Title: 23rd Avenue
123rd Avenue Gateway Boulevard Interchange Review
- Office of the City Auditor
- Larry Laver Gordon M. Babey, M.Sc., P.Eng.
19th Avenue Flyover
23rd Avenue
GatewayBoulevard
CPRail
CalgaryTrail
OCA Webpage - www.edmonton.ca/auditor
2Who We Are
3Roadway Project Life Cycle - Terminology
- Strategic Planning (Transportation Master Plan)
- Concept Planning
- Preliminary Design
- Detailed Design
- Tender/Award
- Construction
- Operations
4The Audit Process
PROJECT MANAGEMENT
AUDIT PROCESS
Strategic Planning
Long-term/Annual Planning
Strategic Planning Concept Planning Preliminary
Design Detailed Design
Long-term/Annual Planning Planning
Strategic Planning Concept Planning Preliminary
Design Detailed Design Construction
Long-term/Annual Planning Planning Fieldwork
Strategic Planning Concept Planning Preliminary
Design Detailed Design Construction Post
Construction
Long-term/Annual Planning Planning Fieldwork
Reporting
5The Audit Process
6Audit Objectives and Reporting
ProjectManagement
CostEstimating
Governance/Approval
Area Planning/Land Acquisition
Procurement
- What are the reasons for the cost increase from
75 to 260 million?
- What are the causes of the delay in project
completion from 2006 to 2011?
-
- Did the City exercise due diligence as project
owner in managing the project?
7What are the reasons for the cost increase from
75 to 261 million?
- Cost increased from 75 million (2003 concept
plan) to - 107 million (2004 preliminary design)
- 134 million (2006 detailed design)
- 261 million (2007 award)
- Overall increase of 186 million
- 86 million for escalation
- 22 million for design/scope changes
- 23 million for underestimation
- 55 million for market conditions
8What are the reasons for the cost increase from
75 to 261 million?
- Benefit-Cost ratio not updated or provided to
decision makers for final decision - The effort put into planning was lower than the
guideline published by the AACE
9What are the reasons for the cost increase from
75 to 261 million?
- Standard methodology for presenting costs not in
place - Tools to validate cost estimates not in place
- Contingencies
- No allowance for unresolved risk elements
- Project cost estimating and budget presentation
are not aligned - Approved budget does not include cost for concept
planning - Cost sharing not reflected in budget
- Cost escalation
- City indices do not reflect heavy construction
escalations - Project estimates not stated in
year-of-expenditure dollars
10What are the causes of the delay in project
completion from 2006 to 2011?
11What are the causes of the delay in project
completion from 2006 to 2011?
- Strategic Planning Possible Lost Opportunities
- Transportation Master Plan, Area Structure Plans,
Traffic Impact Analysis - Fundamental elements were identified during
Strategic Planning - Free flow on Gateway Boulevard/Calgary Trail
- 19th Avenue access
- Pipeline upgrade and environmental concerns
- Cost sharing opportunities
- The need to increase traffic capacity
- Pace of South Edmonton Common development
12What are the causes of the delay in project
completion from 2006 to 2011?
- Concept Planning 9 month delay
- Historically resourcing issues
- Inexperienced staff member assigned as project
manager - Experienced consultant co-managed the project
- Senior Advisory Council established
- Partnering workshop
- Team apprehensive and daunted by the project
- Public hearings remained open 3 months longer
than anticipated - City Council expressed desire to expedite the
project when concept plan approved
13What are the causes of the delay in project
completion from 2006 to 2011?
- Preliminary and Detailed Design 24 month delay
- Citys project manager not full time
- Significant deficiencies in Concept Planning
- Land requirements not communicated in Concept
Plan - Land negotiation delays
- Risk of Municipal Government Act claims after
construction - Design plans developed and maintained for both
over and under passes at 19th Avenue access - Safety concerns identified with underpass
- Alternate designs continued to be evaluated to
end of detailed design
14What are the causes of the delay in project
completion from 2006 to 2011?
- Tender and Construction Award 6 month delay
- Tender close delayed
- Plans and specifications not ready
- Negotiation on tender conditions
- Higher than anticipated costs required Council
approval - Construction term extended 24 months
- Construction of interchange increased from a
2-year period to 3-years (12 months) - Final pavement lift planned for phase 2
incorporated into this project (12 months)
15Cost Estimating Practices
- Organizations
- British Columbia
- New Jersey
- Washington
- Ohio
- Queensland, Australia
- What We Found
- Trending of highway material costs
- Cost estimating validation process
- Office of estimating
- Project cost estimating manual
- Training plan for project cost estimating
- Ongoing analysis of construction inflation
16Did the City exercise due diligence as project
owner in managing the project?
- Ability to influence cost is greatest and most
cost effective early in the project process. - Several reports submitted to Transportation
Public Works Committee/City Council after concept
plan approved - Alternative designs continued to be evaluated
throughout project
17Did the City exercise due diligence as project
owner in managing the project?
- 23rd Avenue Project Assessment
- Project management manual not sufficient
- Communications not fully effective
- Learnings from completed projects not shared
- Process ownership and project resourcing was
lacking - Best practice methods not fully implemented in
the following areas
- Road safety audits
- Risk management
- Records management
- Value engineering
- Constructability reviews
- Partnering sessions
- Traffic impact assessment
- Cost estimating practices
18Enterprise Risk Management
Phase 1Understand the organizations objectives,
strategic direction, stakeholders, and structure.
Phase 4Identification, evaluation and
implementation of actions to address risks
identified as priorities.
Phase 2Identify the consequence a risk event
will have on the stated objectives and existing
mitigating measures.
Phase 5Establish a monitoring process, evaluate
effectiveness of decisions and recommend
revisions.
Phase 3Systematic assessment of risks against
established criteria and setting of priorities.
19Did the City exercise due diligence as project
owner in managing the project?
- Project Management Maturity Assessment
- PMI (Best Practice Methodologies)
- Project Management Institute Maturity Model
- Level 1 Ad Hoc (23rd Avenue/Gateway Boulevard)
- Levels 4/5 (top levels) Integrated/Optimization
(SLRT Drainage Design and Construction)
20Contract Procurement
- 4 contractors pre-qualified only 2 bid
- Tender customization without Law Branch review
(prime contractor issue) - Generally contracts were handled in accordance
with City procedures and processes - Exception - work started on 3 contracts before
documents were in place - Administration reviewed alternative tendering
types to address volatile market conditions - Industry identified a number of potential
improvements - Risk sharing
- Traffic accommodation/detours
- Noise bylaw exemptions (night work)
- Tendering methods
- Flexibility in meeting deadlines (weather delays)
- Involving construction industry during design
21Recommended Improvements
- Alternate project management delivery strategy
- Comprehensive communication plan
- Accountabilities of project managers as project
owners - Recalculation of benefit/cost ratios
- Enhancement of costing models and quality
assurance processes - Adjustment to the capital priorities
planning/budgeting process - Corporate processes (R/R and performance
reporting) - Project team continuity
2223rd Avenue Gateway Boulevard Interchange Review
Questions