Title: Offtake Arrangements Document An Overview
1Offtake Arrangements Document An Overview
Paul Roberts 12th May 2005
2Scope of Offtake Arrangements Document
- Sets Out Technical and Operational Details
Relating to Gas Flows - from NTS to LDZs
- from one LDZ to another LDZ
NTS
NTS/LDZ Offtake
Distribution Network (DN)
3Section A. Scope and Classification
- Parties
- (1) Transco NTS as NTS owner and operator
- (2) Each DNO as DN owner and operator (including
Transco) - System and Offtake Definitions
- Classification of Systems and Points on Systems
- Recording of Specific Details in Supplemental
Agreements
4Section B. Connection Facilities
- Covers Land, Equipment and Buildings at each
Offtake Site - Measurement Equipment (detailed in Section D)
- Telemetry (detailed in Section E)
- Rights Granted to Site Users
- Retention, installation, modification and
replacement of its equipment - Access rights
- Compatibility of Both Parties Equipment
- Decommissioning of an Offtake
- Supplemental Agreement
- Schematic of Connection Facilities - Point of
Offtake - Land diagram
- Details Ownership, Equipment Specification of
Connection Facilities - Site Services for Site Users
5Section B. Connection Facilities
Typical NTS/LDZ Offtake Configuration
Meters
Flow or pressure control
Distribution Network
Odorant injection
Demarcation Point The Offtake
Majority of equipment at Offtake Site owned and
operated by DN
NTS Feeder
6Section C. Safety and Emergency
- Gas Supply Emergencies
- Development and compliance with Emergency
Procedures E1, E2, E3 - Participation in procedure testing - planned by
NTS - Safe Control of Operation (SCO) Interface
Procedure - Safe conduct of works or operations
- Site Emergency Procedures
- Requirements to satisfy legal requirements (eg.
COMAH, Pipeline Safety Regs) - Site Safety Rules
- Safe access and operation of personnel on a
Offtake Site
- Existing Gas Supply Emergency Procedures
- E1 - Network Gas Supply Emergency Procedures
- E2 - Local Gas Supply Emergency Procedures
- E3 - Detailed Internal Procedures to ensure
compliance with E1/E2
7Section D. Measurement
- Responsibility
- Downstream party responsible for measurement and
data provision - Measurement standards
- Measurement data and accuracy - Annex D-1
- Best practice recommendations and technical
standards Annex D-2 - Validation
- Routine every 12 months at downstream partys
cost - Exceptional at upstream partys request
- Fault management
- Failure notification and rectification
- Measurement correction/estimation
- Access to records
- Supplemental Agreement
- Actual uncertainty limits and flow ranges for
measured parameters
8Section E. Telemetry
- Operational Data Flows
- required by upstream party for safe and efficient
operation of its System - Annexes specify standard telemetry signals,
protocols, resilience - Telemetry Failure
- process for resolution
- During SOMSA
- DN transmits signals to NTS via satellite
- Post SOMSA
- Rights for NTS to install own telemetry on
Offtake Site - DN obligation to provide signals to NTS telemetry
equipment
- Supplemental Agreement
- Variations to default telemetry signals,
resilience and protocols
9Section F. Calorific Value
- Responsibility
- DNO obligation under Gas (Calculation of Thermal
Energy) Regulations to determine daily CV for
each LDZ based on daily average CVs for LDZ input
and offtake points - Daily CV determination
- Basis on which Transco NTS will determine daily
CVs for DNOs up to 31 March 2007 - CV Shrinkage Costs
- Cooperation to avoid or minimise CV Shrinkage
10Section G. Maintenance
- Defines Relevant Maintenance to be planned and
co-ordinated - Safety Relevant Maintenance
- can only be carried out safely if affected
parties aware - Flow Relevant Maintenance
- NTS maintenance likely to impact upon ability to
make gas available for offtake - Measurement Equipment Maintenance
- Urgent Maintenance
- Maintenance Planning
- 2 year planning cycle - timescales in Annex G-2
- Final programmes in March, updated in September
- Revisions at 5 days notice, except for safety
reasons subject to payment of other parties works
11Section H. NTS Long Term Planning
- Exchange of demand information
- facilitate production of system development
statements by the transporters in accordance with
licence obligations - Information to be exchanged
- Historic and forecast demand for DM/NDM
firm/interruptible loads - Detailed in Annex H-1
- Timescales for information provision
12Section I. NTS Operational Flows
- Provision of Offtake Profile Notices (OPNs)
- Receipt of initial OPN and subsequent revisions
requested by DN/NTS - Offtake tolerances
- Within day pressure
- Pressures which Transco NTS will make available
between Applicable Offtake Pressures at 0600 and
2200 on reasonable endeavours basis - Interruption
- Process by which Transco NTS may require
interruption of LDZ Interruptible Supply Points - Exchange of information regarding LDZ
Interruptible Supply Points - DNO reimbursement to Transco NTS for relevant
interruption payments it makes to Users - Demand forecasts
- Provision by DNO to Transco NTS of updated demand
forecasts
13Section J. LDZ/LDZ Offtake Planning and
Operational Flows
- Provision of Offtake Profile Notices (OPNs)
- Receipt of initial OPN and subsequent revisions
requested by downstream DNO - System Planning
- Information provision and timescales
- Setting of Offtake Parameter Values
- Maximum Daily Quantity
- Maximum Offtake Rate
- Minimum Offtake Pressure
- Preparation of Offtake Parameter Statement by
upstream DNO - Offtake Parameter Values for LDZ/LDZ Offtakes for
Gas Years 1-5 - Indicative Offtake Parameter Values for Gas Years
6-10 - Establishment of rights to use Close offtakes
14Section K. LDZ System Entry Points
- Applicability
- Existing LDZ System Entry Points
- Capacity Allocation by Transco NTS
- Auction Obligated Incremental NTS Entry Capacity
as per licence obligation - Auction Incremental NTS Entry Capacity as per DNO
instruction - Surrender and Curtailment
- DNO to accommodate nominated flows in accordance
with capacity held by shippers - If DNO unable to accommodate
- may instruct NTS to give interruptible
curtailment notice or buy back - Section I liabilities incurred by NTS reimbursed
by DNO
15Section L. Cost Recovery and Invoicing
- Covers arrangements for adhoc recoverable costs
- Invoicing and payment processes
16Section M. Information Flows
- Offtake Communications Document
- Cover Transporter to Transporter information
exchange - for purposes of OAD and/or UNC
- Specifies
- information to be exchanged (data, reports,
notices, ..) - requirement for information
- Party responsible for information provision
- format of information
- time/frequency of provision
- means of provision
17Section N. General
- Admission, Withdrawal and Termination of Parties
- Supplemental Agreements Execution and Amendment
- upstream party responsible for drafting
- Information and Confidentiality
- Supplemental Agreements confidential
- Liabilities
- Each Party bears its own loss, except where
otherwise stated - Dispute Resolution
- Other Legal Boiler Plating
18Offtake Arrangements Document An Overview
Paul Roberts 28h February 2005
ERF02