Description:

high elevation. close to major power lines and roads. 400 feet from known trails ... surface water, and has the required elevation to ensure high wind speeds needed ... – PowerPoint PPT presentation

Number of Views:49
Avg rating:3.0/5.0
Slides: 17
Provided by: this1
Category:

less

Transcript and Presenter's Notes

Title: Location of Wind Power Plant in Vermont


1
Location of Wind Power Plant in Vermont
  • By Meaghan ONeil
  • and James Brady

2
Introduction
  • Many Vermonters are concerned with the protection
    of the natural beauty of their state. 
  • Due to the environmental effects of power
    production an alternative method with a lower
    impact is needed. 
  • One environmentally friendly option is wind
    generated power. 
  • This is a feasible option in Vermont due to the
    high wind speeds in the high elevations of the
    Green Mountains. 

3
Purpose and Scope
  • The purpose of this project was to locate the
    best place for a wind power plant in Vermont. 
  • The scope of this project included all of Vermont
    and was narrowed down to Chittenden County
    because it has the highest population density.
  • We used ArcView software with GIS data
    layers, from www.vcgi.org, to narrow the location
    down. 
  • The data layers chosen were ones that are
    important to the location of a wind power plant. 
  • These layers include
  • major power lines
  • conserved public and private land
  • surface water
  • population density of counties
  • major roads
  • elevation
  • trails
  • housing
  • wetlands
  • rec sites

4
Methodology
  • ArcView software was used to evaluate the layers
    in focus.
  • This software allows the layers to be placed on
    top of each other giving locations where a power
    plant can be placed based on our criteria. 
  • These layers can also be clipped to a certain
    county making finding a location easier. 
  • After the layers are clipped all necessary
    buffers can be added to aid in picking a
    location.
  • The criteria is as follows
  • densely populated county
  • high elevation
  • close to major power lines and roads
  • 400 feet from known trails
  • 750 feet from housing
  • 300 feet from wetlands
  • not on private or public lands
  • not on ski resorts or surface water

5
(No Transcript)
6
(No Transcript)
7
(No Transcript)
8
(No Transcript)
9
(No Transcript)
10
(No Transcript)
11
(No Transcript)
12
Results
  •      After the data was layered, clipped and
    buffered a final location was chosen. 
  • The final location found is Stimson Mountain.

13
(No Transcript)
14
Final location on a contour map
15
Orthophoto of final location
16
Conclusions and Recommendations
  • Stimson is a good location because it does not
    fall under our buffered trails, wetlands, or
    housing. 
  • Also, it is close to major power lines and roads
    this helps cut cost by only having to make short
    access roads for construction and maintenance
    and short power lines to incorporate the plant
    into the existing power system.  
  • Finally, Stimson does not fall below public land,
    private land or surface water, and has the
    required elevation to ensure high wind speeds
    needed to produce power.