Title: A'Gianolio LISA status 1
1LISA Status LIST 8 Stanford December 11-12,
2004 A. Gianolio LISA Project Manager
2HQ Report
3HQ report
- The ESA-NASA August agreement was presented to
the SSAC and to the SPC. Both bodies expressed
their satisfaction for the achieved framework
that allows the project formulation to start - The LPF project is underway
- The first meeting of the LPF Steering Committee
took place at Estec recently. - France has expressed its interest in
participating to the LTP (with the AOM) - and
consequently to LISA. - Details are being finalised and the multilateral
agreement will be updated to reflect this change
4HQ report
- LISA is firmly set in the Cosmic Vision
programme the authorisation to proceed with the
MF by SPC, IPC and D-SCI is a clear sign of the
importance of the mission in ESA - The LPF MOU is being worked
- Work for the update of the LISA LOA will start
soon - ITAR issues are considered very critical
- all cooperative activities with NASA on LPF (ST7)
have been suspended until ITAR issues are
resolved and JPL will be able to deliver
essential documentation to ESA - Cooperative activities on LISA could be
dramatically reduced or suspended unless ESA can
have timely access to project documents that are
indispensible for the implementation of the
August agreement
5Project Report
6ESA-NASA Agreement
- Following a year of discussion, a programmatic
agreement for the LISA project has been reached
between ESA and NASA in August 2004 - The main elements of the agreement are
- Project description
- Project organisation
- System Engineering functions
- Mission elements share
- The Project description defines the general terms
to be adopted throughout the project
7Programmatic
- The project organisation is as follows
8Programmatic
- In the structure foreseen for the Mission
Formulation phase, a Joint Project Management
Office (JPMO), led by the NASA and the ESA
project managers, is in charge of the overall
project - The ESA and the NASA project managers share equal
responsibility in the management of the project - The JPMO has to approve, inter alia, the mission
reference design and the requirements - The project will adopt, as far as possible, a
single set of procedures, documentation and
reviews
9Programmatic - SW
- The agreement for SW includes the following
- Software algorithms and the corresponding code to
the level of e.g. MatLab routines will be defined
and maintained by MSE throughout the mission
lifetime. - Each Agency will independently verify and
validate all mission software developed by the
other Agency. - Each Agency will exchange models required to
support design, verification, validation and
operations with the other Agency. - If any of the points above requires specific
clearances, NASA will promptly start the required
process. - The last point is a continuous matter of concern
to ESA and recent repeated experiences have shown
that it could well be a show-stopper for the
cooperation
10Programmatic
- The description of the System Engineering
functions constitutes a fundamental step forward
in the cooperation - it identifies the functions in Formulation and in
Implementation - it sanctions the principle that the mission
design has to be done jointly, to the level
required to clearly define the responsibility of
each agency - It establishes that decisions affecting the
project cannot be taken unilaterally by one
Agency - The implementing structure foresees three SE
managers working together to define mission
requirements and reference architecture, to be
submitted to the approval of the two project
managers
11Share of responsibility
- The agreement also contains the following share
of responsibility for deliverables for the
implementation phase - ESA develops the three LISA Opto-mechanical Core
Systems (LOCS) with contributions from NASA -
and verifies them individually - JPL develops the three LISA Instrument Metrology
and Avionics Systems (LIMAS) with contributions
from ESA - integrates them to the three LOCS and
verifies that they function together as a 3-arm
interferometer before and after integration onto
the spacecraft buses. - GSFC integrates each LOCS/LIMAS assembly onto a
spacecraft bus to form a sciencecraft, adds the
constellation software, verifies that the three
sciencecraft, individually and together, fulfill
the performance requirements - Procurement of flight micropropulsion elements
will be decided at a later stage depending on
technology maturity.
12Mission Formulation
- ESA will start an industrial contract for Mission
Formulation on January 17, 2005 - The activity will last two years and is divided
into two phases, lasting respectively 7 and 17
months - The activity is based on the Top Science
Requirements (Iss.1 - 15 March 2003) and the
derived MRD - Regular Milestones have been set to ensure
consistent system design and to phase work with
NASA - Each phase is concluded with a review (Mission
Architecture and Mission Definition Review
respectively) - Additionally, a Mid-term Review will take place
in the middle of phase 2
13Mission Formulation
- Mission Formulation has a different meaning at
ESA and at NASA and care will have to be
exercised to avoid confusion
14(No Transcript)
15Mission Formulation
- The MF contract will be lead by Astrium GmbH,
that will bring their experience on the payload - Astrium Ltd. will support for all spacecraft
system and mission issues - Other contractors and consultants will be pulled
in at a later stage if and as required - The contractor primary interface point will be
the ESA project team - The contractor will work in close cooperation
with the NASA team and will participate to
meetings, as required.
16MF tasks
- Astrium will support ESA in the consolidation of
- Mission constituents and their interfaces
- Model philosophy
- Error budget apportionment and allocation to the
constituents - Risk assessment and risk management plans
- Mission Requirements in order to allow entering
the Definition Phase - All the other elements required to support
discussions with NASA on the share of
responsibility
17MF Phase 1
- The objective of this phase is to consolidate the
LISA mission architecture and design. - Main end products will be a complete set of
draft Specs for the LISA mission elements, the
DDVP, Budgets, Tech Plan - Among others, the following specific points will
be addressed in phase 1 - OB re-design and interfaces with IS
- telescope and structure
- Telescope pointing system
- P/L Avionic and I/F with S/C
- Error budget
- Constellation acquisition
- point ahead
- Critical review and analysis of the S/C and
Propulsion Module design - Mission scenario and Operations
18MF Phase 2
- A reference design (mechanical, optical,
electrical) for the mission elements will be
produced. - Product Tree, IRDs, Functional diagrams, Budgets
will be consolidated - Risk assessment and margin policy will be
reviewed - Environmental constraints will be reviewed
- Key technology identified and technology plan
proposed - MRD will be finalized and draft requirements
documents for the mission elements will be
prepared - The requirements verification logic and methods
will be established
19MF Short term
- Short term (3 months scale) activities will
concentrate on the following major architectural
issues that have relevance in the definition of a
set a requirements for the design - Use of Telescope/CCD as a Star Tracker
- Acquisition and attitude control
- Alignment
- Point ahead angle
- Telescope design
20Data Processing
- European plan of activities
- Request Letter of Intent from interested parties.
- Plan to have algorithm in prototype form at the
end of 4 yrs period. - Need to the define the e2e data processing cycle
with responsibilities and products at the various
stages.
21Data processing
1. Create ad-hoc data processing structure with
ESA chair 2. Define goals, plan of work,
schedule 3. ESA request sci community
LoI 4. Selection of scientists for participation
to data processing structure 5. SPC info paper
6. Mtg with selected parties to define plan of
work and required funding 7. Selected parties to
obtain national funding 8. ESA to place a
contract to study and define the LISA data
processing architecture (March IPC)
22ST7 - DRS
- ST7 is currently undergoing a financial
replanning that may imply some descoping - The LPF project is working under the assumption
of receiving a full ST7-DRS package - Modifications of the current agreements are
considered to have programmatic and scientific
impact to LPF and LISA - It is therefore recommended to maintain the
current ST7 baseline
23LISA Logo
24LPF LTP status
25LPF status
- SRR
- LTP review
- SRR closeout
- Project replanning due to revised LTP delivery
- gt impact on LISA schedule by means of the LPF
launch-LISA PDR link - Industrial team setup - affected by LTP schedule
- LTP and DRS EID-A revision
- Several interfaces to DRS need to be finalised
- DRS compliance to joint ops mode under discussion
26LTP status
- Astrium (D) proposal for the LTP Industrial
Architect due next week - Will contain an LTP development plan with
schedule - Astrium (UK) will integrate the LTP plan in to
the project plan - 1st meeting of the Steering Committee at Estec on
Dec.1 - Agreed to set up the LPF Science Working Team