Construction Issues Associated With Environmental Projects - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

Construction Issues Associated With Environmental Projects

Description:

2. Environmental project work objectives and requirements are unusual: ... Value Engineering Incentive. Variations in Estimated Quantities. Special Clause: ... – PowerPoint PPT presentation

Number of Views:49
Avg rating:3.0/5.0
Slides: 49
Provided by: imsa2
Category:

less

Transcript and Presenter's Notes

Title: Construction Issues Associated With Environmental Projects


1
Construction Issues Associated With
Environmental Projects
Barbara L. Kimler, PE Central Area Engineer Rock
Island District
2
Why Are These Environmental Projects So Expensive?
3
1. Environmental work is technically challenging
  • Embankment materials are hard to work with,
    foundations are soft, and access is difficult.
  • Work requires specialized, expensive construction
    equipment and methods.
  • This results in higher production costs and lower
    productivity rates than traditional civil works
    construction.

4
Example Specialized Equipment Methods
  • Specialized dredges
  • Staging from barges
  • Floating excavators and swamp buggies
  • Timber mats
  • Cofferdams and dewatering
  • Winter work

5
Articulated Dredge
6
Barge Staging
7
Floating Excavator
8
Swamp Buggy
9
Timber Mats(or lack thereof)
10
Cofferdams and Dewatering
11
Winter Work
12
2. Environmental project work objectives and
requirements are unusual
  • To bidders, the contract packages appear like
    typical civil works projects such as channel
    dredging and flood protection. However, the
    actual construction requirements are
    non-traditional

13
Examples
  • Dredgers constructing islands rather than
    focusing on excavating channels
  • Fine grained cover requirements on island
    disposal sites
  • Levees and dikes constructed for impounding water
    rather than for flood protection.
  • .

14
Polander Lake Islands
15
Fine-Grained Sediment Cap
16
Upper Lake Chautauqua Levee
17
Result
  • Bidders underbid our projects not fully
    understanding the requirements
  • Bidders bid higher than standard construction as
    needed to successfully meet our requirements

18
3. Environmental Contracts Have Time and
Scheduling Restrictions and/ or Limitations
  • Working in the floodplain requires scheduling
    work around natural riverine cycles
  • Endangered species and refuge operating
    requirements often further restrict scheduling of
    work

19
Chautauqua Hydrograph
20
Milan Bottoms Section 1135 Endangered Species
Requirements
21
Impacts to a Contractor
  • Additional mobilization and demobilization costs
  • Contractor loses some of the best construction
    season
  • Contractor cant continuously schedule work
    crews, losing equipment and skilled labor to
    other jobs.
  • Field office overhead costs still have to be
    covered
  • Long duration impacts the Contractors ability to
    bid other work - ties up resources and bonding
    capacity

22
So, What Can Be Done?
23
During Contract Development Phase
  • Work with resource agencies regarding endangered
    species restrictions and refuge management
    requirements
  • Communicate/define actual construction
    requirements clearing, work limits, equipment
    access with resource agencies early in the design
    development
  • Utilize contracting methods that do not require
    selection of the lowest bidder. For example, use
    negotiated Best Value procurement methods rather
    than sealed bids

24
During Contract Development Phase, contd
  • Communicate the risks in the contract bid
    documents to the greatest extent possible
  • Include information on ground water levels,
    flooding frequencies, foundation conditions, and
    site access conditions, including photographs as
    needed
  • Include required sequence of work and provide up
    front coordination to the greatest extent
    possible
  • Ensure that the overall goals of the project are
    included
  • Hold a pre-bid conferences on site and document
    the proceedings

25
During the Construction Phase
  • Communicate and reinforce the overall goals of
    the project
  • Utilize partnering as a tool to foster
    communication and joint ownership
  • Keep open communications, without sacrificing the
    integrity of the Contractor/Government
    contractual relationship. Each party needs to
    understand and respect each others role
  • Document lessons learned
  • Share successes!

26
Why Are Contract Changes So Difficult and
Expensive?
27
Contracting BasicsBased on FAR, DFAR, EFAR
and Corps Policy
28
A contract is a legal agreement between the
Government and the Contractor which
  • Binds the Contractor to fulfill the requirements
    of the contract as prescribed in the contract
  • Binds the Government to pay a firm, fixed price
    for successful completion of the contract
    requirements in accordance with the terms and
    conditions of the contract
  • Can only be changed by the Contracting Officer
    (CO) or the Administrative Contracting Officer
    (ACO) via contract modification

29
Definitions
  • Change An alteration in the terms or conditions
    of the contract that materially impacts cost,
    quality, or time of delivery
  • Modification Any written alteration in the
    terms of the contract

30
Changes Clause Allows the CO to make changes,
by written order, in the work within the
contract, including changes
  • In the specifications, drawings, and designs
  • In the method or manner of work performance
  • In Govt furnished facilities, equipment,
    materials, services, or site
  • Directing acceleration in the performance of the
    work

31
Other Clauses From Which Modifications Arise
  • Differing Site Conditions
  • Default Clause
  • Suspension of Work Clause
  • Government Property Clause
  • Value Engineering Incentive
  • Variations in Estimated Quantities
  • Special Clause Damage to Work

32
Common Reasons for Changes Issued Within the
Standard Contract Clauses
33
User Originated Changes
  • User mission or site operations plan change
  • Site availability
  • Funding change
  • Additional needs

The user MUST approach the Corps to initiate
these changes. The change must be within the
scope of the contract
34
Field Originated Changes
  • Differing site conditions
  • Ambiguities in plans and/or specs that result in
    a design change
  • Government caused delays
  • Unusually severe weather (time only)

These changes are initiated by the Corps
35
Changes To Avoid
36
Constructive Change An oral or written act or
omission by the CO or ACO which is construed or
inferred to have the same effect as a formal
written change order
  • Danger - Actions by unauthorized person can
    result in constructive changes due to the concept
    of Apparent Authority , i.e., the Contractor
    has some reasonable basis for assumption that the
    unauthorized person has authority to act on
    behalf of the CO.

37
Cardinal Change A change outside the scope of
the contract.
  • Cardinal changes are NOT authorized by any clause
    in the contract. They are executed only by
    exception and require specific Justification and
    Approval for sole source procurement of the work.
  • The apparent probability that the additional work
    may be done more conveniently, or at a lower cost
    by the original contractor, is NOT a controlling
    factor for justifying sole source work.

38
Factors Considered in the Within Scope
Determination
  • What is reasonably within mind-set of the parties
    at the time the contract was entered into, as
    evidenced by contract documentation
  • Function of the end item
  • Nature and purpose of the contract
  • Often a judgment call, must be supported by the
    CO

39
The Cost of Changes
  • If, due to a contract change, a contractor
    experiences an increase or decrease in cost or
    performance time, he may be due an equitable
    adjustment.

40
Equitable Adjustment
  • The basic purpose of an equitable adjustment is
    to keep the contractor whole when the Government
    modifies a contract. Neither party is to be left
    better or worse off than it was without the
    modification.

41
When negotiating an adjustment, the Government is
tasked with reaching a fair and reasonable price,
(not the lowest possible price), taking into
account factors such as
  • Cost
  • Risk
  • Ingenuity and efficiency
  • Other advantages gained by the Govt and the
    Contractor

42
The following are negotiated and may be included
in the settlement of an equitable adjustment
  • Labor
  • Equipment
  • Materials
  • Overhead (field and home office, including bond)
  • Profit
  • Extension of time
  • Impact costs on the overall project

43
Contract modifications are relatively costly due
to
  • Lack of price competition
  • Assumption of contractor risk for forward priced
    modifications
  • Lack of cost incentive for two-part
    modifications (time and material)
  • Lost efficiencies due to unplanned nature of the
    work
  • Adverse impacts to other contract work
  • Disruption of schedule due to added work and
    interface with ongoing work
  • Increased overhead associated with time extensions

44
So, What Can Be Done ?
45
Minimize The Need For Modifications
  • Ensure that plans and specifications capture all
    technical requirements, site conditions, and site
    operations requirements
  • Avoid ambiguities and conflicts between drawings
    and specifications
  • Increase field explorations to reduce risks and
    frequency of differing site condition changes
  • Detailed condition assessments
  • Borings
  • Surveys
  • Site Visits

46
Minimize The Need For Modifications, contd
  • Ensure only authorized contracting
    representatives give direction to contractors
  • Consider new procurements vs. modification
  • Maintain open communications between Corps
    construction staff, designers, and sponsors

47
When Modification is Inevitable
  • Respect contractual authorities and the role of
    the Govt negotiator
  • Provide information to the negotiator
  • Do not enter into discussions with the contractor

48
For further assistance
  • Contact your respective Corps Districts
    Construction Division staff
  • Contact me
  • Barbara L. Kimler, PE
  • Area Engineer, Central Area Office
  • 5235 Grand Avenue
  • Davenport, Iowa 52807
  • (563) 386-0572
  • Barbara L. Kimler _at_ usace.army.mil
Write a Comment
User Comments (0)
About PowerShow.com