May%202005 - PowerPoint PPT Presentation

About This Presentation
Title:

May%202005

Description:

Interface to the business logic. Custom UI's & scripts may be written. 11. Architecture ... time. Should have dropped JBoss early. questions? comments? concerns? ... – PowerPoint PPT presentation

Number of Views:18
Avg rating:3.0/5.0
Slides: 19
Provided by: nickma5
Learn more at: https://www.se.rit.edu
Category:
Tags: logic | questions

less

Transcript and Presenter's Notes

Title: May%202005


1
  • May 2005

Greg Giacovelli Nick Mancuso Shaun Newsum
Jean-Paul Pietraru Nick Stroh
2
Agenda
  • Background
  • Motivation
  • Requirements
  • Schedule
  • Metrics
  • Architecture
  • Tier Design
  • Domain experience

3
Background
  • Replace the try system
  • Compiles, tests, and saves students submissions
  • Provides immediate feedback to the student
  • Collection of scripts written in the early 1990s
  • Issues
  • Steep learning curve
  • Performance issues at peak hours

4
Motivation
  • New Features
  • Cross platform support
  • Small learning curve
  • A solid framework
  • Provide clear ports for adding future
    customizations expansions
  • Separate concerns to ease maintenance
  • Distribute CPU load

5
Requirements
  • Gathered from
  • Project sponsor
  • Personal experience with old system
  • Sample try lab configuration
  • Tested against
  • Project sponsor
  • try manuals
  • SRS is thorough will be useful to future
    developers

6
Schedule
Due Date Delivered Name Description
12-26-04 12-26-04 Project Plan Plan and schedule
01-06-05 01-26-05 SRS Defines the system requirements
01-25-05 02-18-05 Design Describes the system design
01-20-05 01-20-05 Test Plan Defines the testing approach
01-29-05 02-18-05 M1 Milestone 1 The Framework
02-17-05 02-17-05 Progress report Midpoint project presentation
02-28-05 03-24-05 M2 Milestone 2 Submit
03-31-05 05-02-05 M3 Milestone 3 Compile and Test
04-28-05 04-28-05 Project poster Product presentation poster
04-30-05 N/A M4 Milestone 4 Code complete
05-16-05 05-16-05 Conference Paper End of term paper
05-20-05 N/A M5 Milestone 5 Gold
7
Metrics
Man Hours (Est.) 660
LOC 23550
LOC / Man Hour 35.6
8
Metrics
9
Solution
  • Architectural framework
  • May be easily extended to meet all requirements
  • Runs in any J2EE-compliant application server.
  • Scalable by distributing amongst multiple hosts
  • Distributed submission processing
  • Compile testing is completed by an array of
    clients
  • Increases system performance
  • Scales up by adding more client machines

10
Solution
  • Model-View-Controller
  • Decouples
  • UI from business logic
  • Business logic from data
  • Web services
  • Interface to the business logic
  • Custom UIs scripts may be written

11
Architecture
12
Web Tier
13
Business Tier
14
Data Tier
15
Middle Tier
16
Problems we encountered
  • Configuration issues
  • jBoss
  • Integration tests
  • J2EE complexity
  • Learning curve

17
Post Mortem
  • What went well
  • Solid documentation throughout.
  • Proof-of-concept or better code for each major
    component of the system.
  • What we learned from
  • Too much wind-up time
  • Should have dropped JBoss early

18
questions? comments?concerns?
Write a Comment
User Comments (0)
About PowerShow.com