Title: The Lower Mon Project
1The Lower Mon Project
Briefing to Waterways Association of
Pittsburgh April 14, 2004
William A. Karaffa, P.E. Project Manager
2The Lower Mon Project
Braddock Dam
Demolition of Old Dam 2
3The Lower Mon Project
Braddock Dam
Demolition of Old Dam 2
4The Lower Mon Project
Charleroi Locks
Independent Value Engineering Study Project
Status
5The Lower Mon Project
Charleroi LocksIndependent Value Engineering
Study Best Value Trade-Off Evaluation
6The Lower Mon Project
Charleroi LocksIndependent Value Engineering
Study Final Recommendation
? The Evaluation Team and the PRB acknowledged
the potential cost savings of 25M was very
speculative, due to the preliminary nature of the
VE design. ? The PRB concluded that the risks
associated with the long term operability,
maintainability, and navigation safety of the VE
to be unacceptable, regardless of the potential
cost savings.
7The Lower Mon Project
Charleroi Locks
Project Status ? Right
Bank Work Features - Ongoing ? River Chamber
Demolition Ongoing ? New River Wall
Construction Advertise April 26, 2004 ?
Waterways Site Visit April 22, 2004
8Lower Monongahela River Project Efficient
Constrained Funding Streams
9Lower Monongahela River Project Current Schedule
(30 M / Year)
10Lower Monongahela River Project Impacts of
Constrained Funding
- Completion of Charleroi Locks is delayed 6 years
- Risk of failure at L/D 3 increases significantly
major rehabilitation may be required to extend
project life until 2016 when Dam 3 is removed. - Increased OM costs to maintain depreciated lock
operating equipment at Locks 3 4 - Total benefits foregone with FY-05 constrained
schedule are estimated at 1.2 billion.
11Lower Monongahela River ProjectAdditional OM
Requirements
- Locks 3 4 (Normal Maintenance Schedule)
- 2007 Repair Valves Gate Miter Sills
2.0 M - 2010 Lock Gate Replacement or Rehab
1.5 M - 2017 Repair Valves Gate Miter Sills
2.2 M - Total (Each Project) 5.7 M
- Dam 3
- Significant potential for foundation failure
without major Rehabilitation. Pool 3 could be
lost, resulting in significant impacts to Locks 4
stability, Municipal water intakes, and private
facilities.