Adv' LIGO Seismic Isolation SEI Plans, Schedule, Costs, Team - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

Adv' LIGO Seismic Isolation SEI Plans, Schedule, Costs, Team

Description:

through R&D, including near-term plans. project phase. Costs for project ... One unit must be reworked once a technology decision is made (electro-magnetic ... – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 21
Provided by: LIGO
Category:

less

Transcript and Presenter's Notes

Title: Adv' LIGO Seismic Isolation SEI Plans, Schedule, Costs, Team


1
Adv. LIGO Seismic Isolation (SEI)Plans,
Schedule, Costs, Team
  • Schedule
  • through RD, including near-term plans
  • project phase
  • Costs  for project phase (proposed)
  • Team -- list of people and places

2
Adv. LIGO Seismic Isolation (SEI)Schedule
RD/Design Phase
  • Technology Demonstrator and Controls Development
    Testbed
  • Approx. full scale, HAM-like unit installed in
    the Stanford University Engineering Test Facility
    (ETF) vacuum system
  • Verify kinematics dynamics of design (?
    completed)
  • Further the servo-control development begun on
    the proof-of-concept, two-stage system (currently
    in process)
  • Expect initial phase of servo-controls
    development in support of the LASTI prototypes by
    4thQ 2004

3
Adv. LIGO Seismic Isolation (SEI)Schedule
RD/Design Phase
  • Pathfinder Prototypes part of Preliminary
    Design
  • Full scale, HAM and BSC units (1 each) for the
    LASTI integrated test system
  • External Pre-Isolation (EPI) stages
  • Already in place at LASTI on a HAM and a BSC
    chamber ?
  • One unit must be reworked once a technology
    decision is made (electro-magnetic vs hydraulic
    actuation) decision Jun2003
  • RFP (tender) for 2 phase structural design
    issued Apr2003 ?
  • Proposals are being evaluated now ?
  • Source selection for phase 1 (value engineering)
    in Jun2003 likely 3 awards
  • Source selection for phase 2 (design
    fabrication) in Sep2003 -- likely 2 awards
  • Hiatus during LASTI SEI subsystem testing before
    production phase (phase 3)

4
Adv. LIGO Seismic Isolation (SEI)Schedule
RD/Design Phase
  • Preliminary Design Review (PDR) held Apr 2005
  • After assembly and installation experience at
    LASTI
  • Follows 5 months of Pathfinder stand-alone
    prototype testing at LASTI
  • Production and procurement of long lead items
    initiated after PDR
  • Final Design Review (FDR) held Nov 2005
  • After integrated SUS/SEI testing (test for
    coupled dynamics/interaction)

5
Adv. LIGO Seismic Isolation (SEI)Schedule
Project Phase
  • WBS 4.02.4 SEI Fabrication
  • 4.02.4.1 Fabrication/Procurement
  • 4.02.4.2 Assembly
  • 4.02.4.3 Alignment, Calibration and Test
  • Total duration is 42 months for 30 units
  • WBS 4.02.4.1 Fabrication/Procurement
  • Scope includes
  • procurement of commercial off the shelf
    components, e.g. sensors, processors, racks,
    crates, etc.
  • contract fabrication of custom equipment, e.g.
    UHV actuators, structure, etc.
  • In-house fabrication of custom conditioning
    electronics
  • Assembly
  • Start of Jun2005 enabled by completion of LASTI
    HAM BSC SEI prototype test completion, plus
    test and design review
  • Estimated total duration is 29 months, of which
    structural fabrication is 24 months
  • Recent structural fabrication incumbent bidder
    estimated 23 months total required for the
    production phase
  • First interferometer set of hardware ready for
    assembly 13 months after start, or Jul2006

6
Adv. LIGO Seismic Isolation (SEI)Schedule
Project Phase
  • WBS 4.02.4.2 Assembly
  • WBS 4.02.4.3 Alignment, Calibration and Test
  • Scope includes
  • Receipt/acceptance of materials/components and
    sub-assembliees (assembled structure,
    sensor/actuator pod structures, sensors,
    actuators, in-vacuum cabling, etc.)
  • Clean room assembly of SEI systems (HAM and BSC
    chamber versions) by LIGO Lab at LLO
  • Alignment of sensors, actuators, flexures
    balancing calibration of actuation sensing
  • Functional testing
  • Starts Jul2006, when first sets of hardware are
    received
  • First interferometer set (5 BSC units and 5 HAM
    units) completed by Jul2007 (12 months)
  • Next 2 interferometer sets (10 BSC units and 10
    HAM units) completed Feb2009 (20 months)

7
Adv. LIGO Seismic Isolation (SEI)Schedule
ETC.
8
Adv. LIGO Seismic Isolation (SEI)Summary Schedule
N.B Primavera detailed schedule is summarized in
top, gray bars Systems group proposed revision
(M020121-E2) is lower, blue bars
9
Adv. LIGO Seismic Isolation (SEI)Costs
  • All costs are in base year dollars (un-escalated)
  • Production cost 37,952K including 26
    contingency
  • Proposed construction cost 37,952K 1.7 x
    667K direct labor incl. Indirect 36,819
  • Labor costs are borne by LIGO operations funds
  • Average hardware cost 36,819/30 units
    1,227K each chamber

10
Adv. LIGO Seismic Isolation (SEI)Costs
98.6
11
Adv. LIGO Seismic Isolation (SEI)Costs
  • In-chamber mechanical fabrication 50.3
  • Instruments 19.5
  • Electronics 14.7
  • Mechanics 11.8
  • Assembly, align, calibrate, test 3.1
  • Controls 1.8

12
Adv. LIGO Seismic Isolation (SEI)Costs
  • 3 Interferometers (IFOs) x 6,363K 19,089K for
    in-chamber Mechanical Fab Contracts

13
Adv. LIGO Seismic Isolation (SEI)In-Chamber
Mechanical Fab. Costs
  • In-chamber mechanical fabrication contract unit
    costs are based on an analysis of the actual ETF
    technology demonstrator costs (LIGO-M030024-02)


Should have used 436K for HAM production unit
cost in the cost book rather than the estimated
ETF production unit cost of 429K
14
Adv. LIGO Seismic Isolation (SEI)Instrument Costs
  • Sensing and actuation topology in relation to the
    two in-chamber, isolation stages
  • Sensors
  • Low noise, capacitive displacement sensors (6
    between stages, 12 total)
  • Seismometers, L4-C (6/stage 1)
  • Broadband Seismometer, STS-2 (3/stage 1)
  • Seismometer, GS-13 (3/stage 2)
  • Electro-magnetic Actuators
  • High force between stages 0 and 1, BEI Kimko
    LA50-62-004Z
  • low force between stages 0 and 1, BEI Kimko
    LA18-32-006Z
  • Need ultra-high vacuum (UHV) compatible versions
    should be covered by 26 contingency

15
SEI Instrument Costs
16
SEI Instrument Costs
  • Interferometer 1 (IFO1 or LLO) will already have
    an external pre-isolation (EPI or stage 0) system
    installed
  • Instrument costs 2,273K
  • IFO2 and IFO3 (LHO) also require instrumentation
    for the EPI systems
  • Seismometers, L4-C, 8 total/chamber
  • Load Cells, 8 total/chamber
  • Inductive position sensors, Kaman DIT-5200, 8
    total/chamber
  • Instrument costs 2,558K for each of IFO2 and
    IFO3
  • Total instrument costs 2,273K 2 x 2,558
    7,389K

17
SEI Electronics Costs
  • Electronics module counts are based on a
    conceptual system block diagram employing initial
    LIGO elements and anticipated processing
    requirements for the digital control
  • IFO1 will already have installed EPI (stage 0)
    systems IFO2 and IFO3 will not (just as in the
    case of the instrumentation)
  • Total electronics costs 1,513K IFO1 2,039K
    IFO2 2,021K IFO3 5,573K

18
SEI Electronics Costs
19
SEI Electronics Costs
BOE continues
20
Adv. LIGO Seismic Isolation (SEI)Team
  • LIGO Lab manages the effort and carries the
    financial responsibility for all project phase
    costs
  • Leader Larry Jones (LIGO Lab, acting)
  • Cognizant Engineer Larry Jones (LIGO Lab)
  • Cognizant Scientist Joe Giaime (LSU)
  • Cognizant Scientist for EPI Brian Lantz
    (Stanford)
  • Other Key Participants
  • Stanford Dan DeBra, Amit Ganguli, Corwin
    Hardham, Wensheng Hua, Brian Lantz, Joe van
    Niekerk, Norna Robertson
  • LSU Joe Giaime, Shyang Wen,
  • LIGO Lab Rich Abbott, Dennis Coyne, Marcel
    Hammond, Jonathan Kern, Katie Lilienkamp, Ken
    Mailand, Ken Mason, Richard Mittleman, Samir
    Nayfeh, David Ottaway, Kyle Ryan , Lei Zuo