Title: Overview of the Design Build Process
1Overview of the Design- Build Process
CEM 525 Project Delivery Systems
2Qualifications-based selection
Qualifications-based selection refers to a
design-builder selection process, where one
design-builder is selected for the project, at
least conditionally, on the basis of its
reputation and qualifications typically in an
early phase of a project, and at once, without
actual phasing
3Qualifications-based selection
- The main steps of a typical process involving a
qualifications-based selection procedure are the
following
41. Strategic Facility Planning.
- The owner identifies the prospective project in
broad business terms - Needs are established in terms of project area,
population, technology content, performance
criteria, etc. - A site may or may not have been identified.
- The owner also determines that design-build,
and this process specifically is the desirable
mode of propagation for the project.
52.Selection of Design Builder
- A few potential design-builders are identified
based upon factors such as reputation, previous
owner experience, capacity, pricing methods,
fees, etc. - The short listed design-builders are interviewed
or requested to submit more detailed
qualifications and, on these grounds, evaluated
against criteria established by the owner. A
single design-builder is preliminarily selected.
63. Conclusion of First Part of Contract.
- Contract language and terms are negotiated and
typically a contract is executed to authorize
preliminary design, some design development and
outline specifications, all sufficient to define
the project conceptually, describe the
performance of the intended building, and fix the
price.
74. Project Definition.
- The design-builder joins with the owner in the
establishment of overall project objectives,
requirements, and target budgets and schedules.
Design is started by the design-build entity, and
design decisions proceed along with consideration
of construction factors. The work is carried out
as defined in the contract.
8 5. Design-Build Contract Award.
- Well before the drawings are complete, often as
early as the concept phase, a lump sum price (or
guaranteed maximum cost) is established by the
design-build entity. This is typically done on an
"open book" basis where competitive pricing is
obtained from subcontractors and vendors in the
marketplace. If the owner is content with the
design and price proposal, the design-builder is
contracted for the completion of design and
construction.
9 6. Construction Documents and Construction.
- Upon completion of the design documents for all
elements or for specific phases of the project,
construction commences. The review and approval
process is structured (typically 30-60-90- 100
design complete) to ensure that the owner has the
say also in the subsequent design process. The
process continues in the customary manner but is
enhanced by the incorporation of design and
construction responsibility.
10(No Transcript)
11Two-stage selection
- DescriptionTwo-stage selection refers to a
design-builder selection process where the first
phase involves shortlisting of candidates on the
basis of the qualification statements they
supply, and the second phase involves final
selection on the basis of technical and price
proposals, etc. from the shortlisted offerors.
12 1. Strategic Facility Planning.
- The owner identifies the prospective project in
broad business terms needs are established in
terms of project area, population, technology
content, performance criteria, etc. A site may or
may not have been identified. The owner also
determines that design-build, and this process
specifically is the desirable mode of propagation
for the project.
132. Project Definition.
- The owner establishes the project requirements
in terms of facility size and performance
criteria, finish requirements, quality standards,
applicable codes, regulatory standards,
occupants/ capacities, equipment requirements,
etc. These requirements are defined and
articulated either by in-house professional staff
or by an outside consultant.
143. Request for Qualifications (RFQ).
- Professional, financial and experiential
requirements for offerors as well as general
project parameters are articulated in an RFQ (see
Table 10), either by in-house staff or by an
outside professional consultant. - 4. Qualifications Statements. The project is
advertised, RFQ.s are supplied to interested
design-builders, and qualification statements are
received in response to RFQs. Generally three,
never more than five, of the most qualified firms
are shortlisted for the second stage.
155. Request for Proposals (RFP).
- Design and cost proposals are solicited from the
shortlisted design-build teams in a Request for
Proposal (RFP). Among the items found in a
typical RFP are project design criteria, site
information, contract requirements, selection
procedure and proposal requirements. (see Table
11). - 6.Pre-Proposal Conference. This meeting of all
shortlisted proposers early in the proposal
preparation period is held by many owners to
allow proposers to ask questions and request
clarifications. Outside the meeting, only written
questions and answers are allowed in order to
treat all competitors equally.
167. Proposal Submission and Evaluation.
- Once received, proposals are evaluated on the
basis of quality of design, price and other
predetermined factors related to definition of
best value. Before the final award is made,
proposers may be asked to make inperson
presentations to the owners selection panel. - 8. Contract Award. The selected proposer enters
into contract with the owner, which incorporates
both the owners requirements and the
design-builders proposal.
17 9. Construction Documents and Construction.
- Upon completion of the design documents for all
elements or for specific phases of the project,
construction commences. The review and approval
process is structured (typically 30-60-90- 100
design complete) to ensure that the owner has the
say also in the subsequent design process. The
process continues in the customary manner but is
enhanced by the incorporation of design and
construction responsibility.
18(No Transcript)
19(No Transcript)
20(No Transcript)
21 HANORARIUM
- An honorarium or a stipend is a certain sum
sometimes paid to offerors in consideration for
the cost of preparing a design-build proposal.
When should an honorarium be paid, how much
should it be, and what else should be taken into
account when contemplating honorariums in a
project? The payment of an honorarium is,
however, up to the owner and in many cases no
stipend is paid to unsuccessful teams. In such
situations the construction firm, operating in
accordance with a design-build teaming agreement,
may pay its design team partner for preparing
most of the proposal, thus partially compensating
the A/E partner for its considerable effort in
preparing the design-build proposal. Moreover,
winning design teams of design-build projects
should demand and expect a higher than normal fee
for the balance of its services on the project in
the proposal phase.
22(No Transcript)
23(No Transcript)
24(No Transcript)
25Bridging-type selection
- Description
- Bridging-type selection refers to a process
where a firm price contract is made based on the
owner's preliminary design and candidates' price
offers, followed by the design-builder's
completion of design including possible
modifications on design and price, their review
and acceptation, and subsequently construction.
26 1. Strategic Facility Planning.
- The owner identifies the prospective project in
broad business terms needs are established in
terms of project area, population, technology
content, performance criteria, etc. A site may or
may not have been identified. The owner also
determines that design-build, and this process
specifically is the desirable mode of propagation
for the project.
27 2. Involvement of an Architect.
- The owner hires an architect to complete
preliminary design of the project. These
.scope-of-work. documents define the functional
and aesthetic aspects of the project, while the
details of construction technology are left for
the design-build team to define. The owners
architect remains a consultant to the owner
throughout the design and construction.
28 3. Selection of Design-Builder.
- The owners consultant prepares an extensive
Request for Proposal and, subsequently, bids are
solicited from (or negotiations are initiated
with) design-build entities. The design-builder
is usually selected on the basis of a price
offer, possibly supplemented by qualification
criteria. No technical proposal is needed in this
stage. - 4.Conclusion of Contract. Typically, a firm price
contract is completed. While the price covers all
design and construction, the contract commonly
authorizes the design-build entity to complete
the design and construction documents only, so
that thereafter the parties have a check point on
the modifications.
29 5. Completion of the Project Documents.
- The design-build entity executes design
sufficient to define the project, describe the
performance of the intended building, and price
the possible changes. The owner and his
consultant review the construction documents for
compliance with the design intent and conducts a
price review with the contractor. Normally,
notice to proceed with construction is given.
30 6. Construction Documents and Construction.
- Upon completion of the design documents for all
elements or for specific phases of the project,
construction commences. The review and approval
process is structured (typically 30-60-90- 100
design complete) to ensure that the owner has the
say also in the subsequent design process. The
process continues in the customary manner but is
enhanced by the incorporation of design and
construction responsibility.
31(No Transcript)
32(No Transcript)
33Direct design-build
- Description
- Direct design-build refers to the practice,
where the design-builder becomes involved in the
project prior to the start of the actual design
phase on the basis of the owner's predesign
information such as feasibility studies or maybe
a project program.
34 35Under a direct design-build arrangement, there
are two typical ways to proceed
- Firstly, it is not unusual for the initial
program definition services to be performed on
the basis of an oral understanding or a simple
letter of agreement ?a more complete contract is
developed once the project is better defined.
Thus, after the first contact and discussions on
the project, the design-builder works for project
planning with the understanding that if the owner
is happy with the design-builder.s proposal, the
design-builder will be engaged to do subsequent
design and construction. The proposal work is
generally part of the marketing of the
design-builder which is not properly compensated
for by the owner.
36- Alternatively, the owner may enter into contract
with the design-builder relatively promptly
instead of negotiating about the design-builders
evolving proposal. Typically the agreement
authorizes the design-build entity to do
preliminary design and outline specifications
only to provide the owner a checkpoint before
committing himself to completing the project. New
negotiations are then needed on the basis of the
design-builders proposal. Since the work is
based on a contract, the deliverable by the
design-builder in the initial phase may be
considered to be more complete than that made on
the basis of the negotiated approach.
37 38(No Transcript)
39Design criteria method
- Description
- Design criteria-type design-build refers to the
practice, where the design-builder becomes
involved in the project on the basis of the
owner's design criteria that define the owners
requirements and wishes and direct the subsequent
design process, but do not dictate the
architectural and technical solutions.
40(No Transcript)
41- In a design-build project according to the
design criteria method, the owner prepares a
statement of facility requirements that directs
the design-builders. subsequent proposal design
and is comprehensive enough to assure compliance
by the offerors, but avoids restrictive details
that would inhibit creative solutions. This means
that the owners design professional improves the
general project scope definitions and space
itemization from the programming phase which
results in the owners design criteria package.
42The design criteria package consists typically
of
- site plan and information
- space program including a schedule of rooms
with their type/use, number and area - room-specific criteria for finishes, fixtures
and fittings, services and environment - outline specification for components to be used
- diagrammatic floor or space plans, or schematic
design, and - other pertinent criteria.
43- The completed criteria package is incorporated
into the owners business elements as regards the
project. In competitive design-builder selection
the combination forms the Request for Proposals
(RFP). Correspondingly, business elements include
contractual terms and conditions, time and place
for receipt of proposals, schedule requirements,
bid and contract bond requirements, and basis for
evaluation and selection.55 A framework for an
entire RFP was given above in Table 11 (p. 51) in
the context of competitive two-stage
design-builder selection. Table 21, again,
details an actual RFP which includes the design
criteria of Table 20 referred to earlier.
44(No Transcript)
45(No Transcript)
46(No Transcript)
47Preliminary engineering method
- Description
- Preliminary engineering-type design-build refers
to the practice, where the design-builder becomes
involved in the project on the basis of a
preliminary design solution, which defines the
shape, massing and layout of the prospective
building, and may give strict guidelines or
solutions for many technical components of the
project.
48(No Transcript)
49- The design-build RFP specifications often
combine elements of design and performance while
the owners consultants often carry out the
schematic design phase and continue into the
design development phase, and maybe even
partially into the construction document phase.
Design development as a phase refers, again, to
evolution of design that defines the functional
and aesthetic aspects of the project and the
building systems that satisfy them.
50Therefore, in addition to documents of earlier
design phases, also the following elements are
often completed before the design-builders
involvement
- architectural drawings that include floor
plans, elevations and sections. - technical design where the structural,
mechanical, and electrical systems are developed
by selecting the type of systems, etc. - Additionally, many details can be designed and
many materials specified (cf. Table 23).
Naturally, the primary aim is still that the
building is defined in terms of performance
specifications that merely set forth the
operational characteristics or end result
desired, without saying how that result has to be
achieved or the product constructed. It may be,
however, that the owner designs the systems and
components that are critical to him but leaves
the others alone. Thus, the preliminary
engineering method does not mean that the owner
would progress in all design areas and
disciplines equally although some of the design
aspects of the building were closed.
51(No Transcript)
52(No Transcript)
53(No Transcript)