Title: Design of Traction Sand Traps
1Design of Traction Sand Traps
2Traction Sand Traps
Traction Sand Trap
- Description
- Applications and Siting Criteria
- Factors affecting preliminary design
- Workshop exercise
3General Description
Traction Sand Trap
- Device that temporarily detains runoff to allow
traction sand or abrasives to settle out.
4Types of Traction Sand Traps
Traction Sand Trap
- Vault
- An underground concrete structure designed with a
sedimentation chamber and peak flow diversion. - Modified CMP Riser
- An underground vertical CMP that captures
traction sand below the invert of the outlet pipe
(the outlet pipe invert is above the invert of
the vertical CMP)
5Types of Traction Sand Traps (continued)
Traction Sand Trap
- Infiltration Basin Forebay
- See Appendix B (Section B.3 of the PPDG).
Forebays are designed to capture sediment prior
to discharging into the basin. Forebays may be
sized to accommodate additional traction sand
loading. - Detention Basin
- See Appendix B (Section B.4 of the PPDG).
Detention basins may be sized to store additional
traction sand loading. Preferred method of
capturing Traction Sand.
6Vault
Traction Sand Trap
- Below grade structure placed in-line or off-line
in storm drain systems to capture Traction Sand. - Vault has sedimentation chamber to slow flow
velocities and settle sand. - Sites with large traction sand volumes and not
limited by space are most suitable for detention
basins, not vaults.
7Outlet from louvered pipe
8Corrugated Metal Pipe
Traction Sand Trap
- Below grade structure that uses commercially
available corrugated metal pipe (CMP) placed
vertically with an outflow pipe offset from the
invert of the trap to capture sand. - Sites with small traction sand volumes and/or
limited space are most suitable for modified CMP
traps.
9Modified CMP
10Modified Corrugated Metal Pipe
Traction Sand Trap
This is a double-barreled traction sand trap with
asphalt dikes.
11Infiltration Basin Forebay
Traction Sand Trap
- Infiltration basins may be designed with a
sedimentation forebay to settle and store the
anticipated traction sand volume. - Sedimentation forebay is sized to retain the
traction sand volume and the sediment load
associated with site conditions (sediment loads
not associated with winter activities).
12Infiltration Basin Forebay
Traction Sand Trap
13Detention Basin
Traction Sand Trap
- Detention basins may be designed with additional
storage volume for the anticipated traction sand. - Detention basins should be designed per Appendix
B of the PPDG.
14Detention Basin
Traction Sand Trap
15Traction Sand Trap - Siting and Design Criteria
Traction Sand Trap
- Sites where traction sand or abrasives are
commonly ( gt twice per year) applied to the
roadway. - Detention Basins are considered first.
- Consult District NPDES Storm Water Coordinator to
ensure that the BMP is not classified and
regulated as a underground injection well. - Locate device so water is not introduced above
the roadway subgrade in case of blockage.
16Preliminary Design Factors
Traction Sand Trap
- Design for anticipated sand recovery volume.
- Sufficient volume to store the settled sand
through the winter and avoid scour. - Sufficient hydraulic head for gravity flow.
- Inlet and outlet arrangement to minimize short
circuiting of the flow. - Invert depth no greater than 3 meters if cleaned
by vactor trucks.
17Preliminary Design Factors (CMP type)
Traction Sand Trap
- Weep holes to allow proper drainage and prevent
standing water. - Invert of the sand trap 1 to 2 m above
groundwater. - Maintenance space and/or access ramps for large
equipment to clean out traps. - Flow velocities within the trap should be
minimized (0.6 m/s is typically used) to promote
particle settling and prevent scour.
18Preliminary Design Factors (CMP type)
Traction Sand Trap
- If the design storage volume cannot be met with
one sand trap device then additional storage can
be obtained by - adding more traps in-line
- increasing frequency of clean-out
- Using basin or vault-type traction sand trap
- discussing other options with District
Maintenance and Storm Water Coordinator.
19Sand Volume (All types)
PPDG Page B-21
- V (S)(R)(L)(E)/F
- Where
- V Total volume of traction sand that must be
stored (m3). - S Estimated volume of sand applied (m3/yr).
- R Reduction factor to account for sand
recovered by roadway sweeping. - L Factor to account for other miscellaneous
losses/accumulations. - E Estimated recovery efficiency.
- F Number of times the trap will be cleaned
(times/yr).
20Estimating the Volume of Traction Sand
PPDG Page B-21
- S Estimate of the volume of sand applied
(m3/yr) - Typical application rates range from 47
m3/lane/km/yr for area with average application
rates to 95 m3/lane/km/yr for areas with high
application rates. - Consult District Maintenance.
21Estimating Volume
PPDG Page B-21
- Factors that may affect traction sand application
volume may include - Exposure Roadways on north facing slopes
generally require more traction sand than similar
south facing slopes. The surrounding vegetation
may also significantly affect exposure. - Roadway grade Steeper grades generally receive
more traction sand. - Other sources of similar material Adjacent cut
slopes and other non-paved tributary areas may
contribute similar-sized sediment or other debris
that will be retained in the trap.
22Estimating Volume
PPDG Page B-22
- R Reduction factor to account for sand removed
by roadway sweeping. - Estimate a value between 1.0 (no roadway
sweeping) and 0.6 (aggressive winter roadway
sweeping). - Consult with Maintenance.
23Estimating Volume
PPDG Page B-22
- L Factor to account for other miscellaneous
losses or accumulations. - Accounts for sand that has been carried into or
out of the tributary area by various means such
as wind, snow clearing equipment, or tracking by
vehicles. - Estimate an appropriate value in the range of 0.8
(high losses from known sources such as snow
blowers) to 1.2 (high accumulation from known
sources). - Use a factor of 1.0 for no losses/accumulations.
24Estimating Volume
PPDG Page B-22
- E Estimated recovery efficiency
- Accounts for traction sand that passes through
the sand trap without settling out. - Not all the sand can be recovered because of
particle size limitations, settling
inefficiencies, turbulent flow conditions, and
other factors. - Until empirical information is obtained from
pilot studies, a value of 1.0 should be used.
25Estimating Volume
PPDG Page B-22
- F Number of times trap will be cleaned per
year. - Typically F 1.0, as most basins are cleaned
once per year (normally in the summer). - If obtaining the required storage volume is
difficult, it may be possible to implement
mid-season cleaning. - Consult District Maintenance staff to make sure
mid-season cleaning is practicable and feasible. - Mid-winter cleaning will also likely affect trap
design - Maintenance equipment must access the trap under
wet or snowy conditions. - Cleaning equipment and trap manhole covers or
lids must be operable during cold conditions.
26(No Transcript)
27(No Transcript)
28Exercise 1
Traction Sand Trap
- Given
- Lies on a north-facing slope
- No records of sand application amounts available
- Heavy snow area (Sand applied gt 15 times/year)
- Moderately steep slopes
- Two-lane highway
- Snow is plowed towards cut slope
- Is part of an aggressive roadway sweeping program
- Treatment area length of 0.4 km
- Assume detention and infiltration basins are not
feasible
29Exercise 1
Traction Sand Trap
- Find
- Estimate the total volume of traction sand
applied (S). - Determine the total volume of traction sand that
should be stored (V). - Which sand trap type is most appropriate to store
the traction sand volume? - Determine total volume of traction sand to be
stored (V) if snow blowers were used?
30Traction Sand Trap
Exercise 1 (Solution)
- Estimate the amount of sand applied
- North facing slope, moderate roadway slopes, and
greater than 15 applications per year should
yield an high application rate 95
m3/lane/km/yr. - Two-lane highway, therefore annual load estimate
(S) 2 lanes x 95 m3/lane/km/yr 190 m3/km/yr. - The sand trap will treat 0.4 kilometers of
roadway, therefore the annual volume applied is
190 m3/km/yr x 0.4 km S 76 m3/yr.
31Traction Sand Trap
Exercise 1 (Solution)
- The site is aggressively swept throughout the
winter, therefore a reduction factor (R) 0.6
should be applied. - Snow plows push snow to the inside shoulder which
accumulates traction sand as well as side slope
sediment. The total volume estimate should then
increase due to the additional sediment load (L
1.2) - Use recovery efficiency (E) 1.0
- Assume trap is cleaned once a year (F 1.0)
32Traction Sand Trap
Exercise 1 (Solution)
- The equation for calculating the volume of
traction sand storage is - V (S)(R)(L)(E)/F
- V (76)(0.6)(1.2)(1.0)/1 54.7 m3
- Design Sand Trap for 55 m 3
33Traction Sand Trap
Exercise 1 (Solution)
- Which traction sand trap is most appropriate to
store 55 cubic meters of sand? - Calculate the volume of one 900 mm CMP riser
inlet with a 450 mm outlet pipe
Total available depth (assume there is minimal
distance from inlet to crown of the outflow
pipe) (3 m - 0.15 m - 0.45 m) 2.4 m available
depth Area of the 914 mm pipe (0.914m/2)2 x P
0.66 m2 Volume of one CMP riser 0.66 m2 x
2.4 m 1.6 m3 Number of 914 mm CMP risers
needed for traction sand storage 55 m3 /1.6 m3
34.4 or 35 risers in-line
3m
34Traction Sand Trap
Exercise 1 (Solution)
- Find size of sediment chamber within a vault
- Assume a depth of 2.5 m (Note maximum 3.0 m)
- Assume a width of 2 m
- Required vault length volume / (Width x Depth)
55/(2.5 x 2) 11 m - Length may exceed site constraints, therefore
increase the width to 3 m - Required vault length 55/(2.5x3) 7.33 m
- A detention basin or vault-type traction sand
trap is most appropriate for this site due to the
excessive number of CMP risers needed for
sediment storage
35Traction Sand Trap
Exercise 1 (Solution)
- If the maintenance crews used snow blowers then
the L factor would decrease from 1.2 to 0.8. - The new traction sand volume is
- V (SxRxLxE)/F (76x0.6x0.8x1.0)/1.0 36.5 m3
or 37 m3
36Questions