Title: Press Capacity Expansion
1Press Capacity Expansion
- Metro Users Group
- Houston, Texas
March 1, 2004
2Press Capacity ExpansionWHY?
?
- Revenue Growth
- Profit and Margin Gains
- Shareholder Value Enhancement
- Provide Advertising Clients More Options
- Create Opportunity for News to Use Color
- Strong North Trend Line Before 2001
3Press Capacity ExpansionWall Street Journal
Growth Trend
4Press Capacity ExpansionColor Page Trend
5Press Capacity ExpansionThe Wall Street Journal.
- 96 Pages Straight w/24 Color Pages
- 19 Press Lines _at_ 17 U.S. Plants
- Standardized Existing Presses
- Added Two 4/4 Towers
- 225 Million and 3.5 Years
6Press Capacity ExpansionWhat The Equipment Does
- New Capacity
- 96 Total Pages w/24 Total Color Pages
- Design Flexibility
- Three or Four (4) Section Options
- Color on All Front and Back Section Covers
- 2 Sections Available for Center Spread Color
- 2 Sections Available With Inside Color
7Press Capacity ExpansionKeys to Success
- Planning Planning Planning
- Strong, Diverse Internal Team
- Contract Scope and Clarity Are Essential
- Intense, Owner Driven Project Management
- Focus on the Goals
8Press Capacity ExpansionKeys to Success
- Partner With Your Suppliers
- Customer Runs the Equipment
- Measurable and Fair Acceptance Criteria
- Dont Forget the Acceptance Process
- Deploy Proven Technology
- Training Training Training
9Press Capacity ExpansionFocused Project
Management
- The Buyer OWNS () Project Mgmt
- Demand Professional Project Management
- Continuity and Experience Important
- Communicate Regularly
- Progress Calls With Lead Suppliers
- The Devil Is in the Details
- Focus Ahead Close Out The Punch List
10Press Capacity ExpansionBusiness Partnerships
11Press Capacity ExpansionProven Technology
- Upgraded Shafted AC DrivesABB
- Homogeneous Press Lines by Supplier
- Proven Inker Design Digital Page Packs
- Technotrans Spray Bar Dampening
- Extended ABB Press Controls
- Registration System by Presstech
- Harland-Simon Decision Support Systems
12Press Capacity ExpansionDJ-TKS Engineering
Success
13Press Capacity ExpansionDJ-Goss/ABB Engineering
First
- Integrated Remote and Local Controls
- First Goss Newsliner with Integrated ABB Unit
Controls - First Newsliner with Local Control Panel
14Press Capacity ExpansionThe Execution Plan
- Multi-phased, Multi-path Schedule
- Plans for 8 Goss Sites and 9 TKS Sites
- Multiple Tracks for Each Press Supplier
- Schedule Acceleration Essential
- A-E Construction
- Uniformly Configure Presses Higher Risk
- Install and Commission The Towers
- Training Testing Learning
15Press Capacity ExpansionFrom the OLD to the NEW
- Existing Press 80 Pages with 8 Color Pages
1
16Press Capacity ExpansionFrom the OLD to the NEW
1 2
17Press Capacity ExpansionFrom the OLD to the NEW
1 2 3
18Press Capacity ExpansionFrom the OLD to the NEW
- Remove Old Mono Units Reels
1 2 3 4
19Press Capacity ExpansionFrom the OLD to the NEW
1 2 3 4 GO!!
20Press Capacity ExpansionGoss Newsliner Tower
Orlando
21Press Capacity ExpansionTKS Color Top 6000
Charlotte
22Press Capacity ExpansionAdventure, Surprises and
Challenges
- Stubborn Municipalities Permits
- After-the-fact Spec Interpretation
- Bankruptcy and Recovery
- Warehouse Fire
- Commissioning Standards
- Project Coordination
- Parents and Subsidiaries
- Training Adults Is an ART
23Press Capacity ExpansionLessons Learned
- PromisesPromises Credibility Matters!!
- Training Training Training
- Milestones Milestones Milestones
- Focus on SOLUTIONS and GOALS!
- Think Flexibility Youll Sleep Better!
- Expect The Unexpected Count on IT!
- Contract Scope, Specs Clarity A MUST!
24Press Capacity ExpansionTodays Journal April
9, 2002
25Press Capacity ExpansionColor Page Results
26- Paul Cousineau
- Director Continuous Improvement
- paul.cousineau_at_dowjones.com