ATST M1 ASSEMBLY Procurement Strategy Documentation Cost

Description:

Representatives from Schott and Corning visited NOAO/NSO in early 2005 to ... Corning capable of producing M1 blank in 18-20 months (DCT recent example) ... – PowerPoint PPT presentation

Number of Views:90
Avg rating:3.0/5.0
Slides: 10
Provided by: RPr8
Category:

less

Transcript and Presenter's Notes

Title: ATST M1 ASSEMBLY Procurement Strategy Documentation Cost


1
ATST M1 ASSEMBLYProcurement Strategy
DocumentationCost Schedule
  • Ron Price
  • October 28, 2005

2
Procurement Strategy
  • M1 Blank
  • ATST will procure the M1 Blank as a separate item
    and supply to polisher/M1 Assembly fabricator
  • Early procurement efforts continue
  • M1 Assembly
  • Final design and construction of the M1 Assy will
    be performed by an outside contractor based on
    the M1 Assembly Specification, associated
    Interface Control Documents (ICDs) and
    supplemented by ATST reference design work
    analysis

3
M1 Blank Procurement
  • On-going contact with Schott and Corning since
  • 2002
  • ROM quotes with updates have been received from
    both vendors for costing
  • Schedule M1 on critical path - potential of
    early funding from Air Force for purchase of M1
    blank in 2006
  • Procurement documentation is being drafted

4
M1 Blank Procurement Vendor Status
  • Representatives from Schott and Corning visited
    NOAO/NSO in early 2005 to discuss M1 blank fab
    capabilities
  • Corning
  • Existing fabrication facilities
  • Recently completed 4 meter DCT blank - September
    2005
  • Schott
  • Existing fabrication facilities some scheduling
    issues
  • Have sold off existing 4 meter class blanks
  • May begin fab of one or two 4 meter class blanks
    on speculation in 2006

5
M1 Blank Procurement Documentation
  • Draft documentation for M1 procurement completed
  • Selection Plan
  • M1 Blank Specification
  • M1 Blank Statement of Work
  • M1 Blank drawing

6
M1 Blank Procurement Cost Schedule
  • Cost
  • No significant change to latest ROM quotes
    received other than inflation
  • Schedule
  • Assuming 2 years for M1 blank fab and 3 years for
    M1 polishing in schedule
  • Corning capable of producing M1 blank in 18-20
    months (DCT recent example)
  • Schott significantly longer time required due
    to start from scratch scenario

7
M1 Assembly Procurement
  • Approach - Final design and Construction of M1
    Assy will be performed by outside contractor
    based on the M1 Assembly Specification,
    associated Interface Control Documents (ICDs)
    and ATST design work
  • On-going contact with potential fabricators since
    2002
  • ROM quotes have been received from vendors for
    costing Design Evaluation and Cost Studies
  • Reference Design Studies and Analysis ATST
    design and analysis work will be captured in an
    RDSA document and provided as supplemental
    information to contractor.
  • Acceptance test plan will be developed by ATST,
    negotiated with contractor and executed at
    contractor facility.

8
M1 Assembly Procurement Vendor Status
  • Potential Vendors identified in 2002
  • List includes
  • Brashear LP
  • EOST
  • Goodrich Corp
  • SAGEM/Reosc

9
M1 Assembly Procurement Cost Schedule
  • Cost
  • Inflation increases (4 to 5)
  • Additional requirements
  • M1 surface figure testing at two zenith angles
  • Schedule
  • Assuming 3 years for M1 Assembly design, fab,
    test and delivery to site
  • No changes to date