Title: Level 1 Muon Trigger Status and Commissioning


1
Level 1 Muon Trigger Status and Commissioning
  • Rob McCroskey
  • University of Arizona
  • for the
  • L1 Muon Group

2
L1MU Hardware
  • MTCM (Crate Manager)
  • Production card testing in progress
  • MTCxx (Trigger Card)
  • Production cards beginning fabrication
  • MTFB (Flavor Boards)
  • Production MTM boards ready for fabrication
  • Production MTC10 board design in progress (finish
    in couple weeks)
  • Preproduction MTC05 board in fabrication
  • SLDBs (Gbit/s Serial Links)
  • Production board testing in progress

3
MCEN Hardware
  • MCCM (Crate Manager)
  • Preproduction card layout in progress
  • MCEN (Centroid Finder Card)
  • Preproduction card testing in progress
  • MCPB (Physics Boards)
  • Preproduction board testing in progress

4
L1MU Infrastructure
  • Custom VME backplanes
  • Complete
  • Power supplies
  • Prototype assembled and tested
  • VICOR supplies ordered but with 20-22 week lead
    time
  • Platform services
  • On hold pending final cable plant design
  • Cabling
  • Production at Fermilab and NIU in progress

5
Near Term Commissioning Goals
  • mid-August
  • Stable operation of one (sparse) L1MU trigger
    crate and the L1MU MTM crate
  • Still using preproduction cards
  • early October
  • Add L1CFT MTM crate to the above
  • mid-October
  • Begin commissioning production L1MU crates and
    cards

Done
Underway
Underway
Aiming for stable L1MU operation for
commissioning by mid to late October
6
Longer Term Commissioning Goals
  • Begin full crate testing in late December or
    early January
  • Two octant triggering until then
  • MCEN cards 2 months behind above
  • Temporary power supplies for full crate tests