Albert Park Secondary College Remediation - PowerPoint PPT Presentation

1 / 13
About This Presentation
Title:

Albert Park Secondary College Remediation

Description:

Golder Associates Pty Ltd. Site History 1880s to 1900s ... Spent oxide (cyanide and sulphate) Groundwater. Cyanide, Ammonia, Naphthalene. Remediation Plan ... – PowerPoint PPT presentation

Number of Views:25
Avg rating:3.0/5.0
Slides: 14
Provided by: admi1065
Category:

less

Transcript and Presenter's Notes

Title: Albert Park Secondary College Remediation


1
Albert Park Secondary College Remediation
Public Meeting 20 November 2008
Ian Kluckow Golder Associates Pty Ltd
2
Site History 1880s to 1900s
Albert Park Secondary College
3
Site History 1900s to 1964
Albert Park Secondary College
4
Site History 1900s to 1964
Gasworks Park
Southport NH
Albert Park Secondary College
5
Site History 1964 to 2008
Albert Park Secondary College
6
Soil and Groundwater Sampling
Albert Park Secondary College
7
Contamination
  • Gasworks Byproducts in Soil
  • Coke/ash (Polycyclic aromatic hydrocarbons)
  • Spent oxide (cyanide and sulphate)
  • Groundwater
  • Cyanide, Ammonia, Naphthalene

8
Remediation Plan
  • Remediation Strategy (RAP)
  • Excavate unsuitable soil
  • Treat (onsite or offsite) or dispose offsite
  • Backfill
  • Install separation layer
  • Confirm site suitable through an Environmental
    Audit
  • Environmental Auditor Ken Mival is here tonight
  • Remediation Management
  • Environmental Management Plan
  • Enforced by EPA

9
Site Remediation
  • Department invited major soil treatment companies
    to tender for the works
  • Tender was awarded to Enviropacific Services
  • John Lucas from EPS here tonight
  • Remediation Technology
  • Excavation of soil
  • Batch Thermal Desorption to treat soil
  • Reuse onsite or offsite disposal of soil
  • Remediation commenced November 2008
  • Majority of excavation to occur by April 2009
  • Treatment to commence December 2008

10
Remediation System
Batch Thermal Desorption
11
Environmental Management Plan
  • EMP sets out objectives, targets, monitoring
    and reporting and covers
  • Air Quality Odour/Vapours/Dust
  • Erosion and Water Quality
  • Noise and Vibration
  • Groundwater
  • Contaminated Soils
  • Waste Management
  • Traffic Management
  • Complaints management and community information
  • Contractor must comply with all Victorian
    environmental laws
  • The CEMP and treatment technology has been
    approved EPA.
  • CEMP requirements will be regulated/enforced by
    EPA under a statutory Notice

12
Community Information and Complaints
  • Community Information
  • An information Board will be set up at the site
  • Further community information during remediation
  • Complaints Management
  • EnviroPacific Services Pty Ltd (Contractor),
  • Mitchell Anthony (03) 9686 7137
  • (Mitchell is here tonight)
  • OR
  • EPA Victorias Pollution Watch Line
  • 9695-2777 (24 hours) or
  • www.epa.vic.gov.au

13
  • Questions?
Write a Comment
User Comments (0)
About PowerShow.com