Duct Sealing and Testing for HVAC System Change-outs - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Duct Sealing and Testing for HVAC System Change-outs

Description:

If you have determined that your Residential or NonResidential ... Duct Testing Equipment. The Energy Conservatory. 612 827-1117. www.energyconservatory.com ... – PowerPoint PPT presentation

Number of Views:70
Avg rating:3.0/5.0
Slides: 24
Provided by: douglas83
Category:

less

Transcript and Presenter's Notes

Title: Duct Sealing and Testing for HVAC System Change-outs


1
Duct Sealing and Testing forHVAC System
Change-outs
  • Procedures to Comply with Change-out Rules

2
(No Transcript)
3
(No Transcript)
4
What Do I Do Now
  • If you have determined that your Residential or
    NonResidential HVAC System Change-out requires
    duct sealing and testing follow these steps.

5
Complete Your Work
  • Complete your work as you would any other job.

6
Contractor Test Seal
  • Test and seal the ductwork as necessary.
  • Contractor does not have to be certified to
    perform this test.

7
Contractor Test Seal (cont)
  • The sealing and testing does not have to be
    performed at the same time as the change-out
    work.
  • It must be completed before the building permit
    is signed-off.

8
Contractor Test Seal (cont)
  • Contractor may hire another firm to test or seal
    but contractor is still responsible.
  • HERS raters have test equipment and can perform
    tests for contractor
  • HERS rater may not be hired to seal system.

9
CF-6R
  • After the system is sealed, form CF-6R is
    completed showing results of contractor tests.

10
(No Transcript)
11
HERS Rater
  • Contractor facilitates the hiring of a HERS rater
    to verify test results.
  • HERS rater must review CF-6R for each job prior
    to performing their verification.

12
Independent Third Party
  • The HERS rater may NOT be an employee of the
    installing HVAC contractor.
  • HVAC contractors may be HERS raters, but they may
    NOT test their own work.

13
CF-4R
  • The HERS rater will perform a duct leakage test
    and fill out form CF-4R.

14
(No Transcript)
15
Building Department
  • The building department must receive a properly
    completed CF-4R prior to signing-off the
    building permit.

16
Sampling
  • At the option of the HVAC contractor
  • The HERS rater will verify 100 of the jobs or
  • The HERS rater will verify a sample of the jobs.

17
Sampling Rules
  • Out of each SEVEN jobs that the contractor does,
    the HERS rater will test ONE job.

18
Sampling Rules
  • The jobs do not have to be in the same
    jurisdiction (city or county).
  • They have to be verified by the same HERS rater.

19
CF-4R For Every Job
  • The HERS Rater will complete a CF-4R for each
    house.
  • This includes tested and sampled houses.
  • Thus, the building department will get a CF-4R
    for every job.

20
HERS Providers
  • Two HERS Providers in California
  • 1. CHEERS www.CHEERS.org
  • 2. CalCerts www.CalCerts.com

21
(No Transcript)
22
List of raters
23
Duct Testing Equipment
  • The Energy Conservatory
  • 612 827-1117
  • www.energyconservatory.com
Write a Comment
User Comments (0)
About PowerShow.com