Title: Claiborne Lock and Dam Fish Passage Project


1
Locks are Key to Fish Migration on Alabama River
Lewis Sumner Mobile District Paul Freeman The
Nature Conservancy
2
Background
  • Fish Passage a concern at large dams worldwide
  • Mobile District has studied various ways to allow
    fish passage

3
Background
  • On Chattahoochee R. some success achieved through
    use of lockages and attraction flows
  • Because of past success, TNC and others expressed
    interest in similar project on Alabama R. dams
    and locks.

4
Claiborne Lock and Dam
5
Millers Ferry Lock and Dam
6
Alabama RiverKey Migratory Fish Species
  • paddlefish
  • blue sucker
  • southern walleye
  • Alabama shad
  • Gulf sturgeon
  • Alabama sturgeon
  • striped bass
  • alligator gar
  • striped mullet
  • blacktail river redhorses
  • mooneye
  • American eel
  • blue catfish
  • Atlantic needlefish
  • skipjack herring
  • freshwater drum

7
Lock schedule at Claiborne (April 1 May 31)
  • 10 a.m. open lower gates for 6 hours
  • 4 p.m. open upper gates for 6 hours
  • 10 p.m. open lower gates for 6 hours
  • 4 a.m. open upper gates for 6 hours

8
Lock schedule at Millers Ferry(April 1 May 31)
  • 6 a.m. open lower gates for 4 hours
  • 10 a.m. open upper gates for 4 hours
  • 6 p.m. open lower gates for 4 hours
  • 10 p.m. open upper gates for 4 hours

9
Lockage Results at Claiborne
  • 61 Calendar days available April 1-May 31
  • Lockages occurred on 20 days
  • First lockage April 13
  • Last lockage May 7

10
Lockage Results at Claiborne
  • 85 Total lockages occurred
  • 12 lockages for vessels
  • 73 Total lockages for specifically for fish
    passage
  • Without fish lockages there would have been only
    6 days with lockages and 12 total lockages

11
Lockage Results at Millers Ferry
  • 61 Total days
  • Lockages occurred on 58 days
  • First lockage April 3
  • Last lockage May 31

12
Lockage Results at Millers Ferry
  • 378 Total lockages occurred
  • 57 Lockages for vessels
  • 321 Lockages specifically for fish passage
  • Without fish lockages there would have been only
    27 days with lockages and 57 total lockages

13
Fish Sampling
14
Electro Fishing
15
Paddle Fish caught
16
Tag implantation
17
Tagged Fish release
18
Fish Tracking
19
Opening upper lock gate
20
Acknowledgements
  • Auburn University
  • Geological Survey of Alabama
  • Alabama DCNR
  • U.S. Fish and Wildlife Service
  • The Nature Conservancy
  • U.S. Army Corps of Engineers