BENEFITS FROM EARLY SYSTEM VALIDATION TESTS ON ATV PROGRAM - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

BENEFITS FROM EARLY SYSTEM VALIDATION TESTS ON ATV PROGRAM

Description:

Docking to the Russian ISS part. Cargo. Propulsive support ... limited to mature functions ( basic TM/TC, encryption, first use of live TDRS and ARTEMIS) ... – PowerPoint PPT presentation

Number of Views:24
Avg rating:3.0/5.0
Slides: 18
Provided by: murielle4
Category:

less

Transcript and Presenter's Notes

Title: BENEFITS FROM EARLY SYSTEM VALIDATION TESTS ON ATV PROGRAM


1
BENEFITS FROM EARLY SYSTEM VALIDATION TESTS ON
ATV PROGRAM
  • Pascale FLAGEL
  • ATV Operations
  • French Space Agency
  • Toulouse
  • France

The ATV Control Center development and the ATV
operations definitions are conducted by CNES
Toulouse Space Center, under contracts with the
European Space Agency (ESA).
2
Overview
  • Introduction to ATV program and system
  • ATV System Validation Tests ( SVT) campaign
  • SVT schedule and status
  • Early SVT feedback

3
ATV Program presentation
  • European contribution to ISS
  • Unmanned spacecraft
  • Docking to the Russian ISS part
  • Cargo
  • Propulsive support
  • Refueling
  • Destructive return flight

4
ATV system
ATV
ISS
GPS
Localisation
TDRSS
TDRSS
ISS data
Artemis
Telemetry and Telecommand
Via WhiteSand and MCC-H
ISS Control Center Moscow
Via Redu
ATV Control Center CNES Toulouse- FRANCE
ISS Control Center Houston
Operational co-ordination ATV and ISS data
exchanges
5
ATV System Validation tests definition -1
  • ATV SVT system test campaign to validate
    technically and operationally interface between
    the vehicle and the control center.
  • SVT TEST MEANS
  • 1) Vehicle
  • 1st flight model itself JULES VERNE
  • or
  • a very representative hardware in the loop
    simulator --- main means used for vehicle
    functional validation --- located in Les Mureaux
    ( FRANCE) in EADS facilities

6
Jules VERNE 1st Flight Model
  • Located in
  • BREMEM Germany EADS integration facilities
  • or
  • ESTEC- Nederland ESA integration facilities
  • or
  • KOUROU- French Guyana Launch campaign

7
ATV Simulator --- FSF
8
ATV System Validation tests definition -2
  • SVT TEST MEANS
  • 2) ATV Control Center in CNES facilities in
    Toulouse FRANCE
  • Test scenario prepared by the future operational
    team
  • As far as possible based on operational products
    use
  • Pre-validated with a vehicle simulator (AGCS)
    designed for the control center operational
    qualification.

9
ATV Control Center
  • photo

10
ATV System Validation tests definition -3
  • SVT TEST MEANS
  • 3) link between the vehicle and ATV-CC
  • 1 SVT objective is to validate this operational
    link
  • NASA TDRS constellation
  • ESA ARTEMIS satellite
  • IGS ESA ground network
  • Some tests use live TDRS, ARTEMIS, IGS ----
    heavy
  • Some tests use a ground network configuration
    dedicated for tests

11
FSF- ATV simulator Les Mureaux EADS
ATV Flight Model
BREMEN or ESTEC or KOUROU
Columbus Control Centre (Col-CC)
IGS
Redu
WhiteSandsComplex
12
ATV System Validation tests organisation
  • Under ESA responsibility system lead
  • Overall objectives definition and commitment
  • Coherency of SVT / ATV master planning
  • CNES test lead --- as Control Center and
    operations prime contactor
  • Test detailed definition and implementation
  • Test conduct
  • With vehicle manufacturer support ( EADS)
  • SVT planning, objectives, tests results ---
    reviewed and managed by a SVT working group (
    ESA, CNES, EADS, DLR) chaired by ESA.

13
ATV System Validation tests schedule and status-1
  • SVT objectives spread over 9 testing slots of 2
    to 7 days
  • Planning critical tests means --- SVT run in
    double shifts (from 6h to 14h and from 14h to
    22h).
  • First step (4 SVT slots -- Nov03 to May 04)
  • planning constraints --- decision to keep SVT
    schedule even if tests run on system under
    development
  • limited to mature functions ( basic TM/TC,
    encryption, first use of live TDRS and ARTEMIS)
  • non validating tests
  • challenging but successful

14
ATV System Validation tests schedule and status-2
  • Second step (2 SVT slots -- Dec 04 and June 05)
  • decision to run only validating tests
  • only mature functions tested
  • pragmatic approach
  • Third step (3 SVT slots to run until launch)
  • more conventional approach
  • testing on definitive configurations
  • large objectives

15
Early testing feedback -1
  • First and second steps of ATV SVT campaign were
    run very early in the program
  • Non conventional
  • Challenging but very fruitful
  • Early interface testing
  • Helpful debug, particularly beneficial on a non
    recurrent system to secure the development
    planning

16
Early testing feedback -2
  • Early assessment of operations
  • First implementation of non recurrent operations
    concepts
  • Very useful to finalize their definition
    according to a pragmatic experiment
  • Powerful and motivating driver
  • Excellent driver to push all prerequisite
    activities necessary to a first system test
  • Heavy motivation for all teams to reach a first
    concrete results after several years of design
    activities

17
Conclusion
  • early system validation testing is very
    beneficial for non recurrent and complex system
  • like a mock-up, it allows to secure the
    development and the operational concept
    definition
  • on ATV program, SVT campaign has now standard
    very ambitious objectives they will prepare us
    for operations.