Title: Fibre to the Node Overview
1(No Transcript)
2Fibre to the NodeOverview
December 2008 Mark Ratcliffe
3Overview
- The FTTN Programme
- Progress so far
- Our customers
- Impact of the STD
- Our team today
4What FTTN means for NZers
- World class connectivity
- Step change in services and capability
- Overcome the tyranny of distance
- Platform for increased productivity growth
5Network Performance after FTTN
- Early post-cabinet indicators
- 12Mbps attainable speed (average depending on
performance factors) - Broadband in the area increases by average 34
(noting that initial cabinets are in lowest
penetration areas) - In Pt Chevalier, broadband connections in some
cabinets have increased by up to 200 - Some work still required on the Data source
Actual
Attainable
Data source 5530 network analyser
6The FTTN Programme scale
- To roll out the FTTN programme Chorus will
- Invest 500m
- Once we ramp up, install one cabinet every 40min
until the end of 2011 - Lay 2500km of new fibre
- Cut and reconnect about 4 million copper cable
pairs - Employ or contract 500 full time workers
- Before installing each cabinet we
- Work with the local council to identify each site
- Consult the affected local resident
- Letter drop the neighbourhood
- Present to community interest groups
7The FTTN Programme complexity
8FTTN Dashboard
Delivery of Determinations Undertakings
Delivery of Cabinet Rollout
Customers Migrated
Delivery of RMA Requirements
History - Financial Year 08/09
- Service Company invoicing did occur as expected
project under spent
9Rollout
10North Shore - July 2008
KEY Blue where broadband speeds are improving
for customers during each phase of the project
11North Shore - October 2011
12Our customer focus
- Its our job to meet customer needs
- The commercial aspects of the sub-loop project
have been run parallel with the regulatory
process, and a commercial trial will commence in
December. - Consultation
- Cabinet design
- TCF and the development of the STP
- Chorus forecasting of cabinetisation
13Our customer focus cont.
- We recognise our customers face a challenge
- Sub-loop services cost more than UCLL
- Our customers have to sell the extra value to
end-users - Retail markets and products must be developed
- However loading all the risk onto Chorus is not
the answer (as discussed below, the business case
must stack up) - Across the network our customers have options
UCLL, Sub loop, SLES, BUBA and EUBA
14Impact of draft STD operational
- Risk of delay
- Departures from what was agreed at the TCF and
built into our planning risk derailing our
project management. - Risk of gold plating
- The TCF made a number of decisions aimed at
designing a Sub-loop service that is practically
useful. - The draft STD introduces unwanted complexity and
cost for Chorus and ultimately our customers.
15Impact of draft STD economics
- The draft STD under-prices Sub-loop services.
- It also raises our costs. For example
- Complicated market share and allocation process
- Special purpose database
- Regulating backhaul as dark fibre converts
backhaul transmission into a lower value, lower
revenue access service.
16Impact of STD economics cont.
- Chorus is committed to rolling out fibre past the
Milestones, if possible. No stone unturned. - The draft STD will change our business case.
- Chorus must act as a stand alone business.
- As things stand in the draft STD, we will need
to - Go back to the Telecom board and report that the
FTTN Milestones are uncommercial - Revisit our ability to go further than the FTTN
Milestones - We need the economics to stack up.
17Finalising the STD
- Chorus submits the Commission should refer back
to some key principles - Investment incentives should be preserved
- Industry agreements should be supported
- The realistic needs of our customers should be
met - Consistency with previous STD decisions is
important - Chorus must act in its commercial interests,
taking a long term view - And bear in mind the very real risks of delay and
gold plating
18This conference
- Chorus committed to assisting the Commission
- Happy to take questions
- Chris Dyhrberg to introduce our team