PMI%20North%20Area%20PMP%20Exam%20Study%20Group - PowerPoint PPT Presentation

About This Presentation
Title:

PMI%20North%20Area%20PMP%20Exam%20Study%20Group

Description:

Roles and Responsibilities. Project Manager is integrator ... Having a project plan methodology. Keeping stakeholders and resource managers in the loop with ... – PowerPoint PPT presentation

Number of Views:72
Avg rating:3.0/5.0
Slides: 24
Provided by: z003571
Category:

less

Transcript and Presenter's Notes

Title: PMI%20North%20Area%20PMP%20Exam%20Study%20Group


1
PMI North Area PMP Exam Study Group
  • Integration Management Presentation
  • Prepared by Denise Robertson
  • 22 March 2003

2
Roles and Responsibilities
  • Project Manager is integrator
  • Team members responsibility to complete tasks,
    activities, and work packages.
  • Sponsor or senior managements responsibility to
    protect project from changes and loss of
    resources.

3
Project Plan Execution
  • Includes all efforts necessary to achieve work
    results and identify change requests.
  • PM must assume guiding proactive role constantly
    referring back to project plan.
  • Execution activities are not planning activities.

4
Project Plan Execution Activities
  • Implementing project plan
  • Completing work packages
  • Achieving work results
  • Committing project resources
  • Managing progress
  • Taking preventative actions
  • Soft skill application (guiding, assisting
    communicating, leading negotiating, etc.)
  • Authorizing work using work authorization system
  • Monitoring progress against baseline
  • Taking corrective action
  • Holding team meetings
  • acquiring info with PMIS
  • Monitoring progress against baseline
  • Taking corrective action
  • Holding team meetings
  • acquiring info with PMIS
  • Managing by exception to project plan
  • Identifying changes to be handled in ICC

5
Integrated Change Control
  • Major component of control phase focusing on
  • Meeting performance baselines
  • Making changes
  • Coordinating changes across knowledge areas
  • NB Many activities performed during the control
    phase of the project are NOT part of Integrated
    Change Control see Mulcahy text.

6
Project Plan Development
  • To develop a plan that is bought-into, approved,
    realistic and formal, the project manager must
    perform activities characterized by
  • Having a project plan methodology
  • Keeping stakeholders and resource managers in the
    loop with
  • Meetings
  • Schedule approval
  • Performing and acting on analysis of risks and
    impacts
  • Performing financial analysis
  • Crashing, fast tracking, presenting options to
    management
  • Setting up control plan including EVM system and
    PMIS

7
Project Plan
  • A project plan is a multi-page document created
    by the project manager based on input from the
    team and stakeholders that includes

Project charter budget
Project mgt approach schedule
Scope statement resources
WBS Change control plan/system
Responsibility chart/assignments Performance measurement baselines
Network diagram/major milestones Management plans scope, schedule, cost, quality, staffing, communications, risk response, procurement
8
Corrective (Pro)Action
  • Any actions done to bring expected future project
    performance in line with project plan
  • Accomplished by measuring performance and
    identifying root cause of variation
  • Root cause analysis
  • Schedule recovery
  • Cost recovery
  • Changes to risk
  • Changes to quality
  • Input to project plan execution
  • Output from ICC and all control processes

9
Hysterical Database
Historical information is used to plan and manage
future projects thus improving project
management. Such data or information includes
  • Lessons learned
  • Benchmarks
  • Risks
  • Resources needed
  • Correspondence
  • Tasks
  • WBS
  • Reports
  • Estimates
  • Project plans

10
Project Plan Updates
  • Output from Integrated Change Control
  • Result of controlling project to project plan
  • Requires a plan to exist to be controlled and for
    formal updates
  • Project plan is progressively elaborated even
    though PM will try to finalize during planning.

11
Lessons Learned
  • What was done right, wrong and would have been
    done differently
  • Technically
  • Project Management
  • Management

12
Constraints
  • Factors that may limit the project teams options
  • Organizational structure of performing
    organization
  • Collective bargaining agreements
  • Preferences of the project management team
  • Expected staff assignments
  • Cost
  • Time

13
Baseline
  • Original project plan with approved changes
  • Used to monitor progress of project
  • Basis of comparison for forecasts of final cost
    and schedule
  • May be changed by formal mechanisms with
    accompanying documentation

14
Change Control System
  • Collection of formal documented procedures,
    paperwork, tracking systems and approval levels
    for authorizing changes.
  • Plan for how changes will be managed
  • CCB creation
  • Hard procedures
  • Soft management practices

15
Change Control Board
  • Reviews change requests to determine if
    additional analysis is warranted
  • Approves and rejects changes
  • May include
  • PM
  • Customer
  • Experts
  • Sponsor
  • Others

16
Kickoff Meeting
  • Communications and coordination meeting of all
    parties to project
  • Customers
  • Sellers
  • Project team
  • Senior management
  • Agencies
  • Functional management
  • Sponsor
  • End of planning phase before beginning work on
    project
  • Topics
  • Introductions
  • Review of risks
  • Communications plan
  • Meeting schedule

17
Project Plan Approval
  • Signatures from management, stakeholders and the
    project team are required as formal approval.
  • Project cannot effectively start without formal
    approval.
  • If stakeholder needs and objectives have been
    identified in advance, it should be less
    difficult to obtain signatures really.

18
Work Authorization System
  • Formal procedure for sanctioning project work
    ensuring work is done
  • At right time
  • in right sequence
  • Controls gold plating
  • Defines tasks
  • May take form of WBS dictionary

19
Change Requests
  • Formal documents submitted by anyone on project
    after project plan is approved
  • Identified in project plan execution
  • Handled in integrated change control

20
Configuration Management
  • Rigorous change management as it relates to scope
  • Any documented procedure used to apply technical
    and administrative direction and surveillance to
  • ID and document functional and physical
    characteristics of an item or system
  • Control any changes to such characteristics
  • Record and report change and its implementation
    status
  • Audit the items and system to verify conformance
    to requirements

21
Project Management Information System (PMIS)
  • System set up in advance to keep PM informed of
    the status of all project tasks
  • May consist of
  • Automatic tools
  • Manual tools
  • Reporting
  • Meetings
  • Oral inquiries
  • Gantt charts

22
EVM
  • Earned Value Management is a technique used to
    integrate the
  • Project scope
  • Schedule
  • Resources
  • Measure and report project performance

23
Project Planning Methodology
  • Company standard procedures, forms, and
    guidelines for planning projects that everybody
    uses really.
Write a Comment
User Comments (0)
About PowerShow.com