Title: MINISTRY OF FUEL AND ENERGY OF UKRAINE


1
  • MINISTRY OF FUEL AND ENERGY
    OF UKRAINE
  • Department of Nuclear Energy and Atomic
    Industry

Safety Improvement of Nuclear Power Plants in
Ukraine
Svyshch Andrii
RER/4/027 Strengthening Capabilities for Nuclear
Power Performance and Service Life including
Engineering Aspects Regional Workshop on
Modernization Projects of NPP Instrumentation and
Control Systems Related to Power Uprates and
License Renewals
2
NUCLEAR POWER PLANTS OF UKRAINE
?yiv
3
The Comprehensive Program on Upgrading and
Safety Improvement of Ukrainian NPPs
  • April, 1999 - first IAEA hearings of Ukraine's
    National Report on the Nuclear Safety Convention
    implementation.
  • As a result a Comprehensive Program on Upgrading
    and Safety Improvement of Ukrainian NPPs was
    developed and was acting for a period of
    2002-2005.
  • The Comprehensive Program was the main program on
    safety upgrade of Ukrainian NPPs for the period
    of 2002-2005

4
Structure of the Comprehensive Program on
Upgrading and Safety Improvement of Ukrainian
NPPs
  • Actions ensuring the nuclear safety
  • Actions increasing the level of the fire
    prevention
  • Actions on componential replacement of automatic
    control systems.
  • Actions on NPPs lifetime extension

4
5
Structure of the Comprehensive Program on
Upgrading and Safety Improvement of Ukrainian
NPPs
  • Actions increasing the radiation security level
  • Actions on the electrotechnical equipment
    replacement
  • Actions on equipment qualification
  • Actions on the level of capacity factor
    increasing

5
6
Results of the Structure of the Comprehensive
Program implementation for the period of its
action (2002-2005)
  • 389
  • actions

130 actions
33
Level of funding relative to the planned one
- about 30
6
7
The Comprehensive Program on Upgrading and
Safety Improvement of Ukrainian NPPs Revision
  • Decision on the Comprehensive Program on
    Upgrading and Safety Improvement of Ukrainian
    NPPs revision was stated in the National Report
    on Implementation of Ukraine's Obligations due to
    the Statements of Convention on Nuclear Safety in
    April, 2005.
  • It was approved by international experts

7
8
The Conception on Safety Improvement of NPPs
  • The Conception on Safety Improvement of NPPs
    was approved by the order of Cabinet of Ministry
    of Ukraine 13/12/2005 ? 515.
  • For its implementation the List of
    Technical-organizational Actions was developed
    and introduced by the Order of the Ministry of
    Fuel and Energy of Ukraine and the Regulatory
    body of Ukraine ?19/10 in January, 25 2006.
  • The Conception includes ways of the safety
    improvements, witch are stated as the most
    important in Reports on Safety Analyses of
    Ukrainian NPPs, taking into account the
    international experience in organization of
    safety improvement programs.

8
9
Planned implementation of The Conception on
Safety Improvement of NPPs
  • For the period of 2006-2008 realization of 244
    pilot actions scheduled
  • 2006
    31 actions
  • 2007
    74 actions
  • 2008
    139 actions.

9
10
The Conception on Safety Improvement of NPPs
Implementation
  • In 2006 34 pilot actions on NPPs were fulfilled
    and realization of the other pilot actions begun.
  • In 2007 103 pilot actions on NPPs were fulfilled
    and 68 pilot actions were extended on the other
    NPPs units.
  • For 2008 the residualy actions are scheduled.
  • Until 2010 all the pilot actions are scheduled to
    be extended on the other NPP units.

10
11
Costs Index for the Conception on Safety
Improvement of NPPs
  • 2006 ?. (fact) 147,4 mln hrn
  • 2007 ?. (fact) 213,3 mln hrn
  • 2008 ?. (plan) 322,7 mln hrn

11
12
Rivne NPP
  • At Rivne NPP unit ?1 all the measures due to
    the Conception shall be fulfilled till the end of
    2008. According to these the Periodic Safety
    Review Report will be developed and allow the
    unit's lifetime extension (the projected lifetime
    of the unit expires in 2010).

12
13
  • Thank You for Your Attention!

13
14
Comprehensive Program Implementation
  • In the period of 2002-2005 for implementation
    of the Comprehensive Program 2 026,0 mln hrn.
    were funded.
  • For the money provided owing to international
    technical cooperation programs actions were
    implemented with total cost of 75 mln hrn.
  • Financing owing to the National Budget for
    the Comprehensive Program implementation haven't
    been provided.

14
15
Means of the safety Improvement due to the
Conception
  • Improvement of the reliability level of the
    function of radioactive materials retention in
    the containment
  • Improvement of the reliability level of emergency
    power supply
  • Improvement of the emergency processes control
    function
  • Intensification of analyses and NPP safety
    substantiation
  • Limitation of equipment dependent failures and
    common cause failures, caused by the internal
    events

15
16
Means of the safety Improvement due to the
Conception
  • Control of the coolant leakage with the diameter
    equivalent 100 mm from the first circuit to the
    second circuit
  • Reliability improvement of the function of
    reactor heat removal through the second circuit
  • Reliability improvement of the first circuit high
    pressure protection in cold state and the thermal
    shock protection
  • Reliability improvement of the first circuit heat
    removal and pressure control function

16