Fibre to the Node Overview - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Fibre to the Node Overview

Description:

12Mbps attainable speed (average depending on performance factors) ... In Pt Chevalier, broadband connections in some cabinets have increased by up to 200 ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 19
Provided by: T10851
Category:

less

Transcript and Presenter's Notes

Title: Fibre to the Node Overview


1
(No Transcript)
2
Fibre to the NodeOverview
December 2008 Mark Ratcliffe
3
Overview
  • The FTTN Programme
  • Progress so far
  • Our customers
  • Impact of the STD
  • Our team today

4
What FTTN means for NZers
  • World class connectivity
  • Step change in services and capability
  • Overcome the tyranny of distance
  • Platform for increased productivity growth

5
Network Performance after FTTN
  • Early post-cabinet indicators
  • 12Mbps attainable speed (average depending on
    performance factors)
  • Broadband in the area increases by average 34
    (noting that initial cabinets are in lowest
    penetration areas)
  • In Pt Chevalier, broadband connections in some
    cabinets have increased by up to 200
  • Some work still required on the Data source

Actual
Attainable
Data source 5530 network analyser
6
The FTTN Programme scale
  • To roll out the FTTN programme Chorus will
  • Invest 500m
  • Once we ramp up, install one cabinet every 40min
    until the end of 2011
  • Lay 2500km of new fibre
  • Cut and reconnect about 4 million copper cable
    pairs
  • Employ or contract 500 full time workers
  • Before installing each cabinet we
  • Work with the local council to identify each site
  • Consult the affected local resident
  • Letter drop the neighbourhood
  • Present to community interest groups

7
The FTTN Programme complexity
8
FTTN Dashboard
Delivery of Determinations Undertakings
Delivery of Cabinet Rollout
Customers Migrated
Delivery of RMA Requirements
History - Financial Year 08/09
  • Service Company invoicing did occur as expected
    project under spent

9
Rollout
10
North Shore - July 2008
KEY Blue where broadband speeds are improving
for customers during each phase of the project
11
North Shore - October 2011
12
Our customer focus
  • Its our job to meet customer needs
  • The commercial aspects of the sub-loop project
    have been run parallel with the regulatory
    process, and a commercial trial will commence in
    December.
  • Consultation
  • Cabinet design
  • TCF and the development of the STP
  • Chorus forecasting of cabinetisation

13
Our customer focus cont.
  • We recognise our customers face a challenge
  • Sub-loop services cost more than UCLL
  • Our customers have to sell the extra value to
    end-users
  • Retail markets and products must be developed
  • However loading all the risk onto Chorus is not
    the answer (as discussed below, the business case
    must stack up)
  • Across the network our customers have options
    UCLL, Sub loop, SLES, BUBA and EUBA

14
Impact of draft STD operational
  • Risk of delay
  • Departures from what was agreed at the TCF and
    built into our planning risk derailing our
    project management.
  • Risk of gold plating
  • The TCF made a number of decisions aimed at
    designing a Sub-loop service that is practically
    useful.
  • The draft STD introduces unwanted complexity and
    cost for Chorus and ultimately our customers.

15
Impact of draft STD economics
  • The draft STD under-prices Sub-loop services.
  • It also raises our costs. For example
  • Complicated market share and allocation process
  • Special purpose database
  • Regulating backhaul as dark fibre converts
    backhaul transmission into a lower value, lower
    revenue access service.

16
Impact of STD economics cont.
  • Chorus is committed to rolling out fibre past the
    Milestones, if possible. No stone unturned.
  • The draft STD will change our business case.
  • Chorus must act as a stand alone business.
  • As things stand in the draft STD, we will need
    to
  • Go back to the Telecom board and report that the
    FTTN Milestones are uncommercial
  • Revisit our ability to go further than the FTTN
    Milestones
  • We need the economics to stack up.

17
Finalising the STD
  • Chorus submits the Commission should refer back
    to some key principles
  • Investment incentives should be preserved
  • Industry agreements should be supported
  • The realistic needs of our customers should be
    met
  • Consistency with previous STD decisions is
    important
  • Chorus must act in its commercial interests,
    taking a long term view
  • And bear in mind the very real risks of delay and
    gold plating

18
This conference
  • Chorus committed to assisting the Commission
  • Happy to take questions
  • Chris Dyhrberg to introduce our team
Write a Comment
User Comments (0)
About PowerShow.com