Title: The LHC Beam Position System
1The LHC Beam Position System
Ad-hoc Working Group on LHCÂ Experiment-Machine
Parameter and Signal Exchange 26th March
2002 Rhodri Jones (SL/BI)
2LHC BPM System - General
- 100 Warm, Button Electrode BPMs (LEP) for TI2
TI8 - 922 Button Electrode BPMs (24mm) for Arc DS
- 44 Warm Button Electrodes BPMs for IR3 IR7
- 44 Enlarged Button BPMs (34mm) for IR1,2,5 8
- 24 Directional Couplers for IR1,2,5 8
- 24 Special BPMs for Transverse Damper, Tune
Chromaticity Measurements in IR4 - 1 BPTX timing pick-up per incoming beam for
IR1,2,5 8 - Total of 1166 BPMs for the LHC and its Transfer
Lines
3The Arc BPM - SSS Layout
4Arc BPM - Button Feedthrough
Button Feedthrough
Beam Screen
Liquid Helium Cooling Capillary
5Interaction Region BPMs
Liquid Helium Capillaries
Stripline Electrode
Q2 Coupler
- Stripline length 120mm to give same response as
button - 2 Types
- Warm Coupler - capable of withstanding bake-out
to 200C - Cold Coupler - located in Q2 cryostat (tilted by
45 for cryostat integration) - Directivity measured as 28dB at 200MHz
6The Front-End Electronics
7The Wide Band Time Normaliser
A
B
8The Wide Band Time Normaliser
A (B 1.5ns)
A
B
9The Wide Band Time Normaliser
A
B
A(B1.5ns)
B(A1.5ns)10ns
Interval 10 ? 1.5ns
System output
10The Wide Band Time Normaliser
11WBTN - Linearity v Intensity
For LHC Arc BPMs 1 130mm
12WBTN - Linearity v Position
For LHC Arc BPMs 1 130mm
13The LHC BPM Acquisition System
Tunnel
Surface
14Accuracy and Resolution
15Timing Pick-up for the Experiments(BPTX)
- Located 150m from the IP in front of the D2
Magnet - One BPTX either side of the IP on the incoming
beam - Exclusively used by the experiments
16BPTX Requirements?
- Choice of Pick-up?
- Stripline Coupler?
- Peak voltage (one button) of 20V after 200m of
cable for nominal bunch - Peak voltage (one button) of 1V after 200m of
cable for pilot bunch - Button Electrode BPM?
- Peak voltage (one button) of 5V after 200m of
cable for nominal bunch - Peak voltage (one button) of 250mV after 200m of
cable for pilot bunch - Other Type of Pick-up?
- Type of Signal?
- Sum signal (sum of all 4 pick-up electrodes ? 2 ?
peak voltage)? - Virtually independent of position requires only
1 cable - Sum and Delta Signal?
- Requires 3 cables to give sum, horizontal
position vertical position - Other Type of Signal?
17Next Steps
- SL/BI will supply
- 2 BPTX Pick-ups per Experiment
- Choice of pick-up in collaboration with
Experiments - Experiments responsible for
- Cabling
- All machine cabling to be defined by 15th March
2002! - All machine cabling to be ordered by 15th May
2002 - Any subsequent electronics
- Keep in mind radiation resistance for
electronics in the tunnel