Title: PMI%20North%20Area%20PMP%20Exam%20Study%20Group
1PMI North Area PMP Exam Study Group
- Integration Management Presentation
- Prepared by Denise Robertson
- 22 March 2003
2Roles and Responsibilities
- Project Manager is integrator
- Team members responsibility to complete tasks,
activities, and work packages. - Sponsor or senior managements responsibility to
protect project from changes and loss of
resources.
3Project Plan Execution
- Includes all efforts necessary to achieve work
results and identify change requests. - PM must assume guiding proactive role constantly
referring back to project plan. - Execution activities are not planning activities.
4Project Plan Execution Activities
- Implementing project plan
- Completing work packages
- Achieving work results
- Committing project resources
- Managing progress
- Taking preventative actions
- Soft skill application (guiding, assisting
communicating, leading negotiating, etc.) - Authorizing work using work authorization system
- Monitoring progress against baseline
- Taking corrective action
- Holding team meetings
- acquiring info with PMIS
- Monitoring progress against baseline
- Taking corrective action
- Holding team meetings
- acquiring info with PMIS
- Managing by exception to project plan
- Identifying changes to be handled in ICC
5Integrated Change Control
- Major component of control phase focusing on
- Meeting performance baselines
- Making changes
- Coordinating changes across knowledge areas
- NB Many activities performed during the control
phase of the project are NOT part of Integrated
Change Control see Mulcahy text.
6Project Plan Development
- To develop a plan that is bought-into, approved,
realistic and formal, the project manager must
perform activities characterized by - Having a project plan methodology
- Keeping stakeholders and resource managers in the
loop with - Meetings
- Schedule approval
- Performing and acting on analysis of risks and
impacts - Performing financial analysis
- Crashing, fast tracking, presenting options to
management - Setting up control plan including EVM system and
PMIS
7Project Plan
- A project plan is a multi-page document created
by the project manager based on input from the
team and stakeholders that includes
Project charter budget
Project mgt approach schedule
Scope statement resources
WBS Change control plan/system
Responsibility chart/assignments Performance measurement baselines
Network diagram/major milestones Management plans scope, schedule, cost, quality, staffing, communications, risk response, procurement
8Corrective (Pro)Action
- Any actions done to bring expected future project
performance in line with project plan - Accomplished by measuring performance and
identifying root cause of variation - Root cause analysis
- Schedule recovery
- Cost recovery
- Changes to risk
- Changes to quality
- Input to project plan execution
- Output from ICC and all control processes
9Hysterical Database
Historical information is used to plan and manage
future projects thus improving project
management. Such data or information includes
- Lessons learned
- Benchmarks
- Risks
- Resources needed
- Correspondence
- Tasks
- WBS
- Reports
- Estimates
- Project plans
10Project Plan Updates
- Output from Integrated Change Control
- Result of controlling project to project plan
- Requires a plan to exist to be controlled and for
formal updates - Project plan is progressively elaborated even
though PM will try to finalize during planning.
11Lessons Learned
- What was done right, wrong and would have been
done differently - Technically
- Project Management
- Management
12Constraints
- Factors that may limit the project teams options
- Organizational structure of performing
organization - Collective bargaining agreements
- Preferences of the project management team
- Expected staff assignments
- Cost
- Time
13Baseline
- Original project plan with approved changes
- Used to monitor progress of project
- Basis of comparison for forecasts of final cost
and schedule - May be changed by formal mechanisms with
accompanying documentation
14Change Control System
- Collection of formal documented procedures,
paperwork, tracking systems and approval levels
for authorizing changes. - Plan for how changes will be managed
- CCB creation
- Hard procedures
- Soft management practices
15Change Control Board
- Reviews change requests to determine if
additional analysis is warranted - Approves and rejects changes
- May include
- PM
- Customer
- Experts
- Sponsor
- Others
16Kickoff Meeting
- Communications and coordination meeting of all
parties to project - Customers
- Sellers
- Project team
- Senior management
- Agencies
- Functional management
- Sponsor
- End of planning phase before beginning work on
project - Topics
- Introductions
- Review of risks
- Communications plan
- Meeting schedule
17Project Plan Approval
- Signatures from management, stakeholders and the
project team are required as formal approval. - Project cannot effectively start without formal
approval. - If stakeholder needs and objectives have been
identified in advance, it should be less
difficult to obtain signatures really.
18Work Authorization System
- Formal procedure for sanctioning project work
ensuring work is done - At right time
- in right sequence
- Controls gold plating
- Defines tasks
- May take form of WBS dictionary
19Change Requests
- Formal documents submitted by anyone on project
after project plan is approved - Identified in project plan execution
- Handled in integrated change control
20Configuration Management
- Rigorous change management as it relates to scope
- Any documented procedure used to apply technical
and administrative direction and surveillance to - ID and document functional and physical
characteristics of an item or system - Control any changes to such characteristics
- Record and report change and its implementation
status - Audit the items and system to verify conformance
to requirements
21Project Management Information System (PMIS)
- System set up in advance to keep PM informed of
the status of all project tasks - May consist of
- Automatic tools
- Manual tools
- Reporting
- Meetings
- Oral inquiries
- Gantt charts
22EVM
- Earned Value Management is a technique used to
integrate the - Project scope
- Schedule
- Resources
- Measure and report project performance
23Project Planning Methodology
- Company standard procedures, forms, and
guidelines for planning projects that everybody
uses really.