Distributed Generation Con Edison - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Distributed Generation Con Edison

Description:

1. Distributed Generation Con Edison. A.Kaffashan / M.Rollins. April 23, 2004. 2 ... Multi-level Electronic Monitoring and Control Capabilities. Analytical ... – PowerPoint PPT presentation

Number of Views:151
Avg rating:3.0/5.0
Slides: 22
Provided by: Con4150
Category:

less

Transcript and Presenter's Notes

Title: Distributed Generation Con Edison


1
Distributed Generation Con Edison
A.Kaffashan / M.Rollins April 23, 2004
2
Con Edison Electric Distribution System
  • Area 604 sq mi Population 8,800,000
  • Electric Customers
  • Total 3,200,000
  • Network 2,300,000
  • Radial 835,000
  • Peak Load (2001) 12,207 MW

3
Design Basis of Distribution System
  • Second Contingency
  • High density load areas
  • Urban and financial districts
  • First Contingency
  • Low load density areas
  • Suburban area
  • Separation of feeders

4
Network Characteristics
  • High Reliability
  • Totally Underground
  • Multiple Feeders
  • Multi-level Electronic Monitoring and Control
    Capabilities
  • Analytical Capabilities
  • Real-Time Remote Control

5
Electric Distribution System Networks
  • Networks
    56
  • Feeders
    897
  • Network Transformers 24,000
  • Manholes Boxes 260,000
  • Primary Feeder Cable 27,000 km
  • Secondary Cable 80,000 km

6
Con Edison Electric Distribution System
  • Network Many simultaneous paths for power to
    flow to customers.
  • Each network is fed from one area substation.
  • Typically u 12 - 24 primary feeder
  • u 250 - 750 transformers
  • u 7,500 - 75,000 customers
  • Of 56 major networks u 33 in Manhattan
  • u 10 in Brooklyn
  • u 7 in Queens
  • u 6 in Bronx
  • Except for Manhattan, other Areas have extensive
  • amounts of isolated networks and radial
    distribution.

7
Networks Elements
  • Transformer Transform the voltage from primary
    (13 or 27 kV) to secondary (120
    volts).
  • Network Protector Isolate network from primary
    feeder fault.
  • Fuses On each network protector to backup for
    primary feeder fault
  • secondary fault.
  • Limiters Weak links on each cable end to
    isolate secondary faults to a single
  • section of cable.

8
Simplified Area Network Schematic
Transformer
Distributed Network Grid is 120/208
Isolated Network
Network Protector and Fuse
Customer Load
9
Typical Area and Spot Networks
10
High Tension or High Rise Building
High Rise
Z
125/216V or277/480V
NWP
2500kVA each
2500, 3700, 5000kVA each
13, 27 or 33kV
4 or 13KV
CB (Typ.)
Large Commercial or Industrial Customer
S/S Bus
11
Interconnection Process
  • Preliminary Discussions
  • Major Considerations of Combined Heat and Power
  • Method of Electrical Connection
  • Application and associated documentation
  • Site-specific review by Con Edison
  • Detailed Specifications
  • Design and OM Specs Developed by Con Edison
  • Signed by both the customer and Con Edison
  • Verification Testing
  • Procedure developed by customer
  • Witnessed by Con Edison forces
  • Interconnection Charges
  • Costs related to the DG billed to the customer

12
Interconnection Process
  • Major considerations of CHP installation
  • Con Edison How does the proposed generator
    affect the existing electric system?
  • Available Short Circuit Current
  • Fault Current added by the CHP
  • Building Load with respect to the size of the CHP
    System
  • Will the CHP system be a Qualified Facility?
  • Is the system approved and type tested in
    accordance with the NYS SIR?
  • Site Is there a continuous minimum electrical
    and mechanical load to allow the CHP system to
    continuously run efficiently?

13
Fault Current added by the CHP
  • Area Substation Fault Duty Limitations

14
Effect of CHP System Sizing
  • A short circuit study determines the available
    fault current
  • Customer load must be evaluated to size
    generator(s)

15
Interconnection Process
  • Method of Electrical Connection (Operating modes)
  • Supplemental (parallel) CHP system runs
    continuously, Con Ed provides difference
  • Buy-back not allowed on distribution network
    system (SC11)
  • Standby CHP system runs continuously, providing
    all loads, Con Edison available if CHP system is
    down (SC14RA)
  • Isolated no interconnection with Con Ed system

16
Interconnection Process
  • Application and associated documentation
  • NYS SIR (Radial Feeders)
  • I. Project Contact
  • II. Application Fee
  • III. System Drawings
  • IV. Equipment Description
  • V. Verification Test Procedure
  • (presently limited to 300 kVA)
  • Con Edison (Networks)
  • I. Service Address
  • II. Account Information
  • III. Service Description
  • IV. Contractor Info
  • V. Generator Data
  • VI. Description of System Operation
  • VII. System Drawings

17
Interconnection Process
  • Site-specific review by Con Edison
  • Con Edison (Networks)
  • I. Voltage Protection
  • II. Frequency Protection
  • III. Reverse Power Relay
  • IV. Directional O/C
  • V. Sync Check Relaying
  • DISCONNECT SWITCH
  • NYS SIR (Radial Feeders)
  • I. Voltage Protection
  • II. Frequency Protection
  • III. Site Specific Relaying
  • IV. Dedicated Transformer
  • V. Net Metering
  • DISCONNECT SWITCH

18
Interconnection Process
  • Network interconnection protection requirements
    in Con Edison Handbook for Dispersed Generation
  • Anti-islanding protection (81U/O, 27/59)
  • Reverse power protection (32R)
  • Network protector interlocks
  • Overcurrent protection (50/51)
  • Synchronizing sync check functions (25)
  • Disconnect switch (89)

19
Interconnection Process
  • Detailed specifications
  • Design specifications developed by Con Edison to
    indicate specific equipment required for
    interconnection of CHP system
  • OM specifications developed by Con Edison to
    indicate the methods to be followed when starting
    and working with the CHP system
  • Final agreement between the customer and con
    Edison

20
Interconnection Process
  • Verification testing
  • Procedure developed by customer to show Con
    Edison how the control and protection equipment
    performs as designed
  • Procedure approved and witnessed by Con Edison

21
Interconnection Process
  • Interconnection charges
  • Engineering review of information submitted
    during application
  • Cost to perform work on Con Edison system to
    allow for the interconnection of CHP system
Write a Comment
User Comments (0)
About PowerShow.com