ACMA Membership Survey - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

ACMA Membership Survey

Description:

ICRA Management Consulting Services Limited. Hydro Power Projects ..the plus side ... Transmission Constraints may get eased over time ... – PowerPoint PPT presentation

Number of Views:84
Avg rating:3.0/5.0
Slides: 23
Provided by: icr76
Category:

less

Transcript and Presenter's Notes

Title: ACMA Membership Survey


1
Financing Issues in Hydro Power Projects
9th ASSOCHAM Energy Summit August 24, 2006 New
Delhi
Dhruba Purkayastha General Manager
2
Contents Hydro Power Projects
Current Business Models
Financing Issues
3
Hydro Power Projects ..the plus side
  • Non fossil fuel clean power
  • Lowest lifetime cost of power generation
  • Effective tool for load variation management-peak
    loads
  • Socio-economic development of remote areas
  • Energy security
  • No fuel linked inflationary pressures/input price
    risks

4
Policy directions are progressively ushering
competitive power sector market ..
  • EA 2003 introducing
  • Non-discriminatory open access to transmission at
    least
  • ERCs to follow competitive bidding process
  • CERC to advise GoI on promoting competition
  • Controlling abuse of market power
  • Competitive Bidding Guidelines
  • Competitive acquisition of new generation
    capacity
  • National Tariff Policy 2006
  • Promoting retail competition
  • Supporting competitive acquisition of generation
    capacity
  • Enabling choice
  • Supporting distribution reforms

Should work well with hydro projects also
5
However there are some issues with hydro power
projects
  • High capital costs, longer gestation periods
  • Geological risks leading to increase in project
    costs
  • Long delays in obtaining clearances land and R
    R
  • Disputes between states locking up potential
  • Rationalization of tariffs and tariff
    determination mechanisms

6
Typical market analysis for creating generation
assets
  • Current and forecasted demand supply position
  • Merit order situation and likely projections
  • Transmission constraints /corridor availability
  • Credit worthiness of utilities /off-takers
  • Typically would need a state wise analysis

7
Contracting options for hydro power projects
  • Merchant Power Plant
  • Bidding in tariff based competitive bids to be
    floated by Discoms
  • Long term sale of power to Traders
  • Can be a combination of the above options

8
Typical tariff estimation
Free power
Capital Cost
Design Energy
Cost Plus Tariff
Premium
Short Term
Saleable Tariff
Merit Order in Neighboring States
Transmission Cost
Long Term
9
Likely saleable tariffs in some states
  • Most of the long term agreements at lt Rs. 3/ unit
  • Variable Charges lt Rs.2/unit
  • But Merit Order needs to be projected
  • Higher tariffs are unlikely

Note Only Variable charges Transmission
Charges, unit- paise/unit
10
Short terms tariffs may be somewhat higher
  • Since advent of trading, increase in prices
  • 190 p/u to 350 p/u
  • RTC - 350 p/u
  • Peak- 400- 450 p/u

11
Transmission Constraints may get eased over time
  • In next 7 years 27700 MW of Interregional Link
    Capacity addition planned
  • Substantial addition in North West, North- East
    link and North- NE
  • Total Transmission Linkage from Northern Region
    added by 15500 MW
  • But still intra-regional link capacity of
    HP/Uttaranchal/NE with neighboring states need to
    be validated along with the expansion plan

12
1. Merchant Hydro Power Plant Issues
  • Merchant Plant with Long Term reservation of
    Transmission network
  • For Hydro plant utilisation of Transmission
    Network will be very low
  • In case of change in buyer the Transmission
    Network might need to be reserved again
  • Un-viable option
  • Merchant Plant with Short Term reservation of
    Transmission network
  • Sale in short term - peaking season high
    margins
  • Risk of transmission network availability- every
    three months an issue
  • Feasible Option

13
2. Bidding in Tariff Based Competitive Bids
  • Would need to compete with mine linked pit-head
    coal based power plants
  • NE Hydro Plants - How will they compete in a
    scenario where shortfall is in the western ,
    northern and southern region ?
  • Case 1 Standard Bidding Documents still not
    finalized by MoP ?
  • Tariff Structure Single Part or Two Part tariff
  • Hydrological Risk ?
  • Capacity Index / Incentive ?
  • Peak power can be priced at margin

14
3.Long Term Agreement with Traders
  • Traders can either participate in the tariff
    based competitive bidding or can sell power in
    short term
  • While selling in long term / tariff based
    competitive bidding, what value addition a trader
    can provide ?
  • Credit enhancement
  • Bidding assistance
  • Creating liquidity
  • Need for power exchanges effective market
    clearing mechanism

15
Contents Hydro Power Projects
Current Business Models
Financing Issues
16
Key Risks associated with Hydro Power Plants.1
  • Development Phase
  • Non-fulfillment of any of the Conditions
    Precedent
  • Issues in getting Environmental Clearance
  • Difficulties in Land Possession i.e. RR related
    issues
  • Non-Availability of Financing
  • Issues in upfront equity Infusion
  • Lenders issues with capital cost/ construction
    period in financial closure
  • Construction Phase
  • Geological Risks
  • Delay in CoD, shortfall in tested capacity
  • Force Majeure, EPC contractor non-performance
  • Change in law leading to increase in project
    cost

17
Key Risks associated with Hydro Power Plants 2
  • Operation Phase
  • Lower Capacity Index due to Force Majeure
  • Change in Law leading to increase in additional
    OM expenses and additional capital investment
  • Reduction in output of Power Plant
  • Payment Default by procurer
  • Exchange rate fluctuation

18
Typical issues in financing infrastructure
  • Size, tenure and uncertainty
  • High transaction costs
  • Improper risk allocation
  • Need for efficient subsidization (in some
    cases)
  • Lack of supportive legal and regulatory framework

19
Supply side issues in Infrastructure financing
  • Lack of long term funding sources
  • Under developed debt markets
  • Banks unable to prudently lend long term
  • Absence of financial engineering/
    instruments/credit enhancement
  • Securitization
  • Bond insurance
  • Risk guarantees

20
Typical issues in financing infrastructure also
apply mostly to hydro power projects
  • Improper risk allocation- design of
    concessions/PPP
  • Lack of common enabling policy and regulatory
    frame works
  • Lack of proper financial /lending instruments -
    credit enhancement securitization, bond
    insurance
  • Need for private equity .

21
Some questions in hydro power projects remain.
  • Is it feasible to make the plant run as 100
    Merchant Plant ?
  • Regulatory intervention is capital cost
    determination for merchant hydro projects
  • Will there be a regulatory ceiling on the sale
    price, even for selling it on short term ?
  • Feasibility of routing this power through a
    trader /Absence of power exchanges
  • Reserving the transmission network without a
    power purchase agreement/MoUs

22
Thank you
Write a Comment
User Comments (0)
About PowerShow.com