Title: Myrtle Beach Hurricane and Storm Protection Project
1Myrtle Beach Hurricane and Storm Protection
Project
2Myrtle Beach Project Getting Started
- Feasibility Study
- Had to be economically justified BCR of 3.7
- EIS completed for 50 year life of project
- -Authorization 1990
- -First nourishment 1996-1998 (65 Federal/35
Non-Federal) - -Must be a public beach Public access required
at least every ½ mile
3Myrtle Beach Project Environmental
- Environmental Effects/Issues
- National Environmental Policy Act
(Environmental Assessment / Environmental Impact
Statement) - Coastal Barrier Resources Act (CBRA)
restrictions on borrow sites - Evaluation of general biological effects
- Sea turtle nesting effects
- Benthic organism effects borrow site surf
zone - Burrowing macro-invertebrate effects
- Shore bird effects (nesting, foraging, loafing)
4Myrtle Beach Project Environmental
- Environmental features
- Turtle nesting season May 1st thru November
30th - Peak nesting activity after June 1st
- Till entire length of new beach
- Flatten escarpments as they form
- Nighttime monitors to protect nesting sea turtles
(100 ft buffer) - relocate nests
5Myrtle Beach Project
- Borrow site investigation
- side scan sonar and sub-bottom profiling
- vibracores
- Cultural Resource Survey side scan sonar
magnetometer
6Myrtle Beach Project Beach Nourishment Basics
- Technical
- Protective dune fronted by a sacrificial berm
- Dune height based on maximizing the level of
protection (usually a 25 or 50 year storm event) - Width of sacrificial berm determined by erosion
rate and renourishment cycle - Typically 75 yd3 to 100 yd3 per linear foot
- Renourishment cycle based on computer models
(life cycle analysis using historical erosion
rates and storm frequencies) - Borrow source must be compatible with native
beach
7Myrtle Beach Project
The original beach nourishment project from 1996
to 1998 placed 6.4 million cubic yards of sand at
a cost of 51.3 million. Most recent
renourishment 2007-2009 placed slightly more than
3 million cubic yards Additional renourishment
authorized as needed for 50 years, if funds
appropriated Estimated need for renourishment is
every 8-10 years (unless emergency renourishment
needed)
8Myrtle Beach ProjectPublic Law 84-99 (Emergency
Flood Control Act of 1955)
- Repairing Federally Authorized Hurricane and
Storm Protection Projects is one of eight major
items authorized by P.L. 84-99. - If a major storm and Congress approves emergency
funding, repairs 100 Federally funded
9Myrtle Beach Project
- Typical periodic renourishment construction cost
shared 65/35 - Emergency P.L. 84-99 renourishment funded 100
Federal - Myrtle Beach most recent renourishment a
combination of both types of funds
10Myrtle Beach Project Scope and Sponsors
N. Myrtle Beach
Horry County
Reach 1 ¾ M cubic yds
Myrtle Beach
Reach 2 1.5 M cubic yds
Henry E. Brown Jr. (R) 1st Congressional
District, SC
Reach 3 ¾ M cubic yds
- 29M Project,
- Hurricane Ophelia FCCE funds (14.7M)
- Remainder cost shared 65 Federal / 35 State
Local Sponsors - 25 miles of Coastline 3 million cubic yards of
sand - Enough sand to fill the Empire State Building
- 13 Month Construction Schedule
11Myrtle Beach Project Great Lakes Dredge and Dock
(GLDD) Plan
Reach 1 Last (Jul-Oct)
Reach 2 Second (Mar-Jul)
Reach 3 First (Nov-Feb)
- Work from South to North
- Nov 07 GLDD mobilize 1st dredge
- Dec 07 GLDD mobilize 2nd dredge
12Myrtle Beach Project Before and After Reach 3
(Surfside Beach) February 2008
13Myrtle Beach Project Change to Scope? Are there
Off Shore UXOs in our Borrow Sites?
- On 8 Nov 1943, the Myrtle Beach Airstrip was
renamed Myrtle Beach Army Air Field (MBAAF). - It consisted of two bombing ranges and three
gunnery ranges. - There was a secondary airstrip at Surfside Beach,
about 10 miles south of MBAAF known as Wampee
Flight Strip.
14Myrtle Beach Project Change to Scope? Off Shore
UXOs
- Possible Courses of Action
- COA 1 Do nothing and hope no UXOs are found
- COA 2 Ask contractor to screen for UXOs off
shore - (most expensive and will slow down rate of sand
to beach) - COA 3 Ask contractor to screen for UXOs at
beach - (will slow work down but not as much as COA 2)
- Corps asks Contractor for a cost/scope proposal
for new requirement - Jan 08 Proposal received from GLDD for 1M-2M
- Feb 08 Corps decides cost does not outweigh the
risk/benefit
15Myrtle Beach Project Change to Timeline? New
Orleans District must respond to Midwest Floods
- New Orleans District Newsletter (10 April 2008)
- The Corps is currently running five dredges 24
hours a day, seven days a week in the Southwest
Pass near the mouth of the river to maintain
river navigation. - During high river conditions, shoaling is rapidly
occurring near the mouth of the Mississippi River
where surveys are taken daily and dredge
assignments are constantly being issued to keep
pace with the dynamic changes in the river.
16MYRTLE Beach Project Change to Timeline?25
March 2008
- 0900hrs GLDD tells Charleston District they
want to bid on Mississippi Emergency dredging. - Bids due in two hours!
- GLDD says they will cut off the contract if
we allow them 4-6 week extension on the project
completion date. - GLDD will return to Myrtle Beach in early July
- 0930 Corps meeting to discuss courses of action
- - COA 1 Accept GLDD offer knowing that
- if GLDD is awarded the New Orleans contract, the
dredge will be off the Myrtle Beach project over
4 months - Reaches 1 and 2 will be undernourished during
Hurricane Season - COA 2 Tell GLDD we will hold them to our
contract - 1000 Charleston asks GLDD to request a 1 hour
delay - 1000 PM calls Horry County, Myrtle Beach and N
Myrtle Beach to explain situation and to get
their input. - 1100 Corps approves GLDDs proposal to bid on
New Orleans work
17Myrtle Beach Project - GLDDs New Plan
Reach 1 Second (Jul Aug 08)
Reach 2 Last (Sep - Nov 08)
Reach 1 Last (Jul-Oct 08)
Reach 2 Second (Mar-Jul 08)
Reach 3 First (Nov 07- Feb 08)
- The Change to Schedule results in
- Bad Press from N Myrtle Beach (height of tourist
season) - Myrtle Beach is happy beach remains untouched
over summer - Lesson in public information about impacts during
construction
18Myrtle Beach Project What Happens?
- Chocolate Milkshake
- Shaped by bulldozers
- Where did all the sand go? settling period
- Sacrificial sand and protective berm
19Myrtle Beach Project Profile
20Myrtle Beach Project
21Myrtle Beach Project
22Myrtle Beach ProjectCutterhead Pipeline not
suitable for borrow area
23Myrtle Beach Project
24Myrtle Beach Project Hopper Dredge
25Myrtle Beach Project
26Myrtle Beach Projectexample of contrast-
Virginia Beach
27Myrtle Beach Project Survey Marks
28Myrtle Beach Project
29Myrtle Beach Project
30Myrtle Beach Project
31Myrtle Beach Project
32Myrtle Beach Project - note shielded nightlight
33Myrtle Beach Project
34Myrtle Beach Project Fencing Grassing
- Fences trap sand and build dunes.
- Native dune grasses planted immediately behind
fences. - Eventually grasses grow over dune and help
stabilize it
35Myrtle Beach Project
36Myrtle Beach Project Fencing and Grassing
37Myrtle Beach Project
QUESTIONS?