Title: Ten Year Plan To End Chronic Homelessness
1Ten Year Plan To End Chronic Homelessness
- Conclusions of the
- Financial Analysis
- Presented to the Policy Board to End Homelessness
on January 14th, 2008
2Ad Hoc Funding Committee
- Appointed by ICEH to analyze financial needs,
resources and gaps in fulfilling the Ten Year
Plan - Meetings October-December of 2007
3Some Assumptions in the Financial Analysis
- Fulfilling the Plan Will Require 1600 Units of
PSH - 25 (400) will be Units Through Leasing and 75
(1200) will be Units Through Development - All Needs and Sources are projected over Ten
Years 2007-2017
4Financial Elements of the Ten Year Plan
5Conclusions of the Financial Analysis
- Excel charts are
- available upon request
6Conclusions Rental Subsidies
- If Samaritan Bonus continues to be available,
projected sources will meet our target of 400
Units Through Leasing
7Conclusions Operating Subsidies
- Of the 1200 units of developed PSH, about 495
operating subsidies will come from Mental Health,
Samaritan Bonus and other sources, leaving a need
for about 705 PROJECT BASED SECTION 8 VOUCHERS.
8Conclusions Treatment Services
- Treatment (medical, mental health, and
addictions) will be available for all clients
through The Efforts new FQHC status as well as
MHSA, Drug MediCal, and hospital-funded frequent
user initiatives
9Conclusions Case Management (CM)
- Our biggest and
- most important gap!
- Leased Housing Programs
- Immediate
- Long Term
- Developed Housing Projects
- Current Pipeline
- Long Term
10Case Management Gaps Leased Housing Programs
- A. Immediate Problem
- Three Current Programs 2007-2009 totaling 104
Units (shared housing) - CM funded at 1,500-2,800 per client per year by
the Federal Government - 4,500 per client per year needed for success
- Gap 243,000 annually Â
11Case Management Gaps Leased Housing Programs
- B. Long Term CM Gap
- Projected Programs 20102017 totaling
- 141 Units (scattered site)
- McKinney programs where CM will be underfunded
(3,000 vs. 6,000 need) - Gap is about 90,000 per year cumulative to
544,000Â
12 Management Gaps Developed Housing Projects
- A. Current Pipeline 2008-2010
- 275 Units _at_ 7 projects
- Case Management Resources are
- Mostly Identified
13Case Management Gaps Developed Housing Projects
- B. Long Term Pipeline 2010-2017
- Total 925 Units
- 230 Units to be supported by Mental Health
- 695 Units for which CM resources are not
identified - Gap is about 350,000 per year cumulative to 2.5
million
14Role of Case Manager in Permanent Supportive
Housing
- Help residents identify and achieve goals
through - linkages to services and entitlements
- building daily living skills
- managing crises
- medication management
- building community living skills
- supporting recovery
15Conclusions Other Financial Needs/Gaps
- Central Intake
- Starving existing McKinney funded homeless
programs - Evaluation
16Ten Year Plan
17Recommendations
- Recommendations from the Interagency Council
- A. Project Based Section 8
- The ICEH recommends to the Policy Board that
they recommend that the Housing Authority
prioritize the opportunity to Project Based
Section 8 contracts for permanent supportive
housing. - B. Case Management
- Identify Sustained Income Streams
- C. Adequately Fund Central Intake
18Next Steps for thePolicy Board?