Title: The International Linear Collider
1- The International Linear Collider
Gerry Dugan ILC/GDE and Cornell University
2Why ee- Collisions?
- elementary particles
- well-defined
- energy,
- angular momentum
- uses full COM energy
- produces particles democratically
- can mostly fully reconstruct events
3A Rich History as a Powerful Probe
4The Energy Frontier
5International Linear Collider The Global Design
EffortMission
- Produce a design for the ILC that includes a
detailed design concept, performance assessments,
reliable international costing, an
industrialization plan , siting analysis, as well
as detector concepts and scope. - Coordinate worldwide prioritized proposal driven
R D efforts (to demonstrate and improve the
performance, reduce the costs, attain the
required reliability, etc.)
6GDE Organization
7Formation of the Global Design Effort
- Director Barry Barish Appointed in March 2005
- Appointed Regional Directors (Gerry Dugan
(Americas), Fumihiko Takasaki (Asia), Brian
Foster (Europe)) - Three regional directors have identified GDE
members (with agreement from BB) - Currently 66 members, representing approximately
25 FTE - GDE Central Team consists of
- core accelerator physics experts
- 3 CFS experts (1 per region)
- 3 costing engineers (1 per region)
- 3 communicators (1 per region)
- representatives from World Wide Study
8GDE Central team
Chris Adolphsen, SLAC Deepa Angal-Kalinin,
CCLRC Jean-Luc Baldy, CERN Philip Bambade, LAL,
Orsay Barry Barish, Caltech (the boss) Wilhelm
Bialowons, DESY Grahame Blair, Royal Holloway Jim
Brau, University of Oregon Karsten Buesser,
DESY Elizabeth Clements, Fermilab Michael
Danilov, ITEP Jean-Pierre Delahaye, CERN (EU dep.
dir.) Gerald Dugan, Cornell University (Americas
dir.) Atsushi Enomoto, KEK Brian Foster, Oxford
University (EU dir.) Warren Funk, JLAB Jie Gao,
IHEP Peter Garbincius, Fermilab Terry Garvey,
LAL-IN2P3 Susanna Guiducci, INFN Hitoshi Hayano,
KEK Tom Himel, SLAC Maxine Hronek, Fermilab Bob
Kephart, Fermilab Eun San Kim, Pohang Acc
Lab Hyoung Suk Kim, Kyungpook Natl Univ Shane
Koscielniak, TRIUMF Kyoshi Kubo, KEK Vic Kuchler,
Fermilab Masao Kuriki, KEK Lutz Lilje, DESY
Tom Markiewicz, SLAC David Miller, Univ College
of London Shekhar Mishra, Fermilab Youhei Morita,
KEK Alex Mueller, LAL-IN2P3 Norihito Ohnchi,
KEK Hasan Padamsee, Cornell University Carlo
Pagani, DESY Nan Phinney, SLAC Dieter Proch,
DESY Pantaleo Raimondi, INFN Tor Raubenheimer,
SLAC Francois Richard, LAL-IN2P3 Marc Ross,
SLAC Perrine Royole-Degieux, GDE/LAL Kenji Saito,
KEK Andrei Seryi, SLAC Daniel Schulte, CERN John
Sheppard, SLAC Tetsuo Shidara, KEK Sasha
Skrinsky, Budker Institute Fumihiko Takasaki, KEK
(Asia dir.) Laurent Jean Tavian, CERN Nobuhiro
Terunuma, KEK Nobu Toge, KEK Nick Walker, DESY
(EU dep. dir.) William Willis, Columbia
University Andy Wolski, LBL Hitoshi Yamamoto,
Tohoku Univ Kaoru Yokoya, KEK 66 members
9- International Linear Collider Timeline
2005 2006 2007 2008
2009 2010
Global Design Effort
Project
Baseline configuration
Reference Design
Technical Design
ILC RD Program
Expression of Interest to Host
International Mgmt
10Global Design Effort organization-International
Management Phase
11Starting Point for the GDE
Superconducting RF Main Linac
12Parameters for the ILC
- Ecm adjustable from 200 500 GeV
- Luminosity ? ?Ldt 500 fb-1 in 4 years
- Ability to scan between 200 and 500 GeV
- Energy stability and precision below 0.1
- Electron polarization of at least 80
- The machine must be upgradeable to 1 TeV
13Scope of the 500 GeV machine
- Main linacs length 21 km, 20,000 RF cavities
(total) - RF power 600 10-MW klystrons and modulators
(total) - Cryoplants 6 plants, cooling power 30 kW (_at_4K)
each - Beam delivery length 3 km, 200 magnets
(total) - Damping ring circumference 6 km, 400 magnets
(each) - Beam power 22 MW total
- Site power 200 MW total
- Site footprint length 47 km (for option to
future upgrade to 1 TeV) - Bunch profile at IP 500 x 6 nm, about 300
microns long
14Accelerator Physics Challenges
- Developing efficient high gradient
superconducting RF systems - Requires efficient RF systems, capable of
accelerating high power beams (MW) with small
beam spots (nm). - Achieving nm scale high-power beam spots
- Requires generating high intensity beams of
electrons and positrons - Damping the beams to ultra-low emittance in
damping rings - Transporting the beams to the collision point
without significant emittance growth or
uncontrolled beam jitter - Cleanly dumping the used beams.
15Affordability challenges
Civil
SCRF Linac
16GDE Design Approach
Create a baseline configuration for the machine
Document a concept for ILC machine with a
complete layout, parameters, etc. defined by the
end of 2005. This process continued much of the
design work of the past decade, including the
recent ILC workshops at KEK (Nov. 2004) and
Snowmass (Aug. 2005).
17GDE Baseline Design
- Make forward looking choices, consistent with
attaining performance goals, and understood well
enough to do a conceptual design and reliable
costing by end of 2006. Technical and cost
considerations will be an integral part in making
these choices. - Establish alternate configurations which may
have cost and or performance benefits, but which
need further RD for validation. - - Baseline is under configuration control,with
a defined process for changes to the baseline.
18ILC Baseline Configuration
- Configuration for 500 GeV machine with
expandability to 1 TeV - Some details locations of low energy
acceleration crossing angles are not indicated
in this cartoon.
19ILC Baseline Layout
20ILC Baseline Layout-IR area
21Baseline Gradient
22The Main Linac Configuration
- Klystron 10 MW (alternative sheet beam
klystron) - RF Configuration 3 Cryomodules, each with 8
cavities - Quads one every 24 cavities is enough
23Other Features of the Baseline
- Positron Source Helical Undulator with
Polarized beams
24ILC Siting and Conventional Facilities
- The design is intimately tied to the features of
the site - 1 tunnels or 2 tunnels?
- Deep or shallow?
- Laser straight linac or follow earths curvature
in segments? - GDE ILC Design will be done to samples sites in
the three regions - North American sample site will be near Fermilab
- Japan and Europe are to determine sample sites by
the end of 2005
25Americas Sample Site
- Design to sample sites from each region
- Americas near Fermilab
- Japan
- Europe CERN DESY
- Illinois Site depth 135m
- Glacially derived deposits overlaying Bedrock.
The concerned rock layers are from top to bottom
the Silurian dolomite, Maquoketa dolomitic shale,
and the Galena-Platteville dolomites.
26GDE Reference Design and Technical Design
- A reference design and cost estimate will be
carried out in 2006. A parametric design and
costing approach will be used. - Technical performance and physics performance
will be evaluated for the reference design. - Subsequently, in 2007 and beyond, a full
Technical Design will be developed, based on a
specific site, including a fully-developed cost
estimate, and supported by a global RD program. - The goal is to have the project ready for a
construction start decision around 2010.
27Reference Design Report Matrix
28Preliminary unofficial draft tentative RDR
schedule (not yet confirmed)
- Jan 19-20 KEK meeting. Orient Area systems
managers, define layouts and ML basic unit - Feb 13-14 FNAL mtg Review ML and BDS optic,
Iterate availability budgets, Agree to RDR
Outline and writing assignments, Review costing
methodology for SC cryomodules - March 9-11 GDE, Bangalore Review costing
procedures esp. SC cryomodules, Review AS
progress and plans, Review design parameter
balance, Review TS and GS progress and plans
including resources, Review status on costing
major linac items, Review/optimize linac civil
layout after soliciting comments from experts - April (tbc) DESY mtg Review RF power,
cryomodule, and cavity TS, Review e-, e, RTML
optics, DR Optics, Presentation on LLRF and beam
instrumentation systems and cost estimates - July 19-23 GDE, Vancouver Review ILC design and
cost, Review AS physics studies, Review write-up
progress, propose cost trades and design
modifications - Nov 6-8 GDE, Valencia Finalize RDR
29Test Facility at KEK
30Test Facility at SLAC
31TESLA Test Facility Linac - DESY
240 MeV
120 MeV
16 MeV
4 MeV
32 Cryomodule string test ILCTA-NML at Fermilab
New Muon Lab (NML)
FNPL Photo-Injector
- Building a dedicated ILC cryomodule string test
facility in the New Muon Lab - Building is cleaned out except for removal of CCM
( in progress) - Started to install cryogenic system
- Move FNPL Photo-injector to provide electron beam
(Late FY06) - Upgraded FNPL will provide beam tests of ILC
cryomodules
33(No Transcript)
34ILC Costs
- The ILC will be built as an international joint
project, in which the three regions will
contribute mainly in kind (specific components) - The general concept is that the host country pays
for most of the civil work and support
infrastructure. This will be 25 of the total.
This extra contribution by the host must be at a
level where it is attractive to host the ILC.
The high tech part of the project (75) will be
equally shared by the three regions (at least
that is the present thinking) - Cost estimates must be done in the context of the
in-kind contribution model. - The cost estimate should provide a realistic and
sufficient basis for the regions to make their
decision on the scope of their involvement and
to select the desirable systems/components for
them to manufacture. - An example of how this has been done is the ITER
project
35International Thermonuclear Experimental Reactor
36ITER cost estimate
- Define procurement packages-information needed
by suppliers to prepare contracts. - Obtain estimates from suppliers in different
regions. - ITER project Central Team compares and
re-evaluates estimates from the different
regions. - The Evaluated Cost Estimates are expressed in
a globally unified virtual money, i.e. ITER Unit
Account (IUA) . (1000 in Jan, 1989) - These cost estimates are based on world market
prices for standard material and equipment, and
rates in IUA/hr for assembly labor and
manufacturing support.
37ITER cost estimate
- This approach is taken to remove variations in
costs due to differences in estimating practices
and exchange rates in the several regions. This
approach is most valid for items for which
manufacturing processes are well defined. - The detailed basic data in IUA can be used for
cost optimization and cost reduction studies. - These data are the basis on which the allotment
of in-kind contributions to each region is made. - Because the cost borne by a given region to
supply its in-kind contribution will in general
differ from the nominal cost in translated IUA,
the actual cost of the ITER project will never be
known.
38ILC Cost estimates
- ILC cost estimates must be done in the context of
a project implemented through in-kind
contributions. - We will need to secure regional component cost
estimates and evaluate these in terms of a
globally defined cost unit. (ILC unit) - The complete cost estimate will be translatable
into a given regions currency and cost
estimating methodology. - Because of these differences, the projects cost
on paper will appear different in different
regions.
39ILC cost estimate
- Negotiations between the regions will decide the
relative regional in-kind contributions, based on
the values in ILC units. - The host region will bear the conventional
construction costs. - In-kind contributions, which are the
responsibility of the region to make good on
their contribution, reduce the risk to the
project. - Central resources must have shared
responsibility, and responsibility for
non-delivery by a region must be shared by the
collaboration in a pre-agreed manner. - The true cost of the in-kind contributions will
not be easily determined after completion of the
project. - Cost reduction strategies must be worked out with
regional or international industrial partners.
40ILC Industrialization
- Three industrial forums have been formed to
support the industrialization of the ILC -
Linear Collider Forum of Japan Linear Collider
Forum of America European Superconducting RF Forum
The purpose of the Industrial Forums is to bring
industry, national laboratories, and universities
together at an early stage to plan the ILC in an
industrial context.
41Industrialization issues
- ILC will be viewed as a project, not a
sustainable business area, therefore it must be
prepared to fund one time manufacturing
engineering and tooling costs. - Long term funding uncertainties create barriers
to major industry commitments to the ILC - In general, technology will flow from labs to
small companies small companies will partner
with larger ones for full scale production - ILC test facilities at key labs will accelerate
tech transfer - Specifications can be a major cost driver and
must be critically evaluated - Costs, risk and schedule are interrelated, must
be understood and agreed to by everyone.
42Industrialization issues
- Infrastructure Issues
- For industry to invest in the large
infrastructure required for ILC there would have
to be a follow-on business or market - the ILC project should plan on paying for the
major infrastructure wherever it is built. - Early standardization is important
- Can deal with whatever standards ILC chooses
- Risks
- Let industry make up its mind on risks
- Perceived risks will influence the actual cost of
contracts from industry
43Cost Reductions viaindustrialization
- Each industrial company is characterized by its
own production technologies including production
facility, engineering skill, etc. - When the design configuration and fabrication
process of the ILC components fit to existing
production technologies, cost may be reduced,
because no additional investment is necessary. - Reviews of product design and fabrication
processes are therefore very important.
44Cost Reductions viaindustrialization
- Cost at industry scale fabrication is lower than
that at laboratory scale fabrication. But dont
expect too much for cost reduction through mass
production, because ILC is not large enough for
getting meaningful learning effects. - Quantitative analysis, through industrial
studies, is necessary. - Joint factories can avoiding duplicated
investments - Electro-chemical polishing facility
- EBW facility
- Test facility using liquid helium
- These facilities might be used by industry with a
reasonable charge (rental factory). It does not
matter whether these facilities are located
on-site or off-site.
45Conclusions
- The International Linear Collider is a major new
particle accelerator for the precision study of
fundamental physics at the TeV scale using ee-
colliding beams. - The project is being designed by an international
team and will be executed as a fully
international project, with participation from
the Americas, Asia and Europe. - The project offers major new challenges in
accelerator design and accelerator technology
development, cost optimization, the development
of effective management structures for global
collaboration, and trans-national
industrialization.