Status of the electronic integration in FfM - PowerPoint PPT Presentation

1 / 8
About This Presentation
Title:

Status of the electronic integration in FfM

Description:

Step 3:Gluing of Cooling pipes. Done by two technician and a students (wissenschaftliche ... 1 h 1.5 h preparation and gluing for 2 persons. 12 h hardening ... – PowerPoint PPT presentation

Number of Views:20
Avg rating:3.0/5.0
Slides: 9
Provided by: Har135
Category:

less

Transcript and Presenter's Notes

Title: Status of the electronic integration in FfM


1
Status of the electronic integration in FfM
  • 10.8.2007

2
Status
  • Finished SM3
  • Last chambers will be shipped to MS next Week
  • 2.5 Technicians (Werner Amend, Arnold
    Wiesenäcker, Hannelore Hinke)
  • 1 Diploma Student (Andreas Fick)
  • 2 PhD Students (Konstatin Antipin, Frederick
    Kramer)
  • 1 Postdoc (Matthias Hartig)
  • 6 Students (wissenschaftliche Hilfskräfte)
  • Support from outside (Benjamin Doenigus)

3
Step1 ROB Mounting
  • Well established procedure
  • Done by students (wissenschaftliche Hilfskräfte)
  • 2 students 2-3 h per chamber
  • Rate 1 chamber per day
  • (max. 4 chambers per day)
  • gt No delay expected

4
Step 2 First Electronic Test
  • Starting the production phase
  • 2 Setups for testing
  • Max Rate 2 tests per day
  • Digital Tests 1 h (can
    run in parallel)
  • Noise/Pulser Tests 1 h
  • Stress Test 12 h (can
    run in parallel)
  • gt 1 test / setup / day

5
Step 3Gluing of Cooling pipes
  • Done by two technician and a students
    (wissenschaftliche
  • Hilfskräfte)
  • 1 h 1.5 h preparation and gluing for 2 persons
  • 12 h hardening
  • Rate 1 chamber per day
  • (max. 2 chambers per day)
  • Caused no delay so far
  • Changing production labs
  • gt Gain only a little by improved
    production process

6
Step 4 Second Electronic Test
  • Same setup like for first test
  • 2 Setups for testing
  • Max Rate 2 tests per day
  • Digital Tests 1 h (can
    run in parallel)
  • Noise/Pulser Tests 1 h
  • Stress Test 12 h (can
    run in parallel)
  • gt 1 test / setup / day
  • gt max. rate 1 chamber/day

7
Production Rate per Week
  • Production of 1 Layer per week
  • gt 10 tests a week
  • For SM3
  • Rate lt 10
  • 2-3 chambers needed more than one 2nd test
  • Last 4 Layers
  • 4 Memory errors
  • 2 NI test errors
  • Problems with initialization (?)
  • 6 stress test failures (?)
  • Broken Cable Bridges

8
Improvement
  • 7.5 broken Cable bridges gt bridges are tested
  • MCM ID gt solved by Tom
  • 3rd test stand gt in preparation

Next Steps
  • Update of software CommandCoder, DCS
    firmware, InterComLayer,
  • feeserver,
  • Alexandru agreed to take over this task. He
    needs support gt Meet
  • after the Status Meeting
  • gt Is needed for new PVSS Test Software
    (Andreas)
  • gt Test can be done by Students
  • BUT we need more manpower gt Martin
    Freudenberger will help us
  • Evaluate test results skip long stress test
    with cooling pipes (?)
  • (Another production site)
  • ???