ABB - PowerPoint PPT Presentation

1 / 13
About This Presentation
Title:

ABB

Description:

... Practice for Utility Interface of Photovoltaic (PV) Systems ... Aimed at Photovoltaic Generator Systems, using solid-state inverters for interconnection ... – PowerPoint PPT presentation

Number of Views:63
Avg rating:3.0/5.0
Slides: 14
Provided by: cesCl
Category:
Tags: abb | photovoltaic

less

Transcript and Presenter's Notes

Title: ABB


1
POWER SYSTEM 2002 CONFERENCE -- IMPACT OF
DISTRIBUTED GENERATION
Interconnecting DER With Electric Power Systems
Image
Image
ABB
2
Interconnecting DER with Electric Power Systems
  • Existing IEEE Standards
  • Standards Coordinating Committee 21
  • IEEE Standard 929-2000 Recommended Practice
    for Utility Interface of Photovoltaic (PV)
    Systems
  • Standards Coordinating Committee 23
  • IEEE Standard 1001-1988 Guide for Interfacing
    Dispersed Storage and Generation Facilities with
    Electric Utility Systems
  • Current IEEE Standards Work
  • IEEE P-1547 Standard for Interconnecting
    Distributed Resources with Electric Power Systems

3
Interconnecting DER with Electric Power Systems
  • Definitions

4
Interconnecting DER with Electric Power Systems
  • P-1547 Project Approved in March 1999
  • 4 - 6 meetings of Working Group per year since
    then
  • Working Group Members
  • More than 200 names on Working Group Roster
  • 100 members attend each Working Group Meeting

5
Interconnecting DER with Electric Power Systems
  • Three Official IEEE Balloting Member Categories
  • User
  • The user is the person who will apply the
    standard when interconnecting DER to the electric
    power system. For example, the utility, the DER
    owner, etc.
  • Producer
  • The producer is the person who will apply the
    standard when producing equipment that will be
    interconnected to the electric power system. For
    example, equipment manufacturers, installers,
    etc.
  • General Interest
  • The general interest person is one who is
    interested, but not directly involved in
    interconnecting DER to the electric power system.
    For example, regulatory agencies, financial
    institutions, advocacy groups, etc.

6
Interconnecting DER with Electric Power Systems
  • Draft 7 circulated for ballot --- closing date of
    April 1, 2001
  • Vote Results
  • 66 Affirmative, not enough for approval (75
    required)

7
Interconnecting DER with Electric Power Systems
  • Draft 8 circulated for ballot -- closing date of
    October 2, 2001
  • Vote Results
  • 66 Affirmative, not enough for approval (75
    required)

8
Interconnecting DER with Electric Utility Systems
  • IEEE Standard 929
  • Aimed at Photovoltaic Generator Systems, using
    solid-state inverters for interconnection
  • Usually low kilowatt capacity
  • Inverter inherently limits fault current
  • Inverter tends to shut down automatically upon
    overload or reverse power
  • IEEE Proposed Standard P-1547
  • Intended to address DER without regard to prime
    mover (wind, fuel cell, etc)
  • Attempts to address systems up to 10 Mw in size
  • Seeks to provide universal solution

9
Interconnecting DER with Electric Power Systems
  • User Concerns
  • Safety of Personnel
  • Personnel must be able to work on the EPS and DER
    facility without undue risk of injury or death
  • General public should not be exposed to hazardous
    conditions
  • Fault duty, including DER, should not exceed
    ratings of distribution system equipment,
    including customer-owned equipment connected to
    the system
  • Equipment damage, downed conductors, vault fires,
    etc.
  • Normal load-carrying and interrupting
    capabilities, including DER, should not be
    exceeded
  • Reduction of system reliability, premature
    failure of equipment
  • Protective relaying and control equipment, should
    not be subject to mis-operation as a result of
    DER additions
  • More and longer interruptions, high/low voltage
    problems

10
Interconnecting DER with Electric Power Systems
  • Producer and General Interest Concerns
  • Interconnection costs must be minimal
  • Interconnection equipment should be some fraction
    of the cost of the DER being connected.
  • Utility involvement should be minimized
  • Impact studies cost too much
  • Some utilities use interconnection standards as a
    means of killing DER
  • Interconnection must be simple so that it wont
    discourage DER applications
  • Interconnection apparatus should be maintenance
    free as much as possible
  • Interconnection operation should be automatic

11
Interconnecting DER with Electric Power Systems
  • Basic Problem
  • Most Utility Electric Power Systems (EPS)
    were/are not designed to accommodate active
    generation and energy storage at the distribution
    level.
  • Basic Need
  • Develop technology and operational concepts that
    will enable realization of DR benefits while
    avoiding negative impacts on system reliability
    and safety

12
Interconnecting DER with Electric Power Systems
  • Significant Problem Areas
  • Scaling
  • My typical distribution feeder has a peak load
    of 4 Mw. Adding a few kW of PV is a whole
    different problem than adding 400 kW.
  • Islanding
  • Utility is still responsible for voltage and
    frequency of all its customer connections.
    Creating an island where some utility customers
    are supplied with un-controlled voltage or
    frequency is unacceptable
  • Safety
  • Personnel working on the distribution system MUST
    be protected from backfeed or accidental
    energization
  • Protection System Design
  • Radial distribution line protection is designed
    and coordinated for one way power flow.
    Bi-directional flow in some part or all of a
    feeder is a whole new world of problems
  • Networked Distribution System
  • Consideration postponed to future updates

13
Interconnecting DER With Electric Power Systems
  • Whats Next?
  • Working Group meeting to discuss ballot results,
    possible resolution was held January 30-February
    1
  • Writing Group to meet and attempt to resolve
    negative ballots received on Draft 8
  • New Draft of P-1547 to be circulated for ballot
    before mid-year
  • Still optimistic on submitting proposed standard
    to IEEE Standards Board before the end of 2002
Write a Comment
User Comments (0)
About PowerShow.com