Title: ABB
1POWER SYSTEM 2002 CONFERENCE -- IMPACT OF
DISTRIBUTED GENERATION
Interconnecting DER With Electric Power Systems
Image
Image
ABB
2Interconnecting DER with Electric Power Systems
- Existing IEEE Standards
- Standards Coordinating Committee 21
- IEEE Standard 929-2000 Recommended Practice
for Utility Interface of Photovoltaic (PV)
Systems - Standards Coordinating Committee 23
- IEEE Standard 1001-1988 Guide for Interfacing
Dispersed Storage and Generation Facilities with
Electric Utility Systems - Current IEEE Standards Work
- IEEE P-1547 Standard for Interconnecting
Distributed Resources with Electric Power Systems
3Interconnecting DER with Electric Power Systems
4Interconnecting DER with Electric Power Systems
- P-1547 Project Approved in March 1999
- 4 - 6 meetings of Working Group per year since
then - Working Group Members
- More than 200 names on Working Group Roster
- 100 members attend each Working Group Meeting
5Interconnecting DER with Electric Power Systems
- Three Official IEEE Balloting Member Categories
- User
- The user is the person who will apply the
standard when interconnecting DER to the electric
power system. For example, the utility, the DER
owner, etc. - Producer
- The producer is the person who will apply the
standard when producing equipment that will be
interconnected to the electric power system. For
example, equipment manufacturers, installers,
etc. - General Interest
- The general interest person is one who is
interested, but not directly involved in
interconnecting DER to the electric power system.
For example, regulatory agencies, financial
institutions, advocacy groups, etc.
6Interconnecting DER with Electric Power Systems
- Draft 7 circulated for ballot --- closing date of
April 1, 2001 - Vote Results
- 66 Affirmative, not enough for approval (75
required)
7Interconnecting DER with Electric Power Systems
- Draft 8 circulated for ballot -- closing date of
October 2, 2001 - Vote Results
- 66 Affirmative, not enough for approval (75
required)
8Interconnecting DER with Electric Utility Systems
- IEEE Standard 929
- Aimed at Photovoltaic Generator Systems, using
solid-state inverters for interconnection - Usually low kilowatt capacity
- Inverter inherently limits fault current
- Inverter tends to shut down automatically upon
overload or reverse power - IEEE Proposed Standard P-1547
- Intended to address DER without regard to prime
mover (wind, fuel cell, etc) - Attempts to address systems up to 10 Mw in size
- Seeks to provide universal solution
9Interconnecting DER with Electric Power Systems
- User Concerns
- Safety of Personnel
- Personnel must be able to work on the EPS and DER
facility without undue risk of injury or death - General public should not be exposed to hazardous
conditions - Fault duty, including DER, should not exceed
ratings of distribution system equipment,
including customer-owned equipment connected to
the system - Equipment damage, downed conductors, vault fires,
etc. - Normal load-carrying and interrupting
capabilities, including DER, should not be
exceeded - Reduction of system reliability, premature
failure of equipment - Protective relaying and control equipment, should
not be subject to mis-operation as a result of
DER additions - More and longer interruptions, high/low voltage
problems
10Interconnecting DER with Electric Power Systems
- Producer and General Interest Concerns
- Interconnection costs must be minimal
- Interconnection equipment should be some fraction
of the cost of the DER being connected. - Utility involvement should be minimized
- Impact studies cost too much
- Some utilities use interconnection standards as a
means of killing DER - Interconnection must be simple so that it wont
discourage DER applications - Interconnection apparatus should be maintenance
free as much as possible - Interconnection operation should be automatic
11Interconnecting DER with Electric Power Systems
- Basic Problem
- Most Utility Electric Power Systems (EPS)
were/are not designed to accommodate active
generation and energy storage at the distribution
level. - Basic Need
- Develop technology and operational concepts that
will enable realization of DR benefits while
avoiding negative impacts on system reliability
and safety
12Interconnecting DER with Electric Power Systems
- Significant Problem Areas
- Scaling
- My typical distribution feeder has a peak load
of 4 Mw. Adding a few kW of PV is a whole
different problem than adding 400 kW. - Islanding
- Utility is still responsible for voltage and
frequency of all its customer connections.
Creating an island where some utility customers
are supplied with un-controlled voltage or
frequency is unacceptable - Safety
- Personnel working on the distribution system MUST
be protected from backfeed or accidental
energization - Protection System Design
- Radial distribution line protection is designed
and coordinated for one way power flow.
Bi-directional flow in some part or all of a
feeder is a whole new world of problems - Networked Distribution System
- Consideration postponed to future updates
13Interconnecting DER With Electric Power Systems
- Whats Next?
- Working Group meeting to discuss ballot results,
possible resolution was held January 30-February
1 - Writing Group to meet and attempt to resolve
negative ballots received on Draft 8 - New Draft of P-1547 to be circulated for ballot
before mid-year - Still optimistic on submitting proposed standard
to IEEE Standards Board before the end of 2002