RED1 CHALLENGES - PowerPoint PPT Presentation

About This Presentation
Title:

RED1 CHALLENGES

Description:

... sufficient time to resolve the 'suspensive conditions' ... Business conditions for transfer e.g. asset valuation, ... 'Suspensive Conditions' ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 11
Provided by: adelegr
Category:

less

Transcript and Presenter's Notes

Title: RED1 CHALLENGES


1
RED1 CHALLENGES LEGISLATIVE REQUIREMENTSPARLIA
MENTARY PORTFOLIO COMMITTEE ON MINERALS AND
ENERGY SUBMISSION BY ESKOM FEBRUARY 2007
2
Contents
  1. Background
  2. Working with RED1 in terms of an interim
    Operating Agreement
  3. Lessons Learnt
  4. Conclusion

3
1. Background
  • Eskom ring-fenced its six regions in preparation
    for six wall-to-wall public entity REDs as early
    as 2004, in line with the Energy White Paper and
    the PWC Blueprint on EDI Restructuring
  • RED1 was selected as the first Regional
    Electricity Distributor to be created by July
    2005
  • In May 2005 a decision was taken that REDs will
    be municipal entities and this raised some
    concerns
  • Eskom credit rating, resulting industry cost
    implications and impact on the Eskom capital
    expansion program
  • Governance processes associated with municipal
    entity legislation
  • Notwithstanding these constraints, Eskom entered
    into an interim Operating Agreement with RED1

4
1. Background (continued)
  • Eskom listed its concerns and suggested ways to
    resolve them as part of transfer conditions
    (suspensive conditions) in the Operating
    Agreement
  • In support of immediate progress, the Operating
    Agreement allowed for an earlier transfer of
    domestic customers
  • This provided sufficient time to resolve the
    suspensive conditions
  • In September 2005 Cabinet requested EDI Holdings
    to investigate a model of six Metro REDs and a
    National RED
  • Eskom actively participated in this process
  • In October 2006 Cabinet decided on a model of six
    wall-to-wall public entity REDs
  • This resolved the suspensive conditions related
    to municipal entity governance

5
2. Working with RED1 in terms of an interim
Operating Agreement
The Eskom / RED1 Operating Agreement consists of
the following components
  • Eskom and RED1 obligations in terms of the
    service provided
  • Transition Plan
  • A guiding plan indicating phases, key
    activities and dependencies for transfer
  • Statutory Exemptions and other Conditions
    (Suspensive Conditions)
  • Business conditions for transfer e.g. asset
    valuation, compensation, staff related matters,
    customer and contract transfers, loan covenant
    compliance etc.
  • Requirements for legislative exemptions in terms
    of the Municipal Finance Management Act (MFMA)
    and Municipal Systems Act (MSA)
  • Other legislative, regulatory and statutory
    requirements e.g. regulatory compliance, PFMA
    approval, taxation relief, etc.

6
2a. Operating Agreement - Some Key Obligations
and other areas of cooperation
  • Eskom met the obligations in terms of the
    services provided to RED1
  • Business performance within regulatory provisions
    and industry norms and standards
  • Cooperation during the annual tariff increase
    process to ensure movement towards harmonized
    tariff structures
  • Electrification and Free Basic Electricity
    delivery
  • Minimised customer impact during restructuring
  • In addition, the parties cooperated through
  • Joint load shedding during times of energy
    shortages
  • Making available Eskoms network operating
    (SCADA) system to City of Cape Town
  • Training of City of Cape Town network operating
    staff
  • Joint work groups in preparation for business
    transfer

7
2b. Operating Agreement Transition Plan
In acknowledgement of their commitment to the
eventual transfer of the Eskom supply undertaking
once the suspensive conditions were resolved,
Eskom and RED1 agreed to be guided by a
transitional plan.
8
2c. Operating Agreement Suspensive Conditions
  • Progress
  • Negotiations on staff transfer principles in
    process
  • Preparation for transfer of customer and supplier
    contracts done
  • Electricity supply and service contract with REDs
    defined
  • Eskom loan covenants analysed
  • Transformation funding principles in process of
    being confirmed
  • Issues not yet resolved
  • Asset Valuation and Compensation framework
  • Enabling legislation
  • Taxation relief

Public Entity decision MFMA and MSA exemptions
relating to governance concerns not required
9
3. Lessons Learnt
  1. Enabling Legislation is required to give
    certainty to the restructuring process and to
    move the process beyond a point of no return
  2. Voluntary participation in EDI restructuring
    process will create uncertainty in terms of the
    future realisation of business case benefits
  3. Asset valuation and compensation framework need
    to be in place
  4. Staff related issues to be resolved prior to
    transfer, ensuring organised labour support
  5. Realistic timeframes need to take into account
    the complexities and practicalities of the
    transformation process.

10
4. Conclusion
  • Eskom ring-fencing in preparation for the six
    Public Entity REDs is in an advanced stage
  • Key restructuring enablers need to be supported
    by clear policy. These includes amongst others
  • Asset Valuation and Compensation Framework
  • Municipal Participation
  • National Pricing Framework
  • Industry end-state definition and roadmap
  • Staff Transfer Principles
  • Restructuring Funding
  • Enabling legislation need to support the process,
    including effective regulatory and taxation
    frameworks
  • Eskom will continue to actively support and
    participate in the EDI restructuring process.
Write a Comment
User Comments (0)
About PowerShow.com