Title: E4014 Construction Surveying
1E4014 Construction Surveying
2Road Construction
- Consists of a number of sequential steps
- clearing
- earthworks
- drainage works
- pavement construction
- road furniture
3Road Construction - Clearing
- When
- occurs prior to commencement of earthworks
- Where
- 1.5metres outside road formation
- How
- remove all trees and other vegetation
4Road Construction - Clearing
- Surveyors Role
- mark limits of road formation
- batter points 1.5metres
- stakes with flagging or flag trees
- use plans and tables
5Road Construction - Clearing
- Existing Survey Control
- baseline survey marks and offsets
- permanent marks bench marks
- Accuracy of Setout
- probably 0.5metre horizontal
6Road Construction - Drainage
- When
- before major earthworks
- keep construction site dry
- after major earthworks
- to keep subgrade dry
7Road Construction - DrainageSurface Drains
- Where
- catch drains
- catch surface water flow over adjacent natural
surface and divert it into the drainage system - 2metres from edge of cutting
- maybe construct bank rather than cut surface
drains
- When
- before major earthworks
8Road Construction - DrainageSurface Drains
- Where
- Table Drains
- collect surface water draining off the road
pavement - wide and deep enough to collect and hold all
surface water - deep enough to intercept any subsoil moisture
close to the surface - discharge onto natural surface or into culverts
every 100 metres
- When
- after major earthworks - before subgrade
construction
9Road Construction - DrainageSurface Drains
- Where
- Levy Drains
- used on hills to collect run-off from pavement
area and direct it into flumes which carry the
water down the embankment - prevents scouring of the batters in fill
- When
- before and after major earthworks
10Road Construction - DrainageSurface Drains
- Where
- kerb Gutter
- urban form of table drain
- also used in rural road cuttings
- normally constructed by an extrusion machine
- When
- after major earthworks and pavement construction
11Road Construction - DrainageSubsoil Drains
- Where
- constructed to prevent damage by underground
water from - water seeping down through the pavement
- water rising in springs
- water flowing downhill in the upper soil layers
- control is achieved by
- intercepting ground water before it reaches the
roadway - lowering the water table by providing outlets for
reservoirs surrounded by impervious barriers - subsoil pipes are usually located
- in the shoulder between the pavement and the
table drain - under the edge of pavement
12Road Construction - DrainageSubsoil Drains
- Where
- Culverts
- carry water from one side of the road formation
to the other - pre-cast concrete pipes, pre-cast concrete boxes,
insitu concrete boxes, corrugated steel pipes and
arches - When
- after construction of sub-grade, before placing
the sub-base
13Road Construction - Earthworks
- Proper construction involves
- clearing
- stripping of topsoil
- drainage of swampy areas
- removal of poor materials
- compaction of natural surfaces
- benching of steep slopes
- spreading and compaction of fill materials
14Road Construction - EarthworksPreparation of Site
- clear all timber
- utilities
- re-location of existing utilities
- conduits for future utilities will save cost and
damage to road formation at a later time
15Road Construction - EarthworksPreparation of Site
- access through the site for current traffic
- away from construction site
- in rugged country locate the side-track in the
position of the final catch drain on the up-hill
side of cuttings
16Road Construction - EarthworksPreparation of Site
- Removal of topsoil
- valuable commodity to be conserved for later
landscaping - wasted in fills and destroyed by having fills
placed over it - removal of top soil ensures firmer foundation of
fills - stockpiled in heaps of less than 1 metre in
height - if buried for long periods fertility is lossed
17Road Construction - EarthworksPreparation of Site
- earthworks operation comprises the following
operations - formation of cutting by excavating through the
high ground - formation of embankments by filling over the low
ground - shaping the ground or finished surface to true
formation levels - excavation for drainage works
18Road Construction - EarthworksPreparation of Site
- earthworks operation will involve
- excavating or loosening natural material
- loading the material into haulage units
- transporting the material from cuttings or borrow
pits to fill sites - dumping the material
- compacting the material
19Road Construction - EarthworksPreparation of Site
- Cut Fills
- often the largest task in road works
- often the most costly operation in terms of total
sums of money involved - speed and efficiency depends largely on the
quantity and types of earthmoving plant available - initial plant selection for a site will effect
the its overall progress
20Road Construction - EarthworksPreparation of Site
- Cut Fills, cont
- in most materials except rock the factor
governing the speed of work is likely to be
transporting of the material and not the
excavation itself - capacity of the haulage system must equal the
maximum digging output - it follows that the haul should be kept as short
as possible
21Road Construction - EarthworksPreparation of Site
- Cuttings
- Through Cuts
- may be through a small hill or over the top of a
large hill to lower the grade of a road - prior to construction the material type must be
identified and the angle of repose estimated - Side Hill Cuts
- part of the road in cut and part in fill
- enables balancing of earthworks
- embankment portion tends to move downhill, better
to be full cut
22Road Construction - EarthworksPreparation of Site
- Sequence of operations in CUT
- excavate to reach formation level or to remove
alll unsuitable material - transport away from site the undesirable soils
- organic top soil, heavy highly plastic
water-logged clays, loose sand - haul suitable material from cuts to fill areas
23Road Construction - EarthworksPreparation of Site
- Fills
- eventual aim of all fill work is to position the
the subgrade underlying the pavement layers in
the right location and at the correct level and
to provide drainage to maintain its condition
24Road Construction - EarthworksPreparation of Site
- Removal of material too weak to support fill
- highly organic clays, saturated clays in swamps,
silt and mud - compact the natural surface of fill sites by
rolling
25Road Construction - EarthworksPreparation of Site
- Fills
- material should be obtained from as near to the
embankment site as possible - material should be stable, high bearing strength
and a free draining nature - sand gravel mix, sand clay mix and sand silt mix
are suitable fill materials when correctly placed
26Road Construction - EarthworksPreparation of Site
- Sequence of operations in FILL
- drain water from hollows and holes, dispose of
sludge before filling is begun - spread the fill material into horizontal layers
not more than 250mm deep - thoroughly compact these layers to maximum density
27Road Construction Bases and Sub-Bases
- After the earthworks and compaction of fills,
subgrade is brought up the correct formation and
trimmed
28Road Construction - Bases and Sub-Bases
- Road Pavement
- sub-base layer, maybe
- stronger than the underlying subgrade
- base course layer
- stronger than the sub-base
- surface course
- stronger than the base course
- wheel loads which are most intense near the
surface are taken by materials which are able to
accept the load without significant deformation
29Road Construction - Bases and Sub-Bases
- Base Course
- Rigid
- cement concrete with or without the addition of a
separate wearing course - used in roads effected by flooding or subjected
to heavy traffic loads
30Road Construction - Bases and Sub-Bases
- Base Course, cont
- Flexible bases
- natural materials which deflect slightly under
loads - common in Qld are soil aggregate, crushed rock
and uncrushed stone - level control required as the material is placed
in layers deep enough to ensure required
compaction can be achieved - if tests have not been done on the material the
loose layer should be placed 25 thicker than the
desired final compacted layer