1Integrated Reservoir and Production Management
- Raghu Kulkarni
- Roxar Production Management
-
2Outline
- What is Integrated Reservoir and Production
Management (IRPM) - Huldra Field
- IRPM Future
3Reservoir Management
Reservoir Loop (months-years)
Reservoir Characterization
Development Planning Execution (includes
economic)
Production Loop (days-weeks)
Identify KPI
Production Monitoring
Update OP
Review PLP and RLP
Reservoir Monitoring
KPI Key Performance Index PLP Production Loop
Performance RLP Reservoir Loop Performance OP
Operating Plan
4Reservoir Characterization
Seismic
Structural Info
Well Logs
Geological Model
Production Data
Simulation Model
Simulation
History Match
To Development Planning
5Development Planning
From Reservoir Characterization
6Production Loop Analysis
7Production Loop Data Activity
8The Huldra Case
9Huldra Development
- Will be developed as a NNM well-head platform
with a first stage separator, liquids to
Veslefrikk and gas to Heimdal - All wells will be equipped with multiphase meter
and sand monitoring system - All wells will have downhole PT gauges
- Choke positions will be remotely monitored
10Huldra Data Acquisition
- Measurements
- Bottom-hole Pressures Temperature
- WellHead Pressure Temperature
- Meter FlowRates
- Meter Pressure and Temperature
- Sand Production
- Choke Positions
- Automatic Import
- PROSTY allocated rates
- Manual Import
- Eclipse Simulation
- PVT Tables
- Vertical Lift Tables
Data will be available real-time using DACQUS to
Huldra asset team in Bergen (or anywhere else
and partner offices)
11Huldra IRPM Suite
- Huldra IRPM suite consists of following modules
- DACQUS
- Data Acquisition (time series)
- Visualization
- Mathematical Operations on time series
- Qtotal Q1 Q2 ...Q6
- BHP VLPLookUp(THP,Qo,Wct,Gor)
- Time shifting to compare transients from a common
time datum - Sand production indicators, hydrate formation
indicators - Basic Engineering Analysis
- WellTest
- Analysis of transient data
- History of well multirate tests
- GAP Link (VBA script running GAP from Petroleum
Experts) - Field optimization software
12Gap-link
13IRPM
Manual
14Future
15IRPM Work Process
Data Acquisition And History
Optimization
Constraints
Set Points
16IRPM Challenges
- Technology should apply to dumb as well as
smart fields - Easy common interface
- Ability to connect to different optimization
tools