Phase 2 Detailed Design Review 7 November 2006 - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

Phase 2 Detailed Design Review 7 November 2006

Description:

Filtrate to Return Flow Pump Station. Biosolids to Landfill or ... Receives partially digested and consolidated sludge from stage 1. Mixing/Aeration as required ... – PowerPoint PPT presentation

Number of Views:117
Avg rating:3.0/5.0
Slides: 34
Provided by: Don1111
Category:

less

Transcript and Presenter's Notes

Title: Phase 2 Detailed Design Review 7 November 2006


1
Phase 2 Detailed Design Review 7 November 2006
BEACHLANDS-MARAETAI WWTP UPGRADE
2
DESIGN INTRODUCTION
  • Meet or exceed consent conditions
  • Design from 4,300PE to 10,000PE
  • Best available technology
  • Minimizing whole life costs
  • Valued asset for the future

3
CONSENT DISCHARGE QUALITY
4
DESIGN FLOWS
5
DESIGN INFLUENT QUALITY
6
PROCESS FLOW DIAGRAM
7
WASTE SOLIDS FLOW DIAGRAM
8
3mm SCREENS
  • New Hydropress SSL 2000x865x3 3mm step screen
  • Sindico SP150/900 screw press dewatering
  • Rock trap prior to screen
  • Existing 3mm step screen as standby

9
VORTEX GRIT REMOVAL
  • New 270 vortex grit removal system
  • Huber RoSF3 LOC Coanda grit classifier

10
BIOFILTER
  • Air ducting from inlet works to biofilter for the
    removal of malodorous air
  • Duty/standby Extraction fan

11
STORM FLOW BUFFER
  • New 6000m3 flow buffer
  • Existing actuated control valves
  • Mixing and aeration as required
  • Duty/standby variable speed submersible pumps
  • HDPE lined with concrete step access
  • Manual cleaning with hose reels

12
BIOLOGICAL PROCESS LAGOON ZONES
Anoxic Zone 1
Post-Denitrification Zone 5
Anoxic Zone 2
Reaeration Zone 6
Anoxic Zone 3
Aerobic Zone 4
13
BIOLOGICAL PROCESS LAGOON FLOWS
14
BIOLOGICAL PROCESS LAGOON INPUTS
Secondary Treated Wastewater
Alum
Screen Wastewater RAS Return Flows Biofilter
Drainage Storm Flow Buffer Methanol Lime
Methanol
Internal Recycle
15
AERATION SYSTEM DESIGN 4300PE
NO3-
pH
DO
DO
16
AERATION SYSTEM DESIGN 10,000PE
NO3-
pH
DO
DO
17
BIOLOGICAL PROCESS DESIGN PARAMETERS
18
CLARIFIER
  • 16m diameter
  • 4.5m sidewall depth
  • Sludge and scum scraper
  • RAS pump station
  • Scum pump station

19
POST TREATMENT BUFFER
  • Approximately 9,700m3
  • Post treatment buffer return pump station
  • Effluent Flow Control Valve
  • Maximum daily discharge reached
  • High flow
  • Low flow

20
DISK FILTER
21
UV DISINFECTION
  • WEDECO UV Disinfection System
  • 2 open channels
  • 4 banks of 24 lamps

22
CHEMICAL DOSING SYSTEMS
  • Methanol
  • Denitrification Zone 5
  • Anoxic Zone 1
  • Lime
  • Anoxic Zone 1
  • Alum
  • After biological treatment
  • Pre-filtration

23
CHEMICAL DOSING SYSTEMS
Minimum is based on good quality return flows and
average conditions Maximum is a one day rate
based on poor quality return flows and peak
conditions
24
ANAEROBIC DIGESTER STAGE 1
  • Reconfigure PALs 1 and 2
  • WAS introduced
  • Introduction of Kawakawa Bay WWTP sludge into
    Stage 1
  • Mixing/Aeration as required
  • Lime Dosing
  • Supernatant overflows to Supernatant Pump Station

25
FLUMP
  • Automated sludge removal from stage 1 to stage 2
  • Also provides sludge mixing

26
ANAEROBIC DIGESTER STAGE 2
  • Receives partially digested and consolidated
    sludge from stage 1
  • Mixing/Aeration as required
  • Supernatant overflows to Supernatant Pump Station
  • Sludge is manually removed for dewatering after
    liquid layer is removed

27
SRTs FOR DIGESTERS
Allows one week for sludge transfer
28
SAND DRYING BED
  • 3 sand drying beds
  • 200mm thick sludge depth
  • Dewatered to gt20 dry solids

29
RETURN FLOW PUMP STATIONS
  • Supernatant Pump Station
  • Return supernatant from Anaerobic Digesters to
    Biological Process
  • Transfer supernatant from stage 2 to stage 1
    during sludge transfer operations
  • Return Flows Pump Station
  • Disk Filter backwash water
  • Sand Drying Bed filtrate

30
REUSE WATER PUMP STATION
  • Provides reuse water for process requirements and
    wash down
  • Fill pump
  • Storage tank
  • Booster pumps

31
CONTROL SYSTEM
  • PLC
  • SCADA
  • Telemetry

32
CONSTRUCTION
  • Stage 1 Off line Inlet works and Storm Buffer
  • Stage 2 Offline construction of clarifier,
    pumping stations, tertiary filter, post treatment
    buffer and stage 1 anaerobic digester
  • Stage 3 Existing Lagoon 1 taken offline for
    partition construction and aeration system
    installation. Use Stage 1 anaerobic digester to
    replicate existing biological process
  • Stage 4 Stage 2 anaerobic digester

33
COMMISSIONING SEQUENCING
  • Storm flow buffer
  • Clarifier, RAS/WAS, tertiary filter, chemical
    dosing systems, post treatment buffer
  • Biological process
  • Solids treatment systems
  • 3 month commissioning period
Write a Comment
User Comments (0)
About PowerShow.com