Title: Economic Planning Study MWWG Economic Study Results
1Economic Planning Study MWWG Economic Study
Results
- Presentation to TRANSAC on 10/23/08
2Objectives
- Evaluate Transmission Impacts caused by
installation of wind farms in selected high wind
areas - Quantify congestion for various levels and
locations of new generation - Transmission upgrades necessary to accommodate
500 MW of new generation under N-0 conditions.
3Study Assumptions Scenarios
- GE 1.5 MW machines used to model the wind farm.
- An equivalent Machine of 100 MW, 250 MW and 500
MW were put at the defined location. - 2008 Light Autumn case used as it was the most
recent available case for the existing system
without new GIAs. - MT-NW was increased by the equivalent amount in
order to keep the same dispatch pattern - Judith Gap kept at 135 MW
- No MATL
4Study Assumptions Scenarios
- New Generation in three different high wind areas
were studied - Glacier/ Toole County
- Generation Connected at South Cut Bank 115 KV and
Shelby auto 115 kV - Wheatland/ Judith Basin
- The total generation was connected to Judith Gap
230 kV bus. - Park/ Sweet Grass/ Stillwater
- The total generation was connected to Col. Raplje
161 kV bus
5Path 8 Load Duration Curve for 2007
6Path 18 Load Duration Curve for 2007
7Preliminary Results Glacier / Toole County
8Preliminary Results Glacier Toole County
North of Great Falls (NOGF)
- Thermal overloads seen for N-0 conditions for
high level generation in the NOGF area. - The 230/ 115 kV auto bank at Shelby for 250 MW
and higher - 115 kV lines overload in Cut Bank and Conrad for
500 MW generation. - Overload in the Havre-Rudyard area for 500 MW
generation. - Thermal overloads seen on the 115 kV system due
to N-1 credible N-2 contingencies. ( Causes
overloads in the WAPA control area on the Havre-
Rudyard area) - Limited due to thermal rating of the 115 kV GEC
line between South Cutbank and Shelby. - Low Voltages seen on 69 kV under N-1 and N-2
conditions in Bole area
9Load Duration Curve for NOGF
10Load Duration Curve for NOGF with 100 MW, 250 MW
and 500 MW request with Limiting Constraints
11Preliminary Results South of Great Falls
- There are some segments approaching its thermal
capability under certain N-1 outages in the SOGF
path - E.g. East Helena to Canyon Ferry lines on the
outage of the Great Falls to Ovando 230 kV line. - Credible N-2 of Great Falls to East Helena 100 kV
line overloads the Great Falls to Holter line. - Limiting constraints dependent on the Load and
hydro generation in Great Falls. - The limiting constraints presented in the curves
are preliminary. The values of the limiting
constraints may change as more detailed studies
are performed.
12(No Transcript)
13(No Transcript)
14(No Transcript)
15Preliminary Transient Stability Analysis
- Preliminary analysis have shown an increase in
the trip amount of Colstrip for the 500 kV
contingencies. - No other major dynamic issues were seen.
- Special Protection Schemes may be required in
order to maintain the stability of the system
during certain outages.
16Mitigations Required for 500 MW under N-0
Conditions
- Upgrade of the 230/115 kV bank at Shelby
- Upgrade of the CTs on WAPAs 230 kV line.
- A new 230 kV line from South Cut Bank to Great
Falls - A new 230 kV Substation at South Cut Bank with a
new 230 /115 kV transformer bank at South Cut
Bank. - Upgrade of the 500 kV transmission system in
order to accommodate higher flows - 70 series Compensation on the 500 kV system.
- Increased Ampacity on the 500 kV in order to
accommodate higher flows.
17Preliminary Results Wheatland Judith Basin
County
- Outage of the 230 kV line from Judith Gap to
Broadview causes overload on the underlying 100
kV system. - Outage of the 230 kV line from Judith Gap to
Great Falls also causes an overload on the 230
/100 kV auto bank at Judith Gap. - 230 /100 kV auto bank overload under certain N-1
and N-2 conditions for 100, 250 and 500 MW
generation. - Preliminary Study shows this to be the limiting
constraints for the South of Judith Gap (SOJG).
Further analysis required in order to determine
the correct limit for SOJG. - Increases loading on the series capacitor banks
at Broadview in the event of outage of the
parallel 500 kV line for 250 MW and higher - Overload on the 100 kV due to Credible N-2
contingencies.
18South of Judith Gap (SOJG) Load Duration Curve
19South of Judith Gap (SOJG) Load Duration Curve
20South of Judith Gap (SOJG) Load Duration Curve
21Transient Stability Analysis
- The 500 kV contingencies showed increased amount
of Colstrip tripping under the conditions
studied. - The new generation was required to drop in order
to maintain the stability of the system.
22Mitigations Required for 500 MW under N-0
Conditions
- Upgrade of the 230/100 kV Auto bank at JudithGap
Tap. - Upgrades to the 500 kV system in order to
accomodote higher flows. - 230/500 kV auto banks at Broadview
- Series Compensation at Broadview, Garrison, Taft.
- Ampacity on the 500 kV lines
- SPS to drop the generation units under certain
outages to maintain the stability of the system. -
23Preliminary Results - Park/ Sweet Grass County
- N-0 Overloads for the 500 MW generation.
- 161 kV system in the Columbus Rapleje Area
overload. - N-1 Outage of the 161 kV line causes overload on
the underlying system. - Melville Big Timber 50 kV
- Limiting constraints for the Columbus Rapleje
load duration curve is under study.
24(No Transcript)
25Transient Stability Analysis
- Preliminary analysis shows increase in the
tripping at Colstrip for the 500 kV contingencies - SPS required to maintain the stability of the
system under certain conditions.
26Mitigations Required for 500 MW
- Connection of the 230 to 161 kV at Columbus
Rapleje. - Upgrade to the 500 kV transmission system in
order to accommodate higher flows. - 230/500 auto banks at Broadview
- Series Compensation
27Future Work