Title: Construction Issues Associated With Environmental Projects
1Construction Issues Associated With
Environmental Projects
Barbara L. Kimler, PE Central Area Engineer Rock
Island District
2Why Are These Environmental Projects So Expensive?
31. Environmental work is technically challenging
- Embankment materials are hard to work with,
foundations are soft, and access is difficult. - Work requires specialized, expensive construction
equipment and methods. - This results in higher production costs and lower
productivity rates than traditional civil works
construction.
4Example Specialized Equipment Methods
- Specialized dredges
- Staging from barges
- Floating excavators and swamp buggies
- Timber mats
- Cofferdams and dewatering
- Winter work
5Articulated Dredge
6Barge Staging
7Floating Excavator
8Swamp Buggy
9Timber Mats(or lack thereof)
10Cofferdams and Dewatering
11Winter Work
122. Environmental project work objectives and
requirements are unusual
- To bidders, the contract packages appear like
typical civil works projects such as channel
dredging and flood protection. However, the
actual construction requirements are
non-traditional
13Examples
- Dredgers constructing islands rather than
focusing on excavating channels - Fine grained cover requirements on island
disposal sites - Levees and dikes constructed for impounding water
rather than for flood protection. - .
14Polander Lake Islands
15Fine-Grained Sediment Cap
16Upper Lake Chautauqua Levee
17Result
- Bidders underbid our projects not fully
understanding the requirements - Bidders bid higher than standard construction as
needed to successfully meet our requirements
183. Environmental Contracts Have Time and
Scheduling Restrictions and/ or Limitations
- Working in the floodplain requires scheduling
work around natural riverine cycles - Endangered species and refuge operating
requirements often further restrict scheduling of
work
19Chautauqua Hydrograph
20Milan Bottoms Section 1135 Endangered Species
Requirements
21Impacts to a Contractor
- Additional mobilization and demobilization costs
- Contractor loses some of the best construction
season - Contractor cant continuously schedule work
crews, losing equipment and skilled labor to
other jobs. - Field office overhead costs still have to be
covered - Long duration impacts the Contractors ability to
bid other work - ties up resources and bonding
capacity
22So, What Can Be Done?
23During Contract Development Phase
- Work with resource agencies regarding endangered
species restrictions and refuge management
requirements - Communicate/define actual construction
requirements clearing, work limits, equipment
access with resource agencies early in the design
development - Utilize contracting methods that do not require
selection of the lowest bidder. For example, use
negotiated Best Value procurement methods rather
than sealed bids
24During Contract Development Phase, contd
- Communicate the risks in the contract bid
documents to the greatest extent possible - Include information on ground water levels,
flooding frequencies, foundation conditions, and
site access conditions, including photographs as
needed - Include required sequence of work and provide up
front coordination to the greatest extent
possible - Ensure that the overall goals of the project are
included - Hold a pre-bid conferences on site and document
the proceedings
25During the Construction Phase
- Communicate and reinforce the overall goals of
the project - Utilize partnering as a tool to foster
communication and joint ownership - Keep open communications, without sacrificing the
integrity of the Contractor/Government
contractual relationship. Each party needs to
understand and respect each others role - Document lessons learned
- Share successes!
26Why Are Contract Changes So Difficult and
Expensive?
27Contracting BasicsBased on FAR, DFAR, EFAR
and Corps Policy
28A contract is a legal agreement between the
Government and the Contractor which
- Binds the Contractor to fulfill the requirements
of the contract as prescribed in the contract - Binds the Government to pay a firm, fixed price
for successful completion of the contract
requirements in accordance with the terms and
conditions of the contract - Can only be changed by the Contracting Officer
(CO) or the Administrative Contracting Officer
(ACO) via contract modification
29Definitions
- Change An alteration in the terms or conditions
of the contract that materially impacts cost,
quality, or time of delivery - Modification Any written alteration in the
terms of the contract
30Changes Clause Allows the CO to make changes,
by written order, in the work within the
contract, including changes
- In the specifications, drawings, and designs
- In the method or manner of work performance
- In Govt furnished facilities, equipment,
materials, services, or site - Directing acceleration in the performance of the
work
31Other Clauses From Which Modifications Arise
- Differing Site Conditions
- Default Clause
- Suspension of Work Clause
- Government Property Clause
- Value Engineering Incentive
- Variations in Estimated Quantities
- Special Clause Damage to Work
32Common Reasons for Changes Issued Within the
Standard Contract Clauses
33User Originated Changes
- User mission or site operations plan change
- Site availability
- Funding change
- Additional needs
The user MUST approach the Corps to initiate
these changes. The change must be within the
scope of the contract
34Field Originated Changes
- Differing site conditions
- Ambiguities in plans and/or specs that result in
a design change - Government caused delays
- Unusually severe weather (time only)
These changes are initiated by the Corps
35Changes To Avoid
36Constructive Change An oral or written act or
omission by the CO or ACO which is construed or
inferred to have the same effect as a formal
written change order
- Danger - Actions by unauthorized person can
result in constructive changes due to the concept
of Apparent Authority , i.e., the Contractor
has some reasonable basis for assumption that the
unauthorized person has authority to act on
behalf of the CO.
37Cardinal Change A change outside the scope of
the contract.
- Cardinal changes are NOT authorized by any clause
in the contract. They are executed only by
exception and require specific Justification and
Approval for sole source procurement of the work.
- The apparent probability that the additional work
may be done more conveniently, or at a lower cost
by the original contractor, is NOT a controlling
factor for justifying sole source work.
38Factors Considered in the Within Scope
Determination
- What is reasonably within mind-set of the parties
at the time the contract was entered into, as
evidenced by contract documentation - Function of the end item
- Nature and purpose of the contract
- Often a judgment call, must be supported by the
CO
39The Cost of Changes
- If, due to a contract change, a contractor
experiences an increase or decrease in cost or
performance time, he may be due an equitable
adjustment.
40Equitable Adjustment
- The basic purpose of an equitable adjustment is
to keep the contractor whole when the Government
modifies a contract. Neither party is to be left
better or worse off than it was without the
modification.
41When negotiating an adjustment, the Government is
tasked with reaching a fair and reasonable price,
(not the lowest possible price), taking into
account factors such as
- Cost
- Risk
- Ingenuity and efficiency
- Other advantages gained by the Govt and the
Contractor
42The following are negotiated and may be included
in the settlement of an equitable adjustment
- Labor
- Equipment
- Materials
- Overhead (field and home office, including bond)
- Profit
- Extension of time
- Impact costs on the overall project
43Contract modifications are relatively costly due
to
- Lack of price competition
- Assumption of contractor risk for forward priced
modifications - Lack of cost incentive for two-part
modifications (time and material) - Lost efficiencies due to unplanned nature of the
work - Adverse impacts to other contract work
- Disruption of schedule due to added work and
interface with ongoing work - Increased overhead associated with time extensions
44So, What Can Be Done ?
45Minimize The Need For Modifications
- Ensure that plans and specifications capture all
technical requirements, site conditions, and site
operations requirements - Avoid ambiguities and conflicts between drawings
and specifications - Increase field explorations to reduce risks and
frequency of differing site condition changes - Detailed condition assessments
- Borings
- Surveys
- Site Visits
46Minimize The Need For Modifications, contd
- Ensure only authorized contracting
representatives give direction to contractors - Consider new procurements vs. modification
- Maintain open communications between Corps
construction staff, designers, and sponsors
47When Modification is Inevitable
- Respect contractual authorities and the role of
the Govt negotiator - Provide information to the negotiator
- Do not enter into discussions with the contractor
48For further assistance
- Contact your respective Corps Districts
Construction Division staff - Contact me
- Barbara L. Kimler, PE
- Area Engineer, Central Area Office
- 5235 Grand Avenue
- Davenport, Iowa 52807
- (563) 386-0572
- Barbara L. Kimler _at_ usace.army.mil