Offtake Arrangements Document An Overview - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Offtake Arrangements Document An Overview

Description:

Site Safety Rules. Safe access and operation of personnel on a Offtake Site ... Admission, Withdrawal and Termination of Parties ... – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 19
Provided by: busin67
Category:

less

Transcript and Presenter's Notes

Title: Offtake Arrangements Document An Overview


1
Offtake Arrangements Document An Overview
Paul Roberts 12th May 2005
2
Scope of Offtake Arrangements Document
  • Sets Out Technical and Operational Details
    Relating to Gas Flows
  • from NTS to LDZs
  • from one LDZ to another LDZ

NTS
NTS/LDZ Offtake
Distribution Network (DN)
3
Section A. Scope and Classification
  • Parties
  • (1) Transco NTS as NTS owner and operator
  • (2) Each DNO as DN owner and operator (including
    Transco)
  • System and Offtake Definitions
  • Classification of Systems and Points on Systems
  • Recording of Specific Details in Supplemental
    Agreements

4
Section B. Connection Facilities
  • Covers Land, Equipment and Buildings at each
    Offtake Site
  • Measurement Equipment (detailed in Section D)
  • Telemetry (detailed in Section E)
  • Rights Granted to Site Users
  • Retention, installation, modification and
    replacement of its equipment
  • Access rights
  • Compatibility of Both Parties Equipment
  • Decommissioning of an Offtake
  • Supplemental Agreement
  • Schematic of Connection Facilities - Point of
    Offtake
  • Land diagram
  • Details Ownership, Equipment Specification of
    Connection Facilities
  • Site Services for Site Users

5
Section B. Connection Facilities
Typical NTS/LDZ Offtake Configuration
Meters
Flow or pressure control
Distribution Network
Odorant injection
Demarcation Point The Offtake
Majority of equipment at Offtake Site owned and
operated by DN
NTS Feeder
6
Section C. Safety and Emergency
  • Gas Supply Emergencies
  • Development and compliance with Emergency
    Procedures E1, E2, E3
  • Participation in procedure testing - planned by
    NTS
  • Safe Control of Operation (SCO) Interface
    Procedure
  • Safe conduct of works or operations
  • Site Emergency Procedures
  • Requirements to satisfy legal requirements (eg.
    COMAH, Pipeline Safety Regs)
  • Site Safety Rules
  • Safe access and operation of personnel on a
    Offtake Site
  • Existing Gas Supply Emergency Procedures
  • E1 - Network Gas Supply Emergency Procedures
  • E2 - Local Gas Supply Emergency Procedures
  • E3 - Detailed Internal Procedures to ensure
    compliance with E1/E2

7
Section D. Measurement
  • Responsibility
  • Downstream party responsible for measurement and
    data provision
  • Measurement standards
  • Measurement data and accuracy - Annex D-1
  • Best practice recommendations and technical
    standards Annex D-2
  • Validation
  • Routine every 12 months at downstream partys
    cost
  • Exceptional at upstream partys request
  • Fault management
  • Failure notification and rectification
  • Measurement correction/estimation
  • Access to records
  • Supplemental Agreement
  • Actual uncertainty limits and flow ranges for
    measured parameters

8
Section E. Telemetry
  • Operational Data Flows
  • required by upstream party for safe and efficient
    operation of its System
  • Annexes specify standard telemetry signals,
    protocols, resilience
  • Telemetry Failure
  • process for resolution
  • During SOMSA
  • DN transmits signals to NTS via satellite
  • Post SOMSA
  • Rights for NTS to install own telemetry on
    Offtake Site
  • DN obligation to provide signals to NTS telemetry
    equipment
  • Supplemental Agreement
  • Variations to default telemetry signals,
    resilience and protocols

9
Section F. Calorific Value
  • Responsibility
  • DNO obligation under Gas (Calculation of Thermal
    Energy) Regulations to determine daily CV for
    each LDZ based on daily average CVs for LDZ input
    and offtake points
  • Daily CV determination
  • Basis on which Transco NTS will determine daily
    CVs for DNOs up to 31 March 2007
  • CV Shrinkage Costs
  • Cooperation to avoid or minimise CV Shrinkage

10
Section G. Maintenance
  • Defines Relevant Maintenance to be planned and
    co-ordinated
  • Safety Relevant Maintenance
  • can only be carried out safely if affected
    parties aware
  • Flow Relevant Maintenance
  • NTS maintenance likely to impact upon ability to
    make gas available for offtake
  • Measurement Equipment Maintenance
  • Urgent Maintenance
  • Maintenance Planning
  • 2 year planning cycle - timescales in Annex G-2
  • Final programmes in March, updated in September
  • Revisions at 5 days notice, except for safety
    reasons subject to payment of other parties works

11
Section H. NTS Long Term Planning
  • Exchange of demand information
  • facilitate production of system development
    statements by the transporters in accordance with
    licence obligations
  • Information to be exchanged
  • Historic and forecast demand for DM/NDM
    firm/interruptible loads
  • Detailed in Annex H-1
  • Timescales for information provision

12
Section I. NTS Operational Flows
  • Provision of Offtake Profile Notices (OPNs)
  • Receipt of initial OPN and subsequent revisions
    requested by DN/NTS
  • Offtake tolerances
  • Within day pressure
  • Pressures which Transco NTS will make available
    between Applicable Offtake Pressures at 0600 and
    2200 on reasonable endeavours basis
  • Interruption
  • Process by which Transco NTS may require
    interruption of LDZ Interruptible Supply Points
  • Exchange of information regarding LDZ
    Interruptible Supply Points
  • DNO reimbursement to Transco NTS for relevant
    interruption payments it makes to Users
  • Demand forecasts
  • Provision by DNO to Transco NTS of updated demand
    forecasts

13
Section J. LDZ/LDZ Offtake Planning and
Operational Flows
  • Provision of Offtake Profile Notices (OPNs)
  • Receipt of initial OPN and subsequent revisions
    requested by downstream DNO
  • System Planning
  • Information provision and timescales
  • Setting of Offtake Parameter Values
  • Maximum Daily Quantity
  • Maximum Offtake Rate
  • Minimum Offtake Pressure
  • Preparation of Offtake Parameter Statement by
    upstream DNO
  • Offtake Parameter Values for LDZ/LDZ Offtakes for
    Gas Years 1-5
  • Indicative Offtake Parameter Values for Gas Years
    6-10
  • Establishment of rights to use Close offtakes

14
Section K. LDZ System Entry Points
  • Applicability
  • Existing LDZ System Entry Points
  • Capacity Allocation by Transco NTS
  • Auction Obligated Incremental NTS Entry Capacity
    as per licence obligation
  • Auction Incremental NTS Entry Capacity as per DNO
    instruction
  • Surrender and Curtailment
  • DNO to accommodate nominated flows in accordance
    with capacity held by shippers
  • If DNO unable to accommodate
  • may instruct NTS to give interruptible
    curtailment notice or buy back
  • Section I liabilities incurred by NTS reimbursed
    by DNO

15
Section L. Cost Recovery and Invoicing
  • Covers arrangements for adhoc recoverable costs
  • Invoicing and payment processes

16
Section M. Information Flows
  • Offtake Communications Document
  • Cover Transporter to Transporter information
    exchange
  • for purposes of OAD and/or UNC
  • Specifies
  • information to be exchanged (data, reports,
    notices, ..)
  • requirement for information
  • Party responsible for information provision
  • format of information
  • time/frequency of provision
  • means of provision

17
Section N. General
  • Admission, Withdrawal and Termination of Parties
  • Supplemental Agreements Execution and Amendment
  • upstream party responsible for drafting
  • Information and Confidentiality
  • Supplemental Agreements confidential
  • Liabilities
  • Each Party bears its own loss, except where
    otherwise stated
  • Dispute Resolution
  • Other Legal Boiler Plating

18
Offtake Arrangements Document An Overview
Paul Roberts 28h February 2005
ERF02
Write a Comment
User Comments (0)
About PowerShow.com