Economic Planning Study MWWG Economic Study Results - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Economic Planning Study MWWG Economic Study Results

Description:

The 230/ 115 kV auto bank at Shelby for 250 MW and higher ... Limited due to thermal rating of the 115 kV GEC line between South Cutbank and Shelby. ... – PowerPoint PPT presentation

Number of Views:19
Avg rating:3.0/5.0
Slides: 28
Provided by: oatio
Category:

less

Transcript and Presenter's Notes

Title: Economic Planning Study MWWG Economic Study Results


1
Economic Planning Study MWWG Economic Study
Results
  • Presentation to TRANSAC on 10/23/08

2
Objectives
  • Evaluate Transmission Impacts caused by
    installation of wind farms in selected high wind
    areas
  • Quantify congestion for various levels and
    locations of new generation
  • Transmission upgrades necessary to accommodate
    500 MW of new generation under N-0 conditions.

3
Study Assumptions Scenarios
  • GE 1.5 MW machines used to model the wind farm.
  • An equivalent Machine of 100 MW, 250 MW and 500
    MW were put at the defined location.
  • 2008 Light Autumn case used as it was the most
    recent available case for the existing system
    without new GIAs.
  • MT-NW was increased by the equivalent amount in
    order to keep the same dispatch pattern
  • Judith Gap kept at 135 MW
  • No MATL

4
Study Assumptions Scenarios
  • New Generation in three different high wind areas
    were studied
  • Glacier/ Toole County
  • Generation Connected at South Cut Bank 115 KV and
    Shelby auto 115 kV
  • Wheatland/ Judith Basin
  • The total generation was connected to Judith Gap
    230 kV bus.
  • Park/ Sweet Grass/ Stillwater
  • The total generation was connected to Col. Raplje
    161 kV bus

5
Path 8 Load Duration Curve for 2007
6
Path 18 Load Duration Curve for 2007
7
Preliminary Results Glacier / Toole County
8
Preliminary Results Glacier Toole County
North of Great Falls (NOGF)
  • Thermal overloads seen for N-0 conditions for
    high level generation in the NOGF area.
  • The 230/ 115 kV auto bank at Shelby for 250 MW
    and higher
  • 115 kV lines overload in Cut Bank and Conrad for
    500 MW generation.
  • Overload in the Havre-Rudyard area for 500 MW
    generation.
  • Thermal overloads seen on the 115 kV system due
    to N-1 credible N-2 contingencies. ( Causes
    overloads in the WAPA control area on the Havre-
    Rudyard area)
  • Limited due to thermal rating of the 115 kV GEC
    line between South Cutbank and Shelby.
  • Low Voltages seen on 69 kV under N-1 and N-2
    conditions in Bole area

9
Load Duration Curve for NOGF
10
Load Duration Curve for NOGF with 100 MW, 250 MW
and 500 MW request with Limiting Constraints
11
Preliminary Results South of Great Falls
  • There are some segments approaching its thermal
    capability under certain N-1 outages in the SOGF
    path
  • E.g. East Helena to Canyon Ferry lines on the
    outage of the Great Falls to Ovando 230 kV line.
  • Credible N-2 of Great Falls to East Helena 100 kV
    line overloads the Great Falls to Holter line.
  • Limiting constraints dependent on the Load and
    hydro generation in Great Falls.
  • The limiting constraints presented in the curves
    are preliminary. The values of the limiting
    constraints may change as more detailed studies
    are performed.

12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
Preliminary Transient Stability Analysis
  • Preliminary analysis have shown an increase in
    the trip amount of Colstrip for the 500 kV
    contingencies.
  • No other major dynamic issues were seen.
  • Special Protection Schemes may be required in
    order to maintain the stability of the system
    during certain outages.

16
Mitigations Required for 500 MW under N-0
Conditions
  • Upgrade of the 230/115 kV bank at Shelby
  • Upgrade of the CTs on WAPAs 230 kV line.
  • A new 230 kV line from South Cut Bank to Great
    Falls
  • A new 230 kV Substation at South Cut Bank with a
    new 230 /115 kV transformer bank at South Cut
    Bank.
  • Upgrade of the 500 kV transmission system in
    order to accommodate higher flows
  • 70 series Compensation on the 500 kV system.
  • Increased Ampacity on the 500 kV in order to
    accommodate higher flows.

17
Preliminary Results Wheatland Judith Basin
County
  • Outage of the 230 kV line from Judith Gap to
    Broadview causes overload on the underlying 100
    kV system.
  • Outage of the 230 kV line from Judith Gap to
    Great Falls also causes an overload on the 230
    /100 kV auto bank at Judith Gap.
  • 230 /100 kV auto bank overload under certain N-1
    and N-2 conditions for 100, 250 and 500 MW
    generation.
  • Preliminary Study shows this to be the limiting
    constraints for the South of Judith Gap (SOJG).
    Further analysis required in order to determine
    the correct limit for SOJG.
  • Increases loading on the series capacitor banks
    at Broadview in the event of outage of the
    parallel 500 kV line for 250 MW and higher
  • Overload on the 100 kV due to Credible N-2
    contingencies.

18
South of Judith Gap (SOJG) Load Duration Curve
19
South of Judith Gap (SOJG) Load Duration Curve
20
South of Judith Gap (SOJG) Load Duration Curve
21
Transient Stability Analysis
  • The 500 kV contingencies showed increased amount
    of Colstrip tripping under the conditions
    studied.
  • The new generation was required to drop in order
    to maintain the stability of the system.

22
Mitigations Required for 500 MW under N-0
Conditions
  • Upgrade of the 230/100 kV Auto bank at JudithGap
    Tap.
  • Upgrades to the 500 kV system in order to
    accomodote higher flows.
  • 230/500 kV auto banks at Broadview
  • Series Compensation at Broadview, Garrison, Taft.
  • Ampacity on the 500 kV lines
  • SPS to drop the generation units under certain
    outages to maintain the stability of the system.

23
Preliminary Results - Park/ Sweet Grass County
  • N-0 Overloads for the 500 MW generation.
  • 161 kV system in the Columbus Rapleje Area
    overload.
  • N-1 Outage of the 161 kV line causes overload on
    the underlying system.
  • Melville Big Timber 50 kV
  • Limiting constraints for the Columbus Rapleje
    load duration curve is under study.

24
(No Transcript)
25
Transient Stability Analysis
  • Preliminary analysis shows increase in the
    tripping at Colstrip for the 500 kV contingencies
  • SPS required to maintain the stability of the
    system under certain conditions.

26
Mitigations Required for 500 MW
  • Connection of the 230 to 161 kV at Columbus
    Rapleje.
  • Upgrade to the 500 kV transmission system in
    order to accommodate higher flows.
  • 230/500 auto banks at Broadview
  • Series Compensation

27
Future Work
  • Report
Write a Comment
User Comments (0)
About PowerShow.com