Title: Diapositive 1
1Probe beam status and schedule
- choice of architecture
- 1 photo-injector
- 3 LIL sections 1 for compression and 2 for
acceleration - 1 beamline with diagnostics (leading to 2-beam
teststand)
January 2006
C A L I F E S
2RF gun status
R. Roux July, 7th 2006
- Drawings, overview
- What is under way?
- Open questions, ask for info
- Problems, risks
31. Overview
- Studies finished
- Drawings finished
- List of components
- - gun with a measurement loop
- - 2 tapered waveguides
- - 2 LIL flanges
- - 2 solenoids
- - 1 steerer
- - vacuum chamber (tubes, valve, bellow)
- - 2 gauges
- - 1 ionic pump
- - 1 pneumatic valve
- - 1 translation trolley for the preparation
- chamber (additional request from CERN)
- - NEG coating on the vacuum chamber
- (agreed with CERN people)
RF input
photocathode
steerer
valve
solenoids
vacuum pump
42. Whats under way?
- Gun new supplier, the coupler cell should arrive
between 17th-21th July - if everything OK, order the rest of the gun,
all pieces in September - then, RF measurements, mechanical adjustments
and brazing at LAL - (thanks to Eric Chevallay for the 316LN
stainless steel, we will soon refunded) - Magnetism coils and steerer are ordered, should
arrive in the beginning of September - power supplies will be bought by CERN (offer of
R. Losito) - Vacuum gauges and valve are received, ionic pump
at the end of July - power supply will be bought by CERN (offer
of R. Losito) - Mechanics vacuum chamber and supports are under
construction in LAL workshop - it should be finished in September but
risks of overlap with PHIN gun - machining ? PHIN gun has the
priority !
53. Open questions, ask for info
- Girder if we can reuse the LIL 2300 mm girder,
we need the drawings - open question RF gun assembly on girder at
LAL or at CERN ?
- Cabling Who does the cabling between the
photo-injector and the racks? - -cables for solenoids and steerer (electric and
cooling) - -cable for RF loop
- -cables for gauges and power supply
- -on which side of the linac set the connectors
of the solenoids?
- Possible overlap between the solenoid connectors
and RF network pumps? - (happened on PHIN, solenoids sent back to the
supplier to modify connectors)
- Cooling tuning cooling loop from frozen water
(20C) - the gun will be mechanically deformed in such a
way that - the right tuning frequency achieved at ? 30C
63. Problems, risks
- New supplier for the gun, if not good ? delay
- Money 70 k received this year not enough
to order the power supplies and gun cooling loop
I hope to get the totality of the required
budget next year in March
But up to now, RF gun construction proceeds well
7Laser system
- Signal taken from the Drive Beam Laser
- 2 main distinct tasks
- extraction manipulation of laser beam
(windowing, x4 frequency multiplication, doubling
of the pulse frequency 1.5 ? 3 GHz) - transport of the laser beam over 80 m as far as
the photo-cathode - Subcontractor LILM (Laser Matter Interaction
Lab) from CEA-Saclay - Study of the 2 tasks till the end of 2006
- mechanical design and realization follow-up by
Dapnia - Pb delay of the DB laser ? 1st tests with real
laser will be very late
8Time-schedule
9Beam dynamics
calculations nearly complete ...
- single bunch is fine
- multibunch operationdue to beam-loading, bunch
charge should be linearly reduced to meet energy
phase requirements (1 and 1deg)Qb lt 5nC/N - still to be done
- effect of laser spot misalignment
- estimation of the emittance measurement accuracy
10Time-schedule
11Califes Drawings
Drawings nearly complete ...
12Injection beamline
BPM
screen
LIL section input
vacuum pump
laser table
laser beam
injector (LAL Orsay)
13inter-section
steerer
BPM
14diagnostics beamline
total length (cathode plane to output valve)
21.316 m
screen
RF deflector
QL3 Triplet
Dipole
Dump
vac. pump
15RF system
klystron, RF pulse compression, RF network
supplied by CERN Modulator includes a high
voltage pulsed power supply with negative
polarity three electromagnet power supplies a
filament heater power supply an ion pump power
supply a hydraulic network a X-ray
shielding a control-command system some racks
containing the materiel offers from vendors
received on 1st of July realization time 12-14
months vendor choice at end of July
16RF network
defined in March 2006
1 power phase-shifter has to be developed (fine
tuning of thecompression section)
17Phase-shifter
3 GHz scaling from a SLAC model at 11.4 GHz by
Alexej Grudiev sliding circular guide mode
converter
tolerances and mechanical studymade at
Saclay fabrication will start end of
september power tests at CERN
18Time-schedule
19Vacuum
Vacuum system defined 2 LIL sections tested under
vacuum at Cern
primary pumping group
- 3 valves
- 6 ion pumps for LIL sections
- 2 ion pumps for input and output beamlines
- power supplies, gauges
hardware provided by CERN
20Magnets
QL3
BHZ36
steerer HV solenoids earth field correction quadrupoles dipole
5 2 x 17 3 x 2 3 1
order before August CERN provision CERN provision call for tender (5) before August CERN provision
delivery Nov 2006 - - delivery May 2007 -
21Power supplies requirements
of power supplies type Intensity (A) Voltage (V)
Steerers 12 Bipolar 10 5
Solenoids 2 Unipolar 120 20
Quadrupoles 3 Unipolar 200 10
Dipole 1 Unipolar with degauss capability 100 20
Earth field compensation 2 Unipolar 5 3
Specifications of Power supplies have been done
and conveyed to CERN
22Time-schedule
23Diagnostics
Measure Requirements Requirements chosen solutions
Current Resolution 1 Precision 3 Bandwidth gt 250 MHz Single shot, non destructive BPM (after calibration)
Position Resolution 20µm Precision 100µm Bandwidth gt50 MHz Range 10 mm Single shot, non destructive BPM Screen CCD camera
Profile Resolution 20µm Range 10x10mm Screen CCD camera
Emittance Error lt 20 Quad scan Screen CCD camera
Central energy Resolution DP/P 1 Precision 2 Bandwidth gt250 MHz Single shot 15 bending magnet BPM
Energy spread Resolution DP/P0.5 Time resolution is desirable 15 bending magnet Screen CCD camera possible future ...Streak Camera, segmented photomultiplier, segmented beam dump for time resolution
Bunchlength Resolution 0.5ps rms Variation of bunch length along the train Deflecting cavity Screen CCD camera possible future ... RF pick-up (30-174 GHz) during operations
24BPM
- Specifications single bunch multi-bunch
operation (1-64 _at_ 3 GHz) 0.5 nC - coaxial reentrant cavity, original design from
R. Bossard (CERN) - proposed and developed for TTF (M. Luong, C.
Simon - DAPNIA)
prototype for technology validation
OK pre-serie (2 units) under fabrication
25Beam profile monitors
- 3 profiler systems to different
locationsinjector output, behind the triplet,
behind the dipole - 2 main sub-systems
- the vacuum tank with devices (screen, actuator,
viewport, lighting) - the optics system (lenses, CCD camera, filter
wheel, shielding)
Tank study has started ...
Screen holder
Insertion mecanism
26Optics system
TTF2
CTF3
SOLEIL
optics design (various magnifications) CCD
camera (with Cern MTV interface) ? examples of
optics design with different levels of
integration Califes will start next September
27Time-schedule
28Beam Dump
- Derived from SOLEIL(100 MeV, 0.5 to 8 nC, 3 Hz)
- Adaptation for CALIFES in progress (200 MeV, 1.5
A, 21 ns, 5 Hz)
29CLEX building
CALIFES should fit into CLEX building ...
- the last dipole could include 3 branches
- straight to 2-beam teststand
- 15 to Beam Dump
- 30 to Instrumentation Test Beam
30Time-schedule
31Questions List
Can we have a closed area for Califes ? Which
girders can we re-use from CERN ? Who does the
cabling between the Califes components and the
racks ? Alignment studied by Michel Fontaine
from Dapnia who is the CERN contact person ?
32Cooling needs