Title: How to Survive a DEC Construction Site Inspection
1How to Survive a DEC Construction Site Inspection
Bill Lupo, Environmental Engineer 2 NYSDEC
Division of Water, Region 5
2Overview
- Site Inspection Procedures
- Common Problems and Site Examples
- Remediation Procedure
3DEC does conduct site inspections!
- Purpose
- Document Compliance
- Provide Technical
- Assistance
- Protect Water Resources
4DEC Site Inspection Procedure
- Initiated by
- Follow-up to Plan review
- Citizen Complaint (mud tracked on to road?)
- Drive-by
- Routine visit based on NOI listing
- Inspection schedule
- Document Permit Compliance (stop at job trailer
first) - Tour construction site (invite project manager
along) - Re-visit trailer and discuss inspection results
5Construction Site Stormwater Inspection Report
6Construction Site Stormwater Inspection Report
7Construction Site Stormwater Inspection Report
8On the job site Bare Soil Precipitation
- Cleanup costs
- Lost work days
- Materials and equipment
- replacement costs
-
and . . . Water Quality Standards Violation and
potential fines from DEC more
9Construction Sequencing
10Improper Construction Sequencing
Rock outfall stabilization should be installed
before placing rolled erosion control materials
11Erosion Sediment Control Notes
12Erosion Sediment Control Notes
13Current Site Conditions
Site Inspectors will consider current site
conditions in determining if contractors and
developers are employing ESC measures adequately
Recent Rainfall / Snowmelt Season Soils Drainage
Area Water Courses / Flow Paths Topography /
Slope Length Percent Impervious Cover Vegetative
Cover
14Stabilized Construction EntranceMust be
maintained throughout project!
? Okay
15Common silt fence application problems
- ? Too far from the gutter
- Flapping fabric
- (must be embedded at least 6)
16Common silt fence application problems
? Not maintained should be cleaned and replaced
? Not maintained should be replaced
17Wetland or Sensitive Area Boundaries should be
properly protected to avoid encroachment
Okay ?
Unacceptable ? ?
18- Check Dam Materials should properly direct flow
- Stone Check Dam constructed in conformance with
NYS Technical Standards
19Check Dam Materials should properly direct flow
Square-notch silt fence and hay bale check dams
are not accepted by NYS Technical Standards
20- Seed and Mulch
- Reduces soil loss by up to 90
- Reduces maintenance costs
21Hydroseeding reduces runoff and erosion by
promoting vigorous establishment of plant cover
Your local Soil and Water Conservation District
may be available to assist with hydroseeding
applications
22Rolled Erosion Control Products
Should be applied up and down the slope with
overlapping edges
23Rolled Erosion Control Products
RECP applied across the slope can peel back in
a storm event ?
? RECP could have prevented this gully erosion
24Steep Slopes (gt 21) should be protected
Terracing Rolled Erosion Control Products
Seed and Mulch !!!
Okay ?
25Spillways and Inlets must also be stabilized
- Lack of outlet stabilization can cause
- Channel Cutting
- Undercut Pipes
26Drop Inlet ProtectionA handful of accepted
techniques
? Stone and block inlet protection
? Filter fabric inlet protection
27Drop Inlet Protection and SO many wrong ways!
? Unacceptable straw bales arent protecting
the catch basin
? Unacceptable sand bags over grate caused
ponding
28Drop Inlet Protection more wrong ways!
? Unacceptable fabric under grate causes
ponding
The same catch basin a few months later ?
29Grass Swales They work great if theyre
installed correctly
Good ?
30Grass Swales
? Unacceptable needs to be seeded and mulched
Unacceptable tracks should run up and down side
slopes ?
31Stormwater Management StructuresImproper
installation and maintenance can lead to Water
Quality Violations
? Eroding banks
? Flow bypasses outlet berm doesnt meet box
32Stormwater Management Structures
? Lack of Forebay or settling time excessive
turbid discharge
Forebay berm doesnt meet side slopes ?
33Compacted Cracking Subsiding doesnt provide
acceptable infiltration!
Infiltration / Filtering Problems
Under-drains dont work if they are grouted in!
34Should be embedded in the soil, tightly abutted
and replaced frequently
Straw Bale Dike
Straw / hay bales are NOT acceptable check dam
material
35 No rock outlet does not provide sediment
settlingNo rock on slopesSilt fence barrier
does not allow discharge
Sediment Traps
? No rock on slopes increases sediment load in
trap
36Wetlands arent meant to be sediment traps!
37After the Inspection
- Letter to owner, contractor, and/or engineer
- If inspection rating is unsatisfactory
- Follow-up inspection
- Meeting with DEC Regional staff to discuss
deficiencies and achieve compliance - Notice of Violation
- Consent Order and assessment of penalty
- Stop Work Order
38Stop Work Order
Upon a finding of significant non compliance with
the permit or the applicable SWPPP, the
Department may order an immediate stop to all
construction activity at the site until the
non-compliance is remedied.
39Consent Orders
- Any permit non-compliance constitutes violations
of the CWA and ECL - Maximum penalties are 37,500 per violation per
day - Who is the responsible party?
- The operator must comply with all conditions of
the permit - All contractors and subcontractors associated
with the project must comply with the terms of
the SWPPP
40Resources to Help with These Practices
- New York State Stormwater Management Design
Manual - http//www.dec.state.ny.us/website/dow/mainpage.ht
m - New York State Standards for Erosion and Sediment
Control (Blue Book) - http//www.dos.state.ny.us/lgss/stormwaterpub-old/
index.html
41DEC Regional Stormwater Contacts
- Region 1 631-444-0405 Nassau, Suffolk
- Region 2 718-482-4033 Bronx, Kings, New York,
Queens, Richmond - Region 3 914-332-1835 Dutchess, Orange,
Putnam, Rockland, Sullivan, Ulster,
Westchester - Region 4 518-357-2045 Albany, Columbia,
Delaware, Greene, Montgomery, Otsego,
Rensselaer, Schenectady, Schoharie - Region 5 518-623-3671 Clinton, Essex,
Franklin, Fulton, Hamilton, Saratoga,
Warren, Washington
42DEC Regional Stormwater Contacts
- Region 6 315-793-2554 Herkimer, Jefferson,
Lewis, Oneida, St. Lawrence - Region 7 315-426-7500 Broome, Cayuga,
Chenango, Cortland, Madison, Onondaga,
Oswego, Tioga, Tompkins - Region 8 585-226-2466 Chemung, Genesee,
Livingston, Monroe, Ontario, Orleans,
Schuyler, Seneca, Steuben, Wayne,
Yates - Region 9 716-851-7070 Allegany, Cattaraugus,
Chautauqua, Erie, Niagara, Wyoming
43Websites for Training Professional Associations
- Stormwater Managers Resource Center
http//www.stormwatercenter.net - Center for Watershed Protection
http//www.cwp.org - Certified Professional in Erosion and Sediment
Control, Inc. - http//www.cpesc.net
- SUNY-ESF Continuing Education - Stormwater
Management Program http//www.esf.edu/outreach/sto
rmwater/
44Government Websites