Title: Bull Nose Energy Absorption System
1Bull Nose Energy Absorption System
Part of
- Inland Navigation Safety Initiatives
Current Team Members Jeff Maynard, John
Clarkson, - LRH Bob Willis, Chad Linna,
LRD Kent Hokens MVP Dr. Robert Ebeling,
CEERD-IE
RD funding for FY 09 provided by Navigation
Systems Research Program at ERDC Mr. James E.
Clausner, Program Manager Dr. John Hite, Inland
Focus Area Leader
2(No Transcript)
3(No Transcript)
4Problem
- Head-on collisions with the end of rigid
navigation lock approach walls lead to lashing
failures - The barges that are no longer under control can
collide with dam and/or navigation lock gates - This scenario at its worst can lead to possible
pool loss due to gate failure, total loss of
barge and cargo, damages to navigation
structures, danger to personnel, etc.
5(No Transcript)
6Proposed Demonstration Site Smithland Lock and
Dam
- Pair of 1200 ft locks.
- Upstream approach wall.
- Consider protection of the existing rigid
bullnose with a new deformable bullnose system. - Design for a 3 by 5 barge train fully loaded
weighing 32,000 tons
7Solutions Being Investigated
A deformable (energy absorbing) bullnose
placed in front of an existing rigid bullnose to
reduce or eliminate lashing failures due to
head-on collisions.
8The Basic Physics of a Deformable Bull Nose
System Response
System Response Concept
- The approach taken to solve this problem is to
develop a new deformable bullnose. - A rigid bullnose abruptly de-celerates the barge
train during an impact. - During an abrupt de-acceleration, the forces
imparted to the lashings result in lashing
failures and out of control break-away barges.
9The Basic Physics of a Deformable Bull Nose
System Response
System Response Concept
- The concept is to develop a deformable bullnose
that allows the barge train to de-accelerate at a
lower rate, thereby reducing the possibility for
lashing failures . - We want to thank ACL and AEP for providing
lashing information for our study.
10Deformable Numerical Model To Investigate /
Mitigate Lashing Failures
11(No Transcript)
12(No Transcript)
13Sectional Elevation System 5.3
14Sectional Elevation System 5.3 Isolators at
500 Strain (Extreme Load)
15Sectional Plan System 5.3
16Sectional Plan System 5.3
Impact Nosing Impact face armored
Pier Table
M-1 Corbel
Impact Nosing Floor Slab
Gap
M-1
17Elevation Range of Significant Allisions with
Upper Approach Walls at Smithland Locks, 1981-2007
18System 6
Floating pier table
Permits efficient arrangement of pier table
isolators for all pool elevations
19 Idea of Floating Pier Table Is Based on a
Floating Wave Attenuator Flushing Bay ,NY
20(No Transcript)
21Sectional Elevation System 6
22Sectional Plan System 6
23Sectional Plan System 6
Impact Nosing Impact face armored
Gap
20
M-1 Corbel
Gap
10
0
10
DIP
Floating Pier Table
20
M-1
24Prevention of Barge Tow Lashing Failures
A Deformable Bull Nose Approach
Our goal is to reduce lashing failures and out of
control break-away barges by absorbing the energy
from a tow!
25Winfield Barge Impact Test on Flexible Walls
- Thanks to AEP for supplying tow and crew for the
test! - The initial Rigid Wall Barge Impact Test from
several years ago was instrumental in getting our
arms around these values for design on rigid
walls, ETL 1110-2-563 BARGE IMPACT ANALYSIS FOR
RIGID WALLS. These tests also helped us in our
understanding to pursue the Bull-nose solution.
26Test Site - Winfield Lock and Dam, Kanawha River,
West Virginia
Wall section of interest for impact testing the
upstream guard
27Proposed Guide Wall - LD 25
Why We Selected Winfield
- Winfield is similar in design to several proposed
projects on the Upper Miss - Lock and Dam 22
- Lock and Dam 25
- Other near-term projects to potentially benefit
from this field effort include - Upper Miss LD 3
- J.T. Myers Lock
- Extension
- Greenup Lock Extension
- Soo Locks
- Characteristics -
- 125-foot precast concrete beams.
- Connected to 35-ft-diameter concrete-filled
cells. - Cells anchored with 36-inch pipe piles.
28BIE 2008 Experiment Execution Goal A Safe
Operation with Minimal Impact to Navigation
- Tow configuration will be 3 x 3 jumbo
open-hopper barges (35 x 195 feet each), drafting
9 feet, and displacing approximately 20,000 short
tons.
29BIE 2008 - Technical Objectives/Measurements
- Determined the dynamic impact force under
controlled low-angle/low-velocity impacts on the
deformable lock wall. - Measured the corresponding wall deflection and
strain as a function of time.
30(No Transcript)
31Impact Testing at Winfield LD
32(No Transcript)
33Displacement Time History of Wall Section
34(No Transcript)
35Barge Impact Experiments Winfield Lock
The experiment was conducted on 25 and 26 August
2008.
- 23 Impacts were completed.
- Impact angles from 4 to 20.
- Approach speeds from 0.7 to 2.4 mph.
- Maximum deflections at mid-span. approximately
0.5 inches. - Maximum normal force approx. 500 kips.
- No damage to lock wall was observed.
Corner Barge Approaching Impact Point Winfield
LD, Aug 2008
Force measuring bumper used at Winfield LD
36Assessing the Barge Impact Data
- Current Activities - Extrapolate data for
multiple angles, velocities and other flexible
wall types. - Will write guidance for the efficient design of
new flexible walls.
37PIANC Inland Navigation Safety
- The objective of this working group is to
identify useful safety measures to reduce
accidents. - The ability of the system to quickly return to
service following a major catastrophe (man made
or natural) will be a major area of focus for
this report. - This working group would also inventory recent
safety initiatives in various countries and give
recommendations to improve safety.
38Thank You
- John Clarkson, P.E.
- John.D.Clarkson_at_usace.army.mil
- 304-399-5217
39(No Transcript)
40Barge Impact Experiments
- PI Bruce Barker
- Capability Being Developed
- Measurement of the dynamic response of flexible
beams during full scale impact events. - Final Products
- Document full scale experiment with a 3 x 3 barge
train impacting the upstream flexible guide wall
at Winfield Lock and Dam in an ERDC TR (FY09). - Measurement time histories of impact forces under
a wide range if impacts including bending
strains, lateral and longitudinal beam
displacement, acceleration, and beam deflections.
Wall section of interest for impact testing the
upstream guard
Site selected New upstream guard wall at
Winfield Lock and Dam, WV (Huntington District)
- Benefit
- Provide validation data in support ongoing and
future guide wall designs for flexible lock walls
where non previously exists
41(No Transcript)