Title: General Electricity Company of Libya
1General Electricity Company of Libya (GECOL)
MEDELEC
THE 16th ANNUAL MEETING Casablanca 20-21
March, 2008
2PRESENTATION CONTENTS
- HISTORICAL INTRODUCTION.
- Now days ELECTRICITY .
- FUTURE MASTER PLAN PROJECTS
- ELECTRICAL INTERCONNECTIONS FUTURE STRATEGY
3HISTORICAL INTRODUCTION
- Today, GECOL is a state owned vertically
structured power utility company in the country
responsible for
- Generation
- Transmission
- Distribution
4HISTORICAL INTRODUCTION
- Peak Load
150 MW. - Installed Generation Capacity
250 MW - Small Gas Turbine Units
5-15 MW distributed on the main cities. - Separated Distribution Networks 11-30
kV
1970
- Peak Load
4422 MW. - Installed Generation capacity
6612 MW - Generated Energy
25,514 GWh - 400 kv Transmission system 440
km - 220 kv Transmission system
13,000 km
2007
5HISTORICAL INTRODUCTION
- Customers
1,200,000 - Per-Capita Consumption
3,696 kWh - Urban Rural Electrification Rate gt99
2007
6History
Transmission Lines
7History
Transmission Lines
8History
Substations (Transformer Capacity S/S Number)
9Future
Master Plan Fundamental objectives
- Securing and guarantee the electrical power
supply to the growing demand of electrical energy
to all sectors in the country. - Increasing the level of security and adequacy of
supply - Reducing Cost by Improving service quality
Efficiency - Reducing technical and non technical losses.
- Reinforcing international Interconnections.
10Long Term Load Forecast
Future
- The peak load of electrical power in Libya is
continuously increasing with a relatively high
growth rate 8 per annum.
- Recent studies have shown that the expected peak
demand in Libya in 2?year 2008 will be about 4670
MW, and the figure is expected to reach 5450 MW
by year 2010 Approx. 8000 MW 1n 2015.
11Long Term Load Forecast
Future
- The total expected Peak load
12The Generation Expansion Plan
Future
- Around 11000MW generation capacity need to be
added during the Period (2005 2015). Nearly
4000 MW are needed by the horizon 2010, with a
mixed generation options based on latest
Technology (Steam Combined Cycle) using natural
gas. - Under construction Power plant ( 1500 MW )
- 750 MW Benghazi C.C
- 750 MW Misurata C.C
13The Generation Expansion Plan
Future
- 312 MW West Mountain Ext.
- 500 MW Zwitina gas plant
- 750 MW Srir west gas plant
- 1400 MWGulf steam plant.
- 1400 MW Tripoli West steam plant
14(No Transcript)
15GECOL Transmission System Master Plan.
Future
A. The New 400 kV Grid
- During The Horizon 2010 the main infrastructure
for a strong, reliable flexible adequate
backbone of the new EHV 400 kV Grid will be
Executed. - Therefore, the Future plan of the Libyan
Transmission System is concentrated on the EHV
400 kV grid. - Existing
- 2 (400/220 kV) substations
16GECOL Transmission System Master Plan.
Future
A. The New 400 kV Grid
17Italy
Zawia
Tunisia
Bedia
88
Tripoli East
Tobruk
Benghazi North
Hooms
180
76
20
32
Gwrasha
271
110
14
138
60
Misurata
25
45
Rowis
Benghazi West
23
500 kv
38
252
400
Saloom
150
230
200
126
272
Algeria
Ben walid
Gulf
281
Gdabia
330
238
Ras lanof
272
Gdams
GMMR
Hoon
400 ??
260
375
Sebha
Srir West
The New Libyan EHV 400 kV Network
Existing
Under construction
Under contract
Planning
Interconnection
GECOL
18 The Future plan of the Libyan Transmission
System Expansion includes the construction of
Future
B. 220 kV Transmission System Expansion
- 256 km (1000 km cables core length) of 220 kV U.
G. cables in Tripoli, Benghazi, Zawia Musrata
cities - 71 substations 220 kV in deferent locations in
the country. - Around 2000 km of new 220 kV T. lines.
19 Under contract
Future
B. 220 kV Transmission System Expansion
- 88 km of 220 kV U. G. cables in Tripoli.
- 30 km of 220 kV U. G. cables in Benghazi.
- 10 substations 220 kV ( GIS ) in deferent
locations in the country. - 500 km of new 220 kV T. lines.
20C .Control Centers .
National Control Center (NCC)
Tripoli Regional Control Center (TRCC)
Benghazi Regional Control Center (BRCC)
21Future
- 10 Distribution control centers will be put
into operation during the period 2008-2010. -
Tripoli Regional Control Center (TRCC)
Western Area DCC 30/11 kV
Tripoli DCC 30/11 kV
Western Mountain DCC 66/30/11 kV
SAHEL DCC 30/11 kV
South Region DCC 66/11 kV
Gulf DCC 30/11 kV
22Benghazi Regional Control Center (BRCC)
Benghazi DCC 66/30/11 kV
Toubruk DCC 66/30/11 kV
Green Mountain DCC 66/30/11 kV
Sarir Kufra DCC 66/11 kV
23TRCC
Western Area DCC
Green Mountain DCC
BRCC
Tripoli DCC
Toubruk DCC
NCC
SAHEL DCC
Benghazi DCC
Gulf DCC
Western Mountain DCC
South Region DCC
Sarir Kufra DCC
Future Structure of Control Centers
GECOL
24Electrical Interconnections
- The internal interconnection of the Libyan
transmission system has been achieved since 1993
creating the high voltage 220 kV Libyan national
grid. - The electrical networks of Libya and Egypt are
interconnected on 220 kV voltage level since May
1998. - By the End of this year 2008 the electrical
interconnection between Libya and Tunisia is
expected to be put into operation on the 220 kV.
25Beyda 400 kv
DARNA
ALMARJ
TOBRUK220kv
ASALLUM 220 kv
TOBRUK400kv
BENGHAZI
MARSA MATRUH
TOBRUK 500 kv
AJDABIYA 220 kv
AJDABIYA 400 kv
MARSA MATRUH 500 kv
Existing 220 kv interconnection
Future 500 kv interconnection
JALU
Libya - Egypt Electrical interconnection
26BUOSHMA 220kv
MADNEN
BUOSHMA 400 kv
BUOKMASH
TRIPOLI WEST
TATAWN
Sorman.s 400kv
RABTA
ROWES
ROWES 400kv
Existing 220 kv interconnection
Future 400 kv interconnection
Algeria
Libya - Tunisia Electrical interconnection
Gdams
Hassi Brkin
Libya - Algeria Electrical interconnection
27EHV Interconnections with Egypt Tunisia and
Algeria
- It is expected to construe operate the EHV
500-400 kV link with Egypt by year 2010. - It is expected to contract operate the 400 kV
link with Tunisia during the period (2010-2015)
- Under study the electrical interconnection on 400
kv between Libya and Algeria. - Under study the electrical interconnection on 400
kv (submarine cable) between Libya and Italy.
28Other Possible Interconnections with EuropeLibya
Italy (HVDC) Link
- submarine cable (HVDC )
- 400 KV
- Length 520 km
- Power capacity 1000 MW
500-1000 MW
29Existing 400kV Proposed 500 - 400kV
Spain
Morocco
Algeria
Jordan
Egypt
Tunisia
Libya
- Proposed EHV 500-400 kV interconnection between
ELTAM Countries
30Thank you for your Kind Attention