Title: Project Manager


1
Project Managers Report
  • David Britton 4/July/2005

2
Outline
  1. Project Maps
  2. Resources
  3. People and Roles
  4. Tier-1 Hardware

3
GridPP2 ProjectMap
4
Metrics
  • 84 are currently satisfied the 14 below are not
  • 0.104 Number of LCG/EGEE job slots published by
    the UK.
  • 0.105 Number of LCG/EGEE jobs slots used.
  • 0.106 GridPP KSI2K available.
  • 0.108 GridPP disk storage available
  • 0.111 GridPP tape storage made available to
    LCG/EGEE.
  • 0.112 Fraction of available KSI2K used in
    quarter.
  • 0.113 Fraction of available disk used in
    quarter.
  • 0.114 Fraction of available Tape used in
    quarter.
  • 0.131 Tier-1 service disaster recovery plans up
    to date.
  • 0.143 Accumulated scheduled downtime in the last
    quarter.
  • 3.6.3 LCG Deployment evaluation reports.
  • 5.2.4. Tier-2 Hardware realization.
  • 5.2.7 Quarterly reports received within 1 month
    of the end of the quarter.
  • 6.2.11 Non-HEP applications tested on the GridPP
    Grid.

Shortage of Hardware (wrt planning) This
reflects the slower than planned ramp-up of
resources at the institutes. Tier-2 Report
suggests this is recovering. Low usage of
resources Mitigates the above. Tier-1 Report
shows 2004 56 CPU 48 Disk. 2005 42 CPU
64 Disk.
5
Milestones
A total of 262 milestones defined 54 (21) have
been completed in the first 20 of the project.
There are 4 milestones shown as overdue 0.37
Full Tier-1 Team in place. 0.53 Accounting
package deployed and R-GMA configured at GridPP
sites. 2.4.1 Security GridPP GACL parsing and
policy. 2.4.11 Security Integration of VOMS
interface to GridSite lightweight groups.
Advertisements being prepared for last two posts.
Done at 70 of sites (metric requires 90).
In fact these are done.
6
Change Forms
Five change forms have been enacted during this
period as follows Ganga deliverable 3.2.1 and
3.2.2 have each been delayed by four
months. PhenoGrid deliverable 3.5.7 has been
delayed by 6 months. Interoperability milestones
6.2.1 and 6.2.2 have been delayed to Oct/05 and
Jan/06 respectively
7
Risk Register
Seven high risks identified
R10-LCG and R10-Apps External middleware
dependence.
R22-LCG, R22-Apps, R22-PRO Hardware resources
inadequate.
R32-PRO Security inadequate to operate Grid.
R40-Apps Lack of future funding.
8
Outline
  1. Project Maps
  2. Resources
  3. People and Roles
  4. Tier-1 Hardware

9
GridPP2 Financial Summary
Total includes 273,988 carried forward from
GridPP1. Funds are fully allocated.
0.5m
10
GridPP2 Post Summary
Note-1 Only short ½ FTE of effort at
present. Note-2 Advertisements under preparation.
11
GridPP2 Effort Summary
12
Outline
  1. Project Maps
  2. Resources
  3. People and Roles
  4. Tier-1 Hardware

13
People and Roles
14
Outline
  1. Project Maps
  2. Resources
  3. People and Roles
  4. Tier-1 Hardware

15
Tier-1 Hardware
  • Some work needs to be done updating v26b
    described at GridPP12
  • Provisional 20 increase in Hardware budget needs
    to be added
  • ADS planning is currently being re-done with
    better input.
  • Delay of 2005 hardware purchase needs to be
    included.

16
Conclusions
  • GridPP2 is 20 complete.
  • Need to limit our ambition and focus on what is
    essential (as oppose to what would be nice).

or When neither a carrot or a stick will work