Title: Project Manager
1Project Managers Report
- David Britton 4/July/2005
2Outline
- Project Maps
- Resources
- People and Roles
- Tier-1 Hardware
3GridPP2 ProjectMap
4Metrics
- 84 are currently satisfied the 14 below are not
- 0.104 Number of LCG/EGEE job slots published by
the UK. - 0.105 Number of LCG/EGEE jobs slots used.
- 0.106 GridPP KSI2K available.
- 0.108 GridPP disk storage available
- 0.111 GridPP tape storage made available to
LCG/EGEE. - 0.112 Fraction of available KSI2K used in
quarter. - 0.113 Fraction of available disk used in
quarter. - 0.114 Fraction of available Tape used in
quarter. - 0.131 Tier-1 service disaster recovery plans up
to date. - 0.143 Accumulated scheduled downtime in the last
quarter. - 3.6.3 LCG Deployment evaluation reports.
- 5.2.4. Tier-2 Hardware realization.
- 5.2.7 Quarterly reports received within 1 month
of the end of the quarter. - 6.2.11 Non-HEP applications tested on the GridPP
Grid.
Shortage of Hardware (wrt planning) This
reflects the slower than planned ramp-up of
resources at the institutes. Tier-2 Report
suggests this is recovering. Low usage of
resources Mitigates the above. Tier-1 Report
shows 2004 56 CPU 48 Disk. 2005 42 CPU
64 Disk.
5Milestones
A total of 262 milestones defined 54 (21) have
been completed in the first 20 of the project.
There are 4 milestones shown as overdue 0.37
Full Tier-1 Team in place. 0.53 Accounting
package deployed and R-GMA configured at GridPP
sites. 2.4.1 Security GridPP GACL parsing and
policy. 2.4.11 Security Integration of VOMS
interface to GridSite lightweight groups.
Advertisements being prepared for last two posts.
Done at 70 of sites (metric requires 90).
In fact these are done.
6Change Forms
Five change forms have been enacted during this
period as follows Ganga deliverable 3.2.1 and
3.2.2 have each been delayed by four
months. PhenoGrid deliverable 3.5.7 has been
delayed by 6 months. Interoperability milestones
6.2.1 and 6.2.2 have been delayed to Oct/05 and
Jan/06 respectively
7Risk Register
Seven high risks identified
R10-LCG and R10-Apps External middleware
dependence.
R22-LCG, R22-Apps, R22-PRO Hardware resources
inadequate.
R32-PRO Security inadequate to operate Grid.
R40-Apps Lack of future funding.
8Outline
- Project Maps
- Resources
- People and Roles
- Tier-1 Hardware
9GridPP2 Financial Summary
Total includes 273,988 carried forward from
GridPP1. Funds are fully allocated.
0.5m
10GridPP2 Post Summary
Note-1 Only short ½ FTE of effort at
present. Note-2 Advertisements under preparation.
11GridPP2 Effort Summary
12Outline
- Project Maps
- Resources
- People and Roles
- Tier-1 Hardware
13People and Roles
14Outline
- Project Maps
- Resources
- People and Roles
- Tier-1 Hardware
15Tier-1 Hardware
- Some work needs to be done updating v26b
described at GridPP12 - Provisional 20 increase in Hardware budget needs
to be added - ADS planning is currently being re-done with
better input. - Delay of 2005 hardware purchase needs to be
included.
16Conclusions
- GridPP2 is 20 complete.
- Need to limit our ambition and focus on what is
essential (as oppose to what would be nice).
or When neither a carrot or a stick will work