Title: Distributed Generation Con Edison
1 Distributed Generation Con Edison
A.Kaffashan / M.Rollins April 23, 2004
2Con Edison Electric Distribution System
- Area 604 sq mi Population 8,800,000
- Electric Customers
- Total 3,200,000
- Network 2,300,000
- Radial 835,000
- Peak Load (2001) 12,207 MW
-
3 Design Basis of Distribution System
- Second Contingency
- High density load areas
- Urban and financial districts
- First Contingency
- Low load density areas
- Suburban area
- Separation of feeders
4Network Characteristics
- High Reliability
- Totally Underground
- Multiple Feeders
- Multi-level Electronic Monitoring and Control
Capabilities - Analytical Capabilities
- Real-Time Remote Control
5Electric Distribution System Networks
- Networks
56 - Feeders
897 - Network Transformers 24,000
- Manholes Boxes 260,000
- Primary Feeder Cable 27,000 km
- Secondary Cable 80,000 km
6Con Edison Electric Distribution System
- Network Many simultaneous paths for power to
flow to customers. - Each network is fed from one area substation.
- Typically u 12 - 24 primary feeder
- u 250 - 750 transformers
- u 7,500 - 75,000 customers
- Of 56 major networks u 33 in Manhattan
- u 10 in Brooklyn
- u 7 in Queens
- u 6 in Bronx
- Except for Manhattan, other Areas have extensive
- amounts of isolated networks and radial
distribution.
7Networks Elements
- Transformer Transform the voltage from primary
(13 or 27 kV) to secondary (120
volts). - Network Protector Isolate network from primary
feeder fault. - Fuses On each network protector to backup for
primary feeder fault - secondary fault.
- Limiters Weak links on each cable end to
isolate secondary faults to a single - section of cable.
8Simplified Area Network Schematic
Transformer
Distributed Network Grid is 120/208
Isolated Network
Network Protector and Fuse
Customer Load
9Typical Area and Spot Networks
10High Tension or High Rise Building
High Rise
Z
125/216V or277/480V
NWP
2500kVA each
2500, 3700, 5000kVA each
13, 27 or 33kV
4 or 13KV
CB (Typ.)
Large Commercial or Industrial Customer
S/S Bus
11Interconnection Process
- Preliminary Discussions
- Major Considerations of Combined Heat and Power
- Method of Electrical Connection
- Application and associated documentation
- Site-specific review by Con Edison
- Detailed Specifications
- Design and OM Specs Developed by Con Edison
- Signed by both the customer and Con Edison
- Verification Testing
- Procedure developed by customer
- Witnessed by Con Edison forces
- Interconnection Charges
- Costs related to the DG billed to the customer
12Interconnection Process
- Major considerations of CHP installation
- Con Edison How does the proposed generator
affect the existing electric system? - Available Short Circuit Current
- Fault Current added by the CHP
- Building Load with respect to the size of the CHP
System - Will the CHP system be a Qualified Facility?
- Is the system approved and type tested in
accordance with the NYS SIR? - Site Is there a continuous minimum electrical
and mechanical load to allow the CHP system to
continuously run efficiently?
13Fault Current added by the CHP
- Area Substation Fault Duty Limitations
14Effect of CHP System Sizing
- A short circuit study determines the available
fault current - Customer load must be evaluated to size
generator(s)
15Interconnection Process
- Method of Electrical Connection (Operating modes)
- Supplemental (parallel) CHP system runs
continuously, Con Ed provides difference - Buy-back not allowed on distribution network
system (SC11) - Standby CHP system runs continuously, providing
all loads, Con Edison available if CHP system is
down (SC14RA) - Isolated no interconnection with Con Ed system
16Interconnection Process
- Application and associated documentation
- NYS SIR (Radial Feeders)
- I. Project Contact
- II. Application Fee
- III. System Drawings
- IV. Equipment Description
- V. Verification Test Procedure
- (presently limited to 300 kVA)
- Con Edison (Networks)
- I. Service Address
- II. Account Information
- III. Service Description
- IV. Contractor Info
- V. Generator Data
- VI. Description of System Operation
- VII. System Drawings
17Interconnection Process
- Site-specific review by Con Edison
- Con Edison (Networks)
- I. Voltage Protection
- II. Frequency Protection
- III. Reverse Power Relay
- IV. Directional O/C
- V. Sync Check Relaying
- DISCONNECT SWITCH
- NYS SIR (Radial Feeders)
- I. Voltage Protection
- II. Frequency Protection
- III. Site Specific Relaying
- IV. Dedicated Transformer
- V. Net Metering
- DISCONNECT SWITCH
18Interconnection Process
- Network interconnection protection requirements
in Con Edison Handbook for Dispersed Generation - Anti-islanding protection (81U/O, 27/59)
- Reverse power protection (32R)
- Network protector interlocks
- Overcurrent protection (50/51)
- Synchronizing sync check functions (25)
- Disconnect switch (89)
19Interconnection Process
- Detailed specifications
- Design specifications developed by Con Edison to
indicate specific equipment required for
interconnection of CHP system - OM specifications developed by Con Edison to
indicate the methods to be followed when starting
and working with the CHP system - Final agreement between the customer and con
Edison
20Interconnection Process
- Verification testing
- Procedure developed by customer to show Con
Edison how the control and protection equipment
performs as designed - Procedure approved and witnessed by Con Edison
21Interconnection Process
- Interconnection charges
- Engineering review of information submitted
during application - Cost to perform work on Con Edison system to
allow for the interconnection of CHP system