Title: Adv' LIGO Seismic Isolation SEI Plans, Schedule, Costs, Team
1Adv. LIGO Seismic Isolation (SEI)Plans,
Schedule, Costs, Team
- Schedule
- through RD, including near-term plans
- project phase
- Costs for project phase (proposed)
- Team -- list of people and places
2Adv. LIGO Seismic Isolation (SEI)Schedule
RD/Design Phase
- Technology Demonstrator and Controls Development
Testbed - Approx. full scale, HAM-like unit installed in
the Stanford University Engineering Test Facility
(ETF) vacuum system - Verify kinematics dynamics of design (?
completed) - Further the servo-control development begun on
the proof-of-concept, two-stage system (currently
in process) - Expect initial phase of servo-controls
development in support of the LASTI prototypes by
4thQ 2004
3Adv. LIGO Seismic Isolation (SEI)Schedule
RD/Design Phase
- Pathfinder Prototypes part of Preliminary
Design - Full scale, HAM and BSC units (1 each) for the
LASTI integrated test system - External Pre-Isolation (EPI) stages
- Already in place at LASTI on a HAM and a BSC
chamber ? - One unit must be reworked once a technology
decision is made (electro-magnetic vs hydraulic
actuation) decision Jun2003 - RFP (tender) for 2 phase structural design
issued Apr2003 ? - Proposals are being evaluated now ?
- Source selection for phase 1 (value engineering)
in Jun2003 likely 3 awards - Source selection for phase 2 (design
fabrication) in Sep2003 -- likely 2 awards - Hiatus during LASTI SEI subsystem testing before
production phase (phase 3)
4Adv. LIGO Seismic Isolation (SEI)Schedule
RD/Design Phase
- Preliminary Design Review (PDR) held Apr 2005
- After assembly and installation experience at
LASTI - Follows 5 months of Pathfinder stand-alone
prototype testing at LASTI - Production and procurement of long lead items
initiated after PDR - Final Design Review (FDR) held Nov 2005
- After integrated SUS/SEI testing (test for
coupled dynamics/interaction)
5Adv. LIGO Seismic Isolation (SEI)Schedule
Project Phase
- WBS 4.02.4 SEI Fabrication
- 4.02.4.1 Fabrication/Procurement
- 4.02.4.2 Assembly
- 4.02.4.3 Alignment, Calibration and Test
- Total duration is 42 months for 30 units
- WBS 4.02.4.1 Fabrication/Procurement
- Scope includes
- procurement of commercial off the shelf
components, e.g. sensors, processors, racks,
crates, etc. - contract fabrication of custom equipment, e.g.
UHV actuators, structure, etc. - In-house fabrication of custom conditioning
electronics - Assembly
- Start of Jun2005 enabled by completion of LASTI
HAM BSC SEI prototype test completion, plus
test and design review - Estimated total duration is 29 months, of which
structural fabrication is 24 months - Recent structural fabrication incumbent bidder
estimated 23 months total required for the
production phase - First interferometer set of hardware ready for
assembly 13 months after start, or Jul2006
6Adv. LIGO Seismic Isolation (SEI)Schedule
Project Phase
- WBS 4.02.4.2 Assembly
- WBS 4.02.4.3 Alignment, Calibration and Test
- Scope includes
- Receipt/acceptance of materials/components and
sub-assembliees (assembled structure,
sensor/actuator pod structures, sensors,
actuators, in-vacuum cabling, etc.) - Clean room assembly of SEI systems (HAM and BSC
chamber versions) by LIGO Lab at LLO - Alignment of sensors, actuators, flexures
balancing calibration of actuation sensing - Functional testing
- Starts Jul2006, when first sets of hardware are
received - First interferometer set (5 BSC units and 5 HAM
units) completed by Jul2007 (12 months) - Next 2 interferometer sets (10 BSC units and 10
HAM units) completed Feb2009 (20 months)
7Adv. LIGO Seismic Isolation (SEI)Schedule
ETC.
8Adv. LIGO Seismic Isolation (SEI)Summary Schedule
N.B Primavera detailed schedule is summarized in
top, gray bars Systems group proposed revision
(M020121-E2) is lower, blue bars
9Adv. LIGO Seismic Isolation (SEI)Costs
- All costs are in base year dollars (un-escalated)
- Production cost 37,952K including 26
contingency - Proposed construction cost 37,952K 1.7 x
667K direct labor incl. Indirect 36,819 - Labor costs are borne by LIGO operations funds
- Average hardware cost 36,819/30 units
1,227K each chamber
10Adv. LIGO Seismic Isolation (SEI)Costs
98.6
11Adv. LIGO Seismic Isolation (SEI)Costs
- In-chamber mechanical fabrication 50.3
- Instruments 19.5
- Electronics 14.7
- Mechanics 11.8
- Assembly, align, calibrate, test 3.1
- Controls 1.8
12Adv. LIGO Seismic Isolation (SEI)Costs
- 3 Interferometers (IFOs) x 6,363K 19,089K for
in-chamber Mechanical Fab Contracts
13Adv. LIGO Seismic Isolation (SEI)In-Chamber
Mechanical Fab. Costs
- In-chamber mechanical fabrication contract unit
costs are based on an analysis of the actual ETF
technology demonstrator costs (LIGO-M030024-02)
Should have used 436K for HAM production unit
cost in the cost book rather than the estimated
ETF production unit cost of 429K
14Adv. LIGO Seismic Isolation (SEI)Instrument Costs
- Sensing and actuation topology in relation to the
two in-chamber, isolation stages - Sensors
- Low noise, capacitive displacement sensors (6
between stages, 12 total) - Seismometers, L4-C (6/stage 1)
- Broadband Seismometer, STS-2 (3/stage 1)
- Seismometer, GS-13 (3/stage 2)
- Electro-magnetic Actuators
- High force between stages 0 and 1, BEI Kimko
LA50-62-004Z - low force between stages 0 and 1, BEI Kimko
LA18-32-006Z - Need ultra-high vacuum (UHV) compatible versions
should be covered by 26 contingency
15SEI Instrument Costs
16SEI Instrument Costs
- Interferometer 1 (IFO1 or LLO) will already have
an external pre-isolation (EPI or stage 0) system
installed - Instrument costs 2,273K
- IFO2 and IFO3 (LHO) also require instrumentation
for the EPI systems - Seismometers, L4-C, 8 total/chamber
- Load Cells, 8 total/chamber
- Inductive position sensors, Kaman DIT-5200, 8
total/chamber - Instrument costs 2,558K for each of IFO2 and
IFO3 - Total instrument costs 2,273K 2 x 2,558
7,389K
17SEI Electronics Costs
- Electronics module counts are based on a
conceptual system block diagram employing initial
LIGO elements and anticipated processing
requirements for the digital control - IFO1 will already have installed EPI (stage 0)
systems IFO2 and IFO3 will not (just as in the
case of the instrumentation) - Total electronics costs 1,513K IFO1 2,039K
IFO2 2,021K IFO3 5,573K
18SEI Electronics Costs
19SEI Electronics Costs
BOE continues
20Adv. LIGO Seismic Isolation (SEI)Team
- LIGO Lab manages the effort and carries the
financial responsibility for all project phase
costs - Leader Larry Jones (LIGO Lab, acting)
- Cognizant Engineer Larry Jones (LIGO Lab)
- Cognizant Scientist Joe Giaime (LSU)
- Cognizant Scientist for EPI Brian Lantz
(Stanford) - Other Key Participants
- Stanford Dan DeBra, Amit Ganguli, Corwin
Hardham, Wensheng Hua, Brian Lantz, Joe van
Niekerk, Norna Robertson - LSU Joe Giaime, Shyang Wen,
- LIGO Lab Rich Abbott, Dennis Coyne, Marcel
Hammond, Jonathan Kern, Katie Lilienkamp, Ken
Mailand, Ken Mason, Richard Mittleman, Samir
Nayfeh, David Ottaway, Kyle Ryan , Lei Zuo