is best? (000s)
0
1
2
3
4
Franchise S (100)
60
60 (105) (45)
60
60
NPVS 3,415 lt NPVL 6,190. Now choose L.
45Consider another project with a 3-year life. If
terminated prior to Year 3, the machinery will
have positive salvage value.
Year 0 1 2 3
CF (5,000) 2,100 2,000 1,750
Salvage Value 5,000
3,100 2,000
0
46CFs Under Each Alternative (000s)
0
1
2
3
1.75
1. No termination 2. Terminate 2 years 3.
Terminate 1 year
(5) (5) (5)
2.1 2.1 5.2
2 4
47Assuming a 10 cost of capital, what is the
projects optimal, or economic life?
NPV(no) -123. NPV(2) 215. NPV(1) -273.
48Conclusions
- The project is acceptable only if operated for 2
years. - A projects engineering life does not always
equal its economic life.
49Choosing the Optimal Capital Budget
- Finance theory says to accept all positive NPV
projects. - Two problems can occur when there is not enough
internally generated cash to fund all positive
NPV projects - An increasing marginal cost of capital.
- Capital rationing
50Increasing Marginal Cost of Capital
- Externally raised capital can have large
flotation costs, which increase the cost of
capital. - Investors often perceive large capital budgets as
being risky, which drives up the cost of capital.
(More...)
51- If external funds will be raised, then the NPV of
all projects should be estimated using this
higher marginal cost of capital.
52Capital Rationing
- Capital rationing occurs when a company chooses
not to fund all positive NPV projects. - The company typically sets an upper limit on the
total amount of capital expenditures that it
will make in the upcoming year.
(More...)
53- Reason Companies want to avoid the direct costs
(i.e., flotation costs) and the indirect costs of
issuing new capital. - Solution Increase the cost of capital by enough
to reflect all of these costs, and then accept
all projects that still have a positive NPV with
the higher cost of capital.
(More...)
54- Reason Companies dont have enough managerial,
marketing, or engineering staff to implement all
positive NPV projects. - Solution Use linear programming to maximize NPV
subject to not exceeding the constraints on
staffing.
(More...)
55- Reason Companies believe that the projects
managers forecast unreasonably high cash flow
estimates, so companies filter out the worst
projects by limiting the total amount of projects
that can be accepted. - Solution Implement a post-audit process and tie
the managers compensation to the subsequent
performance of the project.