Title: Overview of the Design Build Process


1
Overview of the Design- Build Process
CEM 525 Project Delivery Systems
  • By Mohammed Jalaluddin

2
Qualifications-based selection
Qualifications-based selection refers to a
design-builder selection process, where one
design-builder is selected for the project, at
least conditionally, on the basis of its
reputation and qualifications typically in an
early phase of a project, and at once, without
actual phasing
3
Qualifications-based selection
  • The main steps of a typical process involving a
    qualifications-based selection procedure are the
    following

4
1. Strategic Facility Planning.
  • The owner identifies the prospective project in
    broad business terms
  • Needs are established in terms of project area,
    population, technology content, performance
    criteria, etc.
  • A site may or may not have been identified.
  • The owner also determines that design-build,
    and this process specifically is the desirable
    mode of propagation for the project.

5
2.Selection of Design Builder
  • A few potential design-builders are identified
    based upon factors such as reputation, previous
    owner experience, capacity, pricing methods,
    fees, etc.
  • The short listed design-builders are interviewed
    or requested to submit more detailed
    qualifications and, on these grounds, evaluated
    against criteria established by the owner. A
    single design-builder is preliminarily selected.

6
3. Conclusion of First Part of Contract.
  • Contract language and terms are negotiated and
    typically a contract is executed to authorize
    preliminary design, some design development and
    outline specifications, all sufficient to define
    the project conceptually, describe the
    performance of the intended building, and fix the
    price.

7
4. Project Definition.
  • The design-builder joins with the owner in the
    establishment of overall project objectives,
    requirements, and target budgets and schedules.
    Design is started by the design-build entity, and
    design decisions proceed along with consideration
    of construction factors. The work is carried out
    as defined in the contract.

8
5. Design-Build Contract Award.
  • Well before the drawings are complete, often as
    early as the concept phase, a lump sum price (or
    guaranteed maximum cost) is established by the
    design-build entity. This is typically done on an
    "open book" basis where competitive pricing is
    obtained from subcontractors and vendors in the
    marketplace. If the owner is content with the
    design and price proposal, the design-builder is
    contracted for the completion of design and
    construction.

9
6. Construction Documents and Construction.
  • Upon completion of the design documents for all
    elements or for specific phases of the project,
    construction commences. The review and approval
    process is structured (typically 30-60-90- 100
    design complete) to ensure that the owner has the
    say also in the subsequent design process. The
    process continues in the customary manner but is
    enhanced by the incorporation of design and
    construction responsibility.

10
(No Transcript)
11
Two-stage selection
  • DescriptionTwo-stage selection refers to a
    design-builder selection process where the first
    phase involves shortlisting of candidates on the
    basis of the qualification statements they
    supply, and the second phase involves final
    selection on the basis of technical and price
    proposals, etc. from the shortlisted offerors.

12
1. Strategic Facility Planning.
  • The owner identifies the prospective project in
    broad business terms needs are established in
    terms of project area, population, technology
    content, performance criteria, etc. A site may or
    may not have been identified. The owner also
    determines that design-build, and this process
    specifically is the desirable mode of propagation
    for the project.

13
2. Project Definition.
  • The owner establishes the project requirements
    in terms of facility size and performance
    criteria, finish requirements, quality standards,
    applicable codes, regulatory standards,
    occupants/ capacities, equipment requirements,
    etc. These requirements are defined and
    articulated either by in-house professional staff
    or by an outside consultant.

14
3. Request for Qualifications (RFQ).
  • Professional, financial and experiential
    requirements for offerors as well as general
    project parameters are articulated in an RFQ (see
    Table 10), either by in-house staff or by an
    outside professional consultant.
  • 4. Qualifications Statements. The project is
    advertised, RFQ.s are supplied to interested
    design-builders, and qualification statements are
    received in response to RFQs. Generally three,
    never more than five, of the most qualified firms
    are shortlisted for the second stage.


15
5. Request for Proposals (RFP).
  • Design and cost proposals are solicited from the
    shortlisted design-build teams in a Request for
    Proposal (RFP). Among the items found in a
    typical RFP are project design criteria, site
    information, contract requirements, selection
    procedure and proposal requirements. (see Table
    11).
  • 6.Pre-Proposal Conference. This meeting of all
    shortlisted proposers early in the proposal
    preparation period is held by many owners to
    allow proposers to ask questions and request
    clarifications. Outside the meeting, only written
    questions and answers are allowed in order to
    treat all competitors equally.

16
7. Proposal Submission and Evaluation.
  • Once received, proposals are evaluated on the
    basis of quality of design, price and other
    predetermined factors related to definition of
    best value. Before the final award is made,
    proposers may be asked to make inperson
    presentations to the owners selection panel.
  • 8. Contract Award. The selected proposer enters
    into contract with the owner, which incorporates
    both the owners requirements and the
    design-builders proposal.

17
9. Construction Documents and Construction.
  • Upon completion of the design documents for all
    elements or for specific phases of the project,
    construction commences. The review and approval
    process is structured (typically 30-60-90- 100
    design complete) to ensure that the owner has the
    say also in the subsequent design process. The
    process continues in the customary manner but is
    enhanced by the incorporation of design and
    construction responsibility.

18
(No Transcript)
19
(No Transcript)
20
(No Transcript)
21
HANORARIUM
  • An honorarium or a stipend is a certain sum
    sometimes paid to offerors in consideration for
    the cost of preparing a design-build proposal.
    When should an honorarium be paid, how much
    should it be, and what else should be taken into
    account when contemplating honorariums in a
    project? The payment of an honorarium is,
    however, up to the owner and in many cases no
    stipend is paid to unsuccessful teams. In such
    situations the construction firm, operating in
    accordance with a design-build teaming agreement,
    may pay its design team partner for preparing
    most of the proposal, thus partially compensating
    the A/E partner for its considerable effort in
    preparing the design-build proposal. Moreover,
    winning design teams of design-build projects
    should demand and expect a higher than normal fee
    for the balance of its services on the project in
    the proposal phase.

22
(No Transcript)
23
(No Transcript)
24
(No Transcript)
25
Bridging-type selection
  • Description
  • Bridging-type selection refers to a process
    where a firm price contract is made based on the
    owner's preliminary design and candidates' price
    offers, followed by the design-builder's
    completion of design including possible
    modifications on design and price, their review
    and acceptation, and subsequently construction.

26
1. Strategic Facility Planning.
  • The owner identifies the prospective project in
    broad business terms needs are established in
    terms of project area, population, technology
    content, performance criteria, etc. A site may or
    may not have been identified. The owner also
    determines that design-build, and this process
    specifically is the desirable mode of propagation
    for the project.

27
2. Involvement of an Architect.
  • The owner hires an architect to complete
    preliminary design of the project. These
    .scope-of-work. documents define the functional
    and aesthetic aspects of the project, while the
    details of construction technology are left for
    the design-build team to define. The owners
    architect remains a consultant to the owner
    throughout the design and construction.

28
3. Selection of Design-Builder.
  • The owners consultant prepares an extensive
    Request for Proposal and, subsequently, bids are
    solicited from (or negotiations are initiated
    with) design-build entities. The design-builder
    is usually selected on the basis of a price
    offer, possibly supplemented by qualification
    criteria. No technical proposal is needed in this
    stage.
  • 4.Conclusion of Contract. Typically, a firm price
    contract is completed. While the price covers all
    design and construction, the contract commonly
    authorizes the design-build entity to complete
    the design and construction documents only, so
    that thereafter the parties have a check point on
    the modifications.

29
5. Completion of the Project Documents.
  • The design-build entity executes design
    sufficient to define the project, describe the
    performance of the intended building, and price
    the possible changes. The owner and his
    consultant review the construction documents for
    compliance with the design intent and conducts a
    price review with the contractor. Normally,
    notice to proceed with construction is given.

30
6. Construction Documents and Construction.
  • Upon completion of the design documents for all
    elements or for specific phases of the project,
    construction commences. The review and approval
    process is structured (typically 30-60-90- 100
    design complete) to ensure that the owner has the
    say also in the subsequent design process. The
    process continues in the customary manner but is
    enhanced by the incorporation of design and
    construction responsibility.

31
(No Transcript)
32
(No Transcript)
33
Direct design-build
  • Description
  • Direct design-build refers to the practice,
    where the design-builder becomes involved in the
    project prior to the start of the actual design
    phase on the basis of the owner's predesign
    information such as feasibility studies or maybe
    a project program.

34

35
Under a direct design-build arrangement, there
are two typical ways to proceed
  • Firstly, it is not unusual for the initial
    program definition services to be performed on
    the basis of an oral understanding or a simple
    letter of agreement ?a more complete contract is
    developed once the project is better defined.
    Thus, after the first contact and discussions on
    the project, the design-builder works for project
    planning with the understanding that if the owner
    is happy with the design-builder.s proposal, the
    design-builder will be engaged to do subsequent
    design and construction. The proposal work is
    generally part of the marketing of the
    design-builder which is not properly compensated
    for by the owner.

36
  • Alternatively, the owner may enter into contract
    with the design-builder relatively promptly
    instead of negotiating about the design-builders
    evolving proposal. Typically the agreement
    authorizes the design-build entity to do
    preliminary design and outline specifications
    only to provide the owner a checkpoint before
    committing himself to completing the project. New
    negotiations are then needed on the basis of the
    design-builders proposal. Since the work is
    based on a contract, the deliverable by the
    design-builder in the initial phase may be
    considered to be more complete than that made on
    the basis of the negotiated approach.

37

38
(No Transcript)
39
Design criteria method
  • Description
  • Design criteria-type design-build refers to the
    practice, where the design-builder becomes
    involved in the project on the basis of the
    owner's design criteria that define the owners
    requirements and wishes and direct the subsequent
    design process, but do not dictate the
    architectural and technical solutions.

40
(No Transcript)
41
  • In a design-build project according to the
    design criteria method, the owner prepares a
    statement of facility requirements that directs
    the design-builders. subsequent proposal design
    and is comprehensive enough to assure compliance
    by the offerors, but avoids restrictive details
    that would inhibit creative solutions. This means
    that the owners design professional improves the
    general project scope definitions and space
    itemization from the programming phase which
    results in the owners design criteria package.

42
The design criteria package consists typically
of
  • site plan and information
  • space program including a schedule of rooms
    with their type/use, number and area
  • room-specific criteria for finishes, fixtures
    and fittings, services and environment
  • outline specification for components to be used
  • diagrammatic floor or space plans, or schematic
    design, and
  • other pertinent criteria.

43
  • The completed criteria package is incorporated
    into the owners business elements as regards the
    project. In competitive design-builder selection
    the combination forms the Request for Proposals
    (RFP). Correspondingly, business elements include
    contractual terms and conditions, time and place
    for receipt of proposals, schedule requirements,
    bid and contract bond requirements, and basis for
    evaluation and selection.55 A framework for an
    entire RFP was given above in Table 11 (p. 51) in
    the context of competitive two-stage
    design-builder selection. Table 21, again,
    details an actual RFP which includes the design
    criteria of Table 20 referred to earlier.

44
(No Transcript)
45
(No Transcript)
46
(No Transcript)
47
Preliminary engineering method
  • Description
  • Preliminary engineering-type design-build refers
    to the practice, where the design-builder becomes
    involved in the project on the basis of a
    preliminary design solution, which defines the
    shape, massing and layout of the prospective
    building, and may give strict guidelines or
    solutions for many technical components of the
    project.

48
(No Transcript)
49
  • The design-build RFP specifications often
    combine elements of design and performance while
    the owners consultants often carry out the
    schematic design phase and continue into the
    design development phase, and maybe even
    partially into the construction document phase.
    Design development as a phase refers, again, to
    evolution of design that defines the functional
    and aesthetic aspects of the project and the
    building systems that satisfy them.

50
Therefore, in addition to documents of earlier
design phases, also the following elements are
often completed before the design-builders
involvement
  • architectural drawings that include floor
    plans, elevations and sections.
  • technical design where the structural,
    mechanical, and electrical systems are developed
    by selecting the type of systems, etc.
  • Additionally, many details can be designed and
    many materials specified (cf. Table 23).
    Naturally, the primary aim is still that the
    building is defined in terms of performance
    specifications that merely set forth the
    operational characteristics or end result
    desired, without saying how that result has to be
    achieved or the product constructed. It may be,
    however, that the owner designs the systems and
    components that are critical to him but leaves
    the others alone. Thus, the preliminary
    engineering method does not mean that the owner
    would progress in all design areas and
    disciplines equally although some of the design
    aspects of the building were closed.