Title: Research and Development for the International Linear Collider
1Research and Development for the International
Linear Collider
- presented by Marc Ross - for the ILC Project
Managers
Marc Ross - (Fermilab), Nick Walker - (DESY),
Akira Yamamoto (KEK)
2ILC Background
- traced back to
- e/e- collider labs
- where the linear collider was born
- BINP, SLAC, KEK, Cornell, DESY,
- where cold SRF linac technology started
- Technology Reviewed (TRC)
- Recommendation made (ITRP)
- 1995, 2002 and 2004
- 0.5-1 TeV ILC ? Superconducting Linacs
3Look back 2004
- International Technology Recommendation Panel
(ITRP) Report - (released during LINAC 2004 Conference, Lubeck)
Basis of the ITRP decision basis of our progress
since then rests in large part on EU XFEL
project
4International Linear Collider R D
- OUTLINE
- Reference Design a global effort
- Critical R D for Accelerator systems (non SRF)
- Critical R D for Main Linac Technology
- Project Preparation
- Conclusion
5ILC Reference Design
- 3000 bunches each 3 nC e / e- 20 MW avg.
Beam Delivery and Interaction Region
6ILC R D Global effort
- ILC Reference Design (RD)
- based on R D in support of TESLA, SBLC,
JLC/NLC, VLEPP, CLIC - RD Report authored by 325 institutions (including
physics/detectors) - EU-XFEL ? a large scale demonstration
7SRF Test Facilities
7
8(Non-SRF) Beam Test Facilities
8
9GDE ILC Timeline and Mission
GDE process
Reference Design Report (RDR)
Tech. Design Phase (TDP) 1
TDP 2
LHC physics
Ready for Project Submission
Prepare a design and a plan that is completely
ready to go - 2012. The request from the HEP
community is clear (Brian Foster). Since the
timeline is uncertain focus on R D for cost
and risk reduction develop ties within the
accelerator community to facilitate a global
project
9
10Resources
- Basis institutional and regional support for
science ILC will provide. - Also Support for science complements strong
interest in emerging technologies - ILC development effort utilizes
- ILC project preparation-specific funding
- support for design and cost/risk reduction
studies for the TDR - other project-specific funding (XFEL etc)
- generic RD
- support for the development of specific
technologies - combinations of the above
- beam test facility support
11In-Kind RD
- provides return for regions/institutions
investing resources for technical development - To ILC
- Beam Studies
- Infrastructure usage
- Engineering and Testing
- To contributing Institute / Region
- Technology transfer between partner ILC
institutions - Infrastructure development and qualification
- Community connection mechanisms
12The role of RD
- in support of a mature, low risk design
- take advantage the ongoing, increasing global
investment in SRF and related technology - the big impact of the ITRP decision
- Improve performance, reduce cost, challenge
limitations, develop inter-regional ties, develop
regional technical centers - Both a project-based and a generic focus
- The ILC has
- A Baseline Design to be extended and used for
comparison (RDR) - But ready for deployment
- Research and Development activities on Alternates
to the Baseline - Engages the community ? venue for cost-saving /
risk-reduction actvities - Plug compatibility / modularity policy ?
flexibility between the above - The critical role of associated projects XFEL,
Project X, SNS, JLab12, ERLs, - Models of project implementation
- The transition from RD to a real project
- The link between Technical Phase RD and the
project political process
13International Linear Collider R D
- Reference Design a global effort
- Critical R D for Accelerator systems (non SRF)
- Critical R D for Main Linac Technology
- Project Preparation
- Conclusion
14ILC Reference Design
Examples
Beam Delivery and Interaction Region
- Positron Source, Damping Ring, Beam Delivery
15Critical R D Accelerator Systems Positron
Source
- Positron Source Design
- Each ILC pulse high energy electrons pass through
a helical undulator that generates 20 MeV gamma
rays - These gamma rays are directed on a high power
rotating titanium target - Generated positrons are collected through a very
short focus, close proximity lens (OMD) and
captured in a normal-conducting RF accelerator - The positrons are injected into the positron
damping ring to be used for collisions on the
next machine pulse
16RDR Positron Source Layout
- R D Priorities
- Undulator (UK RAL, Cornell Mikailichenko)
- Target (KEK, BINP Logachev)
- Optical Matching Device (OMD)- replacement for
Flux Concentrator - Liquid Lithium Lens (KEK, BINP Logachev)
- Capture RF normal conducting accelerator
(Paramonov INR, SLAC)
17Linear Collider Positron Source
lt Li Out
Li In gt
Lithium Lens with feeding cables. (Courtesy of
Yu. Shatunov, BINP)
Lithium Lens CAD model section view. (Courtesy of
Alexander Mikhailichenko, Cornell)
18BINP Positron System R D
- Liquid Lead target development for KEK-B
- (years of operational experience at BINP)
- Initial activity for SLAC - NLC
- Alternate to baseline rotating target (also
tested at BINP) - To be installed at KEK-B Linac 2009
- Boron Nitride window / brazing tests underway
- Used in liquid target
- Also applicable to Lithium Lens applications
- Liquid Lithium Lens
- factor 2 improved capture compared to pulsed
electromagnet - design study in 2009 support from BINP and KEK
- High pressure Li is main issue
19 Positron source First Ever Full Length
Undulator Cryomodule
Ln2 precooling
Constructed by Rutherford Appleton Lab. First
cooldown of complete system early Sept 08.
Vac vessel closed
Vertical magnet tests successful design field
exceeded in both 1.75m undulators But, vacuum
leak when cold now being repaired should be
complete by Jan 09
KEK ATF Beam Test planning
20Critical R D Accelerator Systems Damping
Ring
- Damping Ring Design
- Two 6 km circumference 5GeV damping rings (e /
e-) - Each pulse inject 3000 bunches and damp to
very low emittance in 200 ms - Bunch spacing 6 ns
- Extract one by one with very fast pulse
magnet kicker a bunch every 300 ns - Component testing with beam at test facilities
- Cornell (CESR TA)
- Dafne (Frascati)
- ATF (KEK)
21Damping Rings Critical RD
- Electron cloud.
- Goal is to demonstrate effective mitigation
methods. - Studies are in progress at CesrTA, DA?NE, KEKB.
- Fast injection/extraction kickers.
- Goal is to demonstrate fast, high-power pulsers
meeting ILC damping rings specifications. - Studies are in progress at ATF, DA?NE, SLAC.
- Low-emittance tuning.
- Goal is to demonstrate reliable operation with 2
pm vertical emittance. - Typical beam size few microns
- Swiss Light Source has recently achieved 3 pm.
- Studies are in progress at ATF and CesrTA.
21
22Electron Cloud Studies in CesrTA
- Installation of wigglers in former location of
CLEO (above). - Retarding field analyzers in wiggler vacuum
chambers, and first data (right).
22
23Fast Kicker RD
- The goal is to develop and demonstrate a
high-reliability fast kicker that meets the ILC
specifications for damping ring injection and
extraction. - RD program includes activities at SLAC, INFN/LNF
and KEK. Drift Step Recovery Diodes ? - Anatoly Krasnykh, SLAC and
- A. Kardo-Sysoev, Ioffe Institute of Physics (RAS)
Proposed for smaller 3 km circumference damping
rings
23
24Fast Injection/Extraction Kickers SLAC
- Researchers at SLAC are investigating two
possible technologies MOSFET array, and DSRD
fast switch. - Both technologies provide attractive
characteristics. - A hybrid pulser may be the best solution.
1 ns / division
24
25Critical R D Accelerator Systems Beam
Delivery
- Beam Delivery (BDS) Design
- BDS delivers the beam from the high power linac
to the users detector - The BDS provides high power collimation and
precision focusing of the beams - There will be two detectors arranged to they can
be exchanged using a push-pull mechanism - Critical BDS components live within the
detector - BDS relies on precision instrumentation systems
and optics correction algorithms - Collimation of high density, high power beams is
a key technology - Beam testing is required ATF2 at KEK
26Beam Delivery System R D
- ATF2
- constructed, hardware mostly commissioned
- Next beam commissioning
- Developing long-terms plans for AFT2
- SC FD
- squeezed beta tests, etc
- IR integration (MDI)
- have a new version of IR Interface Document
- the document is focused on functional
requirements - MDI and DDI (Detector-Detector Interface)
- Also a lot of progress on detailed Detector and
MDI design
Andrei Seryi, SLAC, BDS Group Leader
26
27Travelling focus
Travelling focus idea proposed by Vladimir
Balakin at the "Beam-Beam and Beam-Radiation
Interactions, High Intensity and Nonlinear
Effects", the 7th ICFA Workshop on Beam Dynamics,
UCLA, USA, 13-16 May 1991, and also at the Linear
Collider Workshop LC91, Protvino, 1991
28International Linear Collider R D
- Reference Design a global effort
- Critical R D for Accelerator systems (non SRF)
- Critical R D for Main Linac Technology
- Project Preparation
- Conclusion
29Critical R D Main Linac Technology
- Main Linac Design
- Each pulse a 3 MHz bunch train of e- and e is
accelerated from 5 to 250 GeV using two 11 km
linacs - Each linac has 8000 9 cell superconducting
standing wave RF cavities operating at 1.3 GHz - Gradient 31.5 MV/m
- RF Power for each linac is provided through
rectangular waveguide from 300 10 MW peak power
multi-beam klystrons - The main linac is a cost driver R D is
underway to - Improve gradient performance
- Produce and transport high power RF more
efficiently - Test components and systems in each region
- EU-XFEL (17 GeV) uses almost identical technology
30Superconducting Cavity RD
- Niobium Sheet metal cavity
- Fabrication
- Forming and welding (EBW)
- Surface Process
- Chemical etching and polishing
- Cleaning
- Inspection/Tests
- Optical Inspection (warm)
- Thermometry (cold)
30
31Combined Yield of Jlab and DESY Tests
23 tests, 11 cavities One Vendor
48 Tests, 19 cavities ACCEL, AES, Zanon, Ichiro,
Jlab
50
Yield 45 at 35 MV/m being achieved by cavities
with a qualified vendor !!
31
32Klystron RF Power Source
- Russian Design team fabricated in Japan
- Most successful 10 MW multi-beam klystron ?
BASELINE
33Cost Reduced RF Concepts
Basis 2 tunnels
Surface Klystron Cluster (SLAC KEK)
Both options aimed at single-tunnel solutions
Also Distributed RF Source Concept (KEK)
34Civil Engineering
- 30 of the estimated cost
- Three sample sites studied Japan, CERN,
Illinois - Quite similar configurations deep rock dual
tunnel - JINR suggested a 4th sample site near Dubna
- Studied 20 years ago
- This site has several contrasting features that
provide a comparison basis - Single tunnel with near surface building
- Soft tunneling material
- Siting process is political but it is useful to
have studied and reported sample sites
35Deep Shallow Site Configurations
35
36International Linear Collider R D
- Reference Design a global effort
- Critical R D for Accelerator systems (non SRF)
- Critical R D for Main Linac Technology
- Project Preparation
- Collaboration with CERN
- Making the transition from broad-based R D to a
practical Project - Conclusion
37Collaboration with CLIC / CERN
- Formulated (Barish/Aymar) 11.2007
- Established in 02.2008 initially 5 working
groups - Exclusive strategy
- pick and choose efforts with strong commonality
optimize use of resources - startup philosophy choose tasks more likely to
succeed - Promoting communication / links between the two
groups - will facilitate discussion and consensus building
between teams - improving the credibility of both
- Common costing methodology / basis is a
collaboration priority
38ILC R D Resources
- (summarized in R D Plan published 2008.06)
- 2007-2010 ? 4 years
39International Linear Collider R D
- Reference Design a global effort
- Critical R D for Accelerator systems (non SRF)
- Critical R D for Main Linac Technology
- Project Preparation
- Conclusion
40Conclusion
- ILC Global Design Effort has 3 goals
- Developing the community
- Doing R D
- Designing the ILC and preparing a practical
Project - Until end 2012
- ILC GDE is launching the first truly global
large scale international science project - Based roughly equally in each of three regions
Americas, Europe and Asia - We invite and strongly encourage your continued
and increased participation!