A'Gianolio LISA status 1 - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

A'Gianolio LISA status 1

Description:

December 11-12, 2004. A. Gianolio. LISA Project Manager. Dec. 11-12, 2004 LIST #8. A.Gianolio LISA status - 2. LISA Programme. HQ Report ... – PowerPoint PPT presentation

Number of Views:21
Avg rating:3.0/5.0
Slides: 27
Provided by: csarg
Category:
Tags: lisa | dec | eid | finalised | gianolio | status

less

Transcript and Presenter's Notes

Title: A'Gianolio LISA status 1


1
LISA Status LIST 8 Stanford December 11-12,
2004 A. Gianolio LISA Project Manager
2
HQ Report
3
HQ report
  • The ESA-NASA August agreement was presented to
    the SSAC and to the SPC. Both bodies expressed
    their satisfaction for the achieved framework
    that allows the project formulation to start
  • The LPF project is underway
  • The first meeting of the LPF Steering Committee
    took place at Estec recently.
  • France has expressed its interest in
    participating to the LTP (with the AOM) - and
    consequently to LISA.
  • Details are being finalised and the multilateral
    agreement will be updated to reflect this change

4
HQ report
  • LISA is firmly set in the Cosmic Vision
    programme the authorisation to proceed with the
    MF by SPC, IPC and D-SCI is a clear sign of the
    importance of the mission in ESA
  • The LPF MOU is being worked
  • Work for the update of the LISA LOA will start
    soon
  • ITAR issues are considered very critical
  • all cooperative activities with NASA on LPF (ST7)
    have been suspended until ITAR issues are
    resolved and JPL will be able to deliver
    essential documentation to ESA
  • Cooperative activities on LISA could be
    dramatically reduced or suspended unless ESA can
    have timely access to project documents that are
    indispensible for the implementation of the
    August agreement

5
Project Report
6
ESA-NASA Agreement
  • Following a year of discussion, a programmatic
    agreement for the LISA project has been reached
    between ESA and NASA in August 2004
  • The main elements of the agreement are
  • Project description
  • Project organisation
  • System Engineering functions
  • Mission elements share
  • The Project description defines the general terms
    to be adopted throughout the project

7
Programmatic
  • The project organisation is as follows

8
Programmatic
  • In the structure foreseen for the Mission
    Formulation phase, a Joint Project Management
    Office (JPMO), led by the NASA and the ESA
    project managers, is in charge of the overall
    project
  • The ESA and the NASA project managers share equal
    responsibility in the management of the project
  • The JPMO has to approve, inter alia, the mission
    reference design and the requirements
  • The project will adopt, as far as possible, a
    single set of procedures, documentation and
    reviews

9
Programmatic - SW
  • The agreement for SW includes the following
  • Software algorithms and the corresponding code to
    the level of e.g. MatLab routines will be defined
    and maintained by MSE throughout the mission
    lifetime.
  • Each Agency will independently verify and
    validate all mission software developed by the
    other Agency.
  • Each Agency will exchange models required to
    support design, verification, validation and
    operations with the other Agency.
  • If any of the points above requires specific
    clearances, NASA will promptly start the required
    process.
  • The last point is a continuous matter of concern
    to ESA and recent repeated experiences have shown
    that it could well be a show-stopper for the
    cooperation

10
Programmatic
  • The description of the System Engineering
    functions constitutes a fundamental step forward
    in the cooperation
  • it identifies the functions in Formulation and in
    Implementation
  • it sanctions the principle that the mission
    design has to be done jointly, to the level
    required to clearly define the responsibility of
    each agency
  • It establishes that decisions affecting the
    project cannot be taken unilaterally by one
    Agency
  • The implementing structure foresees three SE
    managers working together to define mission
    requirements and reference architecture, to be
    submitted to the approval of the two project
    managers

11
Share of responsibility
  • The agreement also contains the following share
    of responsibility for deliverables for the
    implementation phase
  • ESA develops the three LISA Opto-mechanical Core
    Systems (LOCS) with contributions from NASA -
    and verifies them individually
  • JPL develops the three LISA Instrument Metrology
    and Avionics Systems (LIMAS) with contributions
    from ESA - integrates them to the three LOCS and
    verifies that they function together as a 3-arm
    interferometer before and after integration onto
    the spacecraft buses.
  • GSFC integrates each LOCS/LIMAS assembly onto a
    spacecraft bus to form a sciencecraft, adds the
    constellation software, verifies that the three
    sciencecraft, individually and together, fulfill
    the performance requirements
  • Procurement of flight micropropulsion elements
    will be decided at a later stage depending on
    technology maturity.

12
Mission Formulation
  • ESA will start an industrial contract for Mission
    Formulation on January 17, 2005
  • The activity will last two years and is divided
    into two phases, lasting respectively 7 and 17
    months
  • The activity is based on the Top Science
    Requirements (Iss.1 - 15 March 2003) and the
    derived MRD
  • Regular Milestones have been set to ensure
    consistent system design and to phase work with
    NASA
  • Each phase is concluded with a review (Mission
    Architecture and Mission Definition Review
    respectively)
  • Additionally, a Mid-term Review will take place
    in the middle of phase 2

13
Mission Formulation
  • Mission Formulation has a different meaning at
    ESA and at NASA and care will have to be
    exercised to avoid confusion

14
(No Transcript)
15
Mission Formulation
  • The MF contract will be lead by Astrium GmbH,
    that will bring their experience on the payload
  • Astrium Ltd. will support for all spacecraft
    system and mission issues
  • Other contractors and consultants will be pulled
    in at a later stage if and as required
  • The contractor primary interface point will be
    the ESA project team
  • The contractor will work in close cooperation
    with the NASA team and will participate to
    meetings, as required.

16
MF tasks
  • Astrium will support ESA in the consolidation of
  • Mission constituents and their interfaces
  • Model philosophy
  • Error budget apportionment and allocation to the
    constituents
  • Risk assessment and risk management plans
  • Mission Requirements in order to allow entering
    the Definition Phase
  • All the other elements required to support
    discussions with NASA on the share of
    responsibility

17
MF Phase 1
  • The objective of this phase is to consolidate the
    LISA mission architecture and design.
  • Main end products will be a complete set of
    draft Specs for the LISA mission elements, the
    DDVP, Budgets, Tech Plan
  • Among others, the following specific points will
    be addressed in phase 1
  • OB re-design and interfaces with IS
  • telescope and structure
  • Telescope pointing system
  • P/L Avionic and I/F with S/C
  • Error budget
  • Constellation acquisition
  • point ahead
  • Critical review and analysis of the S/C and
    Propulsion Module design
  • Mission scenario and Operations

18
MF Phase 2
  • A reference design (mechanical, optical,
    electrical) for the mission elements will be
    produced.
  • Product Tree, IRDs, Functional diagrams, Budgets
    will be consolidated
  • Risk assessment and margin policy will be
    reviewed
  • Environmental constraints will be reviewed
  • Key technology identified and technology plan
    proposed
  • MRD will be finalized and draft requirements
    documents for the mission elements will be
    prepared
  • The requirements verification logic and methods
    will be established

19
MF Short term
  • Short term (3 months scale) activities will
    concentrate on the following major architectural
    issues that have relevance in the definition of a
    set a requirements for the design
  • Use of Telescope/CCD as a Star Tracker
  • Acquisition and attitude control
  • Alignment
  • Point ahead angle
  • Telescope design

20
Data Processing
  • European plan of activities
  • Request Letter of Intent from interested parties.
  • Plan to have algorithm in prototype form at the
    end of 4 yrs period.
  • Need to the define the e2e data processing cycle
    with responsibilities and products at the various
    stages.

21
Data processing
1. Create ad-hoc data processing structure with
ESA chair 2. Define goals, plan of work,
schedule 3. ESA request sci community
LoI 4. Selection of scientists for participation
to data processing structure 5. SPC info paper
6. Mtg with selected parties to define plan of
work and required funding 7. Selected parties to
obtain national funding 8. ESA to place a
contract to study and define the LISA data
processing architecture (March IPC)
22
ST7 - DRS
  • ST7 is currently undergoing a financial
    replanning that may imply some descoping
  • The LPF project is working under the assumption
    of receiving a full ST7-DRS package
  • Modifications of the current agreements are
    considered to have programmatic and scientific
    impact to LPF and LISA
  • It is therefore recommended to maintain the
    current ST7 baseline

23
LISA Logo
24
LPF LTP status
25
LPF status
  • SRR
  • LTP review
  • SRR closeout
  • Project replanning due to revised LTP delivery
  • gt impact on LISA schedule by means of the LPF
    launch-LISA PDR link
  • Industrial team setup - affected by LTP schedule
  • LTP and DRS EID-A revision
  • Several interfaces to DRS need to be finalised
  • DRS compliance to joint ops mode under discussion

26
LTP status
  • Astrium (D) proposal for the LTP Industrial
    Architect due next week
  • Will contain an LTP development plan with
    schedule
  • Astrium (UK) will integrate the LTP plan in to
    the project plan
  • 1st meeting of the Steering Committee at Estec on
    Dec.1
  • Agreed to set up the LPF Science Working Team
Write a Comment
User Comments (0)
About PowerShow.com