General Electricity Company of Libya - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

General Electricity Company of Libya

Description:

Around 2000 km of new 220 kV T. lines. B. 220 kV Transmission System Expansion. Future ... Egypt. Jordan. Existing 400kV. Proposed 500 - 400kV. Thank you for ... – PowerPoint PPT presentation

Number of Views:904
Avg rating:3.0/5.0
Slides: 31
Provided by: abdulbasit5
Category:

less

Transcript and Presenter's Notes

Title: General Electricity Company of Libya


1
General Electricity Company of Libya (GECOL)
MEDELEC
THE 16th ANNUAL MEETING Casablanca 20-21
March, 2008
2
PRESENTATION CONTENTS
  • HISTORICAL INTRODUCTION.
  • Now days ELECTRICITY .
  • FUTURE MASTER PLAN PROJECTS
  • ELECTRICAL INTERCONNECTIONS FUTURE STRATEGY

3
HISTORICAL INTRODUCTION
  • Today, GECOL is a state owned vertically
    structured power utility company in the country
    responsible for
  • Generation
  • Transmission
  • Distribution

4
HISTORICAL INTRODUCTION
  • Peak Load
    150 MW.
  • Installed Generation Capacity
    250 MW
  • Small Gas Turbine Units
    5-15 MW distributed on the main cities.
  • Separated Distribution Networks 11-30
    kV

1970
  • Peak Load
    4422 MW.
  • Installed Generation capacity
    6612 MW
  • Generated Energy
    25,514 GWh
  • 400 kv Transmission system 440
    km
  • 220 kv Transmission system
    13,000 km

2007
5
HISTORICAL INTRODUCTION
  • Customers
    1,200,000
  • Per-Capita Consumption
    3,696 kWh
  • Urban Rural Electrification Rate gt99

2007
6
History
Transmission Lines
7
History
Transmission Lines
8
History
Substations (Transformer Capacity S/S Number)
9
Future
Master Plan Fundamental objectives
  • Securing and guarantee the electrical power
    supply to the growing demand of electrical energy
    to all sectors in the country.
  • Increasing the level of security and adequacy of
    supply
  • Reducing Cost by Improving service quality
    Efficiency
  • Reducing technical and non technical losses.
  • Reinforcing international Interconnections.

10
Long Term Load Forecast
Future
  • The peak load of electrical power in Libya is
    continuously increasing with a relatively high
    growth rate 8 per annum.
  • Recent studies have shown that the expected peak
    demand in Libya in 2?year 2008 will be about 4670
    MW, and the figure is expected to reach 5450 MW
    by year 2010 Approx. 8000 MW 1n 2015.

11
Long Term Load Forecast
Future
  • New projects
  • The total expected Peak load

12
The Generation Expansion Plan
Future
  • Around 11000MW generation capacity need to be
    added during the Period (2005 2015). Nearly
    4000 MW are needed by the horizon 2010, with a
    mixed generation options based on latest
    Technology (Steam Combined Cycle) using natural
    gas.
  • Under construction Power plant ( 1500 MW )
  • 750 MW Benghazi C.C
  • 750 MW Misurata C.C

13
The Generation Expansion Plan
Future
  • Contract awarded
  • 312 MW West Mountain Ext.
  • 500 MW Zwitina gas plant
  • 750 MW Srir west gas plant
  • 1400 MWGulf steam plant.
  • 1400 MW Tripoli West steam plant
  • Under contract
  • 750 MW Sebha gas Plant

14
(No Transcript)
15
GECOL Transmission System Master Plan.
Future
A. The New 400 kV Grid
  • During The Horizon 2010 the main infrastructure
    for a strong, reliable flexible adequate
    backbone of the new EHV 400 kV Grid will be
    Executed.
  • Therefore, the Future plan of the Libyan
    Transmission System is concentrated on the EHV
    400 kV grid.
  • Existing
  • 2 (400/220 kV) substations
  • 442 km lines

16
GECOL Transmission System Master Plan.
Future
A. The New 400 kV Grid
  • Under construction
  • 7 substations
  • 2720 km lines
  • Contract awarded
  • 8 substations
  • 630 km lines

17
Italy
Zawia
Tunisia
Bedia
88
Tripoli East
Tobruk
Benghazi North
Hooms
180
76
20
32
Gwrasha
271
110
14
138
60
Misurata
25
45
Rowis
Benghazi West
23
500 kv
38
252
400
Saloom
150
230
200
126
272
Algeria
Ben walid
Gulf
281
Gdabia
330
238
Ras lanof
272
Gdams
GMMR
Hoon
400 ??
260
375
Sebha
Srir West
The New Libyan EHV 400 kV Network
Existing
Under construction
Under contract
Planning
Interconnection
GECOL
18
The Future plan of the Libyan Transmission
System Expansion includes the construction of
Future
B. 220 kV Transmission System Expansion
  • 256 km (1000 km cables core length) of 220 kV U.
    G. cables in Tripoli, Benghazi, Zawia Musrata
    cities
  • 71 substations 220 kV in deferent locations in
    the country.
  • Around 2000 km of new 220 kV T. lines.

19
Under contract
Future
B. 220 kV Transmission System Expansion
  • 88 km of 220 kV U. G. cables in Tripoli.
  • 30 km of 220 kV U. G. cables in Benghazi.
  • 10 substations 220 kV ( GIS ) in deferent
    locations in the country.
  • 500 km of new 220 kV T. lines.

20
C .Control Centers .
National Control Center (NCC)
Tripoli Regional Control Center (TRCC)
Benghazi Regional Control Center (BRCC)
21
Future
  • 10 Distribution control centers will be put
    into operation during the period 2008-2010.

Tripoli Regional Control Center (TRCC)
Western Area DCC 30/11 kV
Tripoli DCC 30/11 kV
Western Mountain DCC 66/30/11 kV
SAHEL DCC 30/11 kV
South Region DCC 66/11 kV
Gulf DCC 30/11 kV
22
Benghazi Regional Control Center (BRCC)
Benghazi DCC 66/30/11 kV
Toubruk DCC 66/30/11 kV
Green Mountain DCC 66/30/11 kV
Sarir Kufra DCC 66/11 kV
23
TRCC
Western Area DCC
Green Mountain DCC
BRCC
Tripoli DCC
Toubruk DCC
NCC
SAHEL DCC
Benghazi DCC
Gulf DCC
Western Mountain DCC
South Region DCC
Sarir Kufra DCC
Future Structure of Control Centers
GECOL
24
Electrical Interconnections
  • The internal interconnection of the Libyan
    transmission system has been achieved since 1993
    creating the high voltage 220 kV Libyan national
    grid.
  • The electrical networks of Libya and Egypt are
    interconnected on 220 kV voltage level since May
    1998.
  • By the End of this year 2008 the electrical
    interconnection between Libya and Tunisia is
    expected to be put into operation on the 220 kV.

25
Beyda 400 kv
DARNA
ALMARJ
TOBRUK220kv
ASALLUM 220 kv
TOBRUK400kv
BENGHAZI
MARSA MATRUH
TOBRUK 500 kv
AJDABIYA 220 kv
AJDABIYA 400 kv
MARSA MATRUH 500 kv
Existing 220 kv interconnection
Future 500 kv interconnection
JALU
Libya - Egypt Electrical interconnection
26
BUOSHMA 220kv
MADNEN
BUOSHMA 400 kv
BUOKMASH
TRIPOLI WEST
TATAWN
Sorman.s 400kv
RABTA
ROWES
ROWES 400kv
Existing 220 kv interconnection
Future 400 kv interconnection
Algeria
Libya - Tunisia Electrical interconnection
Gdams
Hassi Brkin
Libya - Algeria Electrical interconnection
27
EHV Interconnections with Egypt Tunisia and
Algeria
  • It is expected to construe operate the EHV
    500-400 kV link with Egypt by year 2010.
  • It is expected to contract operate the 400 kV
    link with Tunisia during the period (2010-2015)
  • Under study the electrical interconnection on 400
    kv between Libya and Algeria.
  • Under study the electrical interconnection on 400
    kv (submarine cable) between Libya and Italy.

28
Other Possible Interconnections with EuropeLibya
Italy (HVDC) Link
  • submarine cable (HVDC )
  • 400 KV
  • Length 520 km
  • Power capacity 1000 MW

500-1000 MW
29
Existing 400kV Proposed 500 - 400kV
Spain
Morocco
Algeria
Jordan
Egypt
Tunisia
Libya
  • Proposed EHV 500-400 kV interconnection between
    ELTAM Countries

30
Thank you for your Kind Attention
Write a Comment
User Comments (0)
About PowerShow.com