The Lower Mon Project - PowerPoint PPT Presentation

About This Presentation
Title:

The Lower Mon Project

Description:

The Evaluation Team and the PRB acknowledged the potential cost ... Total benefits foregone with FY-05 constrained schedule are estimated at $1.2 billion. ... – PowerPoint PPT presentation

Number of Views:19
Avg rating:3.0/5.0
Slides: 12
Provided by: HEDW5
Category:
Tags: foregone | lower | mon | project

less

Transcript and Presenter's Notes

Title: The Lower Mon Project


1
The Lower Mon Project
Briefing to Waterways Association of
Pittsburgh April 14, 2004
William A. Karaffa, P.E. Project Manager
2
The Lower Mon Project
Braddock Dam
Demolition of Old Dam 2
3
The Lower Mon Project
Braddock Dam
Demolition of Old Dam 2
4
The Lower Mon Project
Charleroi Locks
Independent Value Engineering Study Project
Status
5
The Lower Mon Project
Charleroi LocksIndependent Value Engineering
Study Best Value Trade-Off Evaluation
6
The Lower Mon Project
Charleroi LocksIndependent Value Engineering
Study Final Recommendation
? The Evaluation Team and the PRB acknowledged
the potential cost savings of 25M was very
speculative, due to the preliminary nature of the
VE design. ? The PRB concluded that the risks
associated with the long term operability,
maintainability, and navigation safety of the VE
to be unacceptable, regardless of the potential
cost savings.
7
The Lower Mon Project
Charleroi Locks
Project Status ? Right
Bank Work Features - Ongoing ? River Chamber
Demolition Ongoing ? New River Wall
Construction Advertise April 26, 2004 ?
Waterways Site Visit April 22, 2004
8
Lower Monongahela River Project Efficient
Constrained Funding Streams
9
Lower Monongahela River Project Current Schedule
(30 M / Year)
10
Lower Monongahela River Project Impacts of
Constrained Funding
  • Completion of Charleroi Locks is delayed 6 years
  • Risk of failure at L/D 3 increases significantly
    major rehabilitation may be required to extend
    project life until 2016 when Dam 3 is removed.
  • Increased OM costs to maintain depreciated lock
    operating equipment at Locks 3 4
  • Total benefits foregone with FY-05 constrained
    schedule are estimated at 1.2 billion.

11
Lower Monongahela River ProjectAdditional OM
Requirements
  • Locks 3 4 (Normal Maintenance Schedule)
  • 2007 Repair Valves Gate Miter Sills
    2.0 M
  • 2010 Lock Gate Replacement or Rehab
    1.5 M
  • 2017 Repair Valves Gate Miter Sills
    2.2 M
  • Total (Each Project) 5.7 M
  • Dam 3
  • Significant potential for foundation failure
    without major Rehabilitation. Pool 3 could be
    lost, resulting in significant impacts to Locks 4
    stability, Municipal water intakes, and private
    facilities.
Write a Comment
User Comments (0)
About PowerShow.com