Laser Building Status
  • Original Deadline 2/28/2005
  • Since the contract awarded a month
    earlier (9/04 instead of 10/04)
  • the contract completion date was
    1/31/2005
  • Mid last month, a problem stand-out
  • JLab supposed to provide the locations
    of all utilities
  • three known 480V systems could not be
    located (no drawings!)
  • some meetings, several memos, two weeks
    later, a solution was found
  • New completion date 2/15/2005
  • Jobs after the laser building construction
    completion to get the lab ready
  • cable trays, utilities
  • screens
  • safety interlock system

2
Transversity Tasks (II)
  • Polarized 3He target
  • Polarization reversal
  • adiabatic RF flip
  • laser polarization reversal
  • Vertical coils
  • Target ladder-oven system
  • Cells
  • Optical lines
  • NMR
  • EPR
  • Field measurement