Title: A Critical Look At Critical Chain Project Management
1A Critical Look At Critical Chain Project
Management
Best Practice Project Management
- Tzvi Raz, Ph.D., P.M.P.
- Tel Aviv University, Israel
- tzvir_at_tauex.tau.ac.il
- Robert Barnes, M.Sc., Dip. Mgmt, P.M.P.
- The iE3 Group Ltd, New Zealand
- robert.barnes_at_xtra.co.nz
- www.robertb.co.nz
- My presentation supported by
2Agenda
- Introduction - What is CCPM?
- Critical analysis of CCPM
- based on the evidence in the research literature
and in practice. - CCPM - substitute for or addition to conventional
PM. - NB - I have significantly edited this
presentation since the conference
3Section 1. Introduction
- Critical Chain Project Management is -
- A fresh look at Project Management from Eliyahu
Goldratt ( Critical Chain) - Applies Theory Of Constraints (TOC) to Projects
- Claimed to achieve dramatic successes for
projects, as TOC did for processes ( The
Goal) - Intuitively Plausible
- Seems to hold answers to many of the problems
that have long troubled Project Managers - Creating huge interest in the PM community
- eg, at least one paper on CCPM in most PM Network
issues
4Critical Chain Project Mgmt
- Is it New and Brilliant?
- or Largely Hype?
- First - what is it?
- (How does it differ from conventional PM?)
5An Overview Of CCPM
- Step 1. Identify Critical Chain
- Initial Schedule -gt Critical Path. (A-gt B-gt D)
- Resource leveling -gt Critical Chain. (A-gtB-gt C-gt
D) - Critical Chain - The longest path through the
network after resource leveling.
6An Overview Of CCPM (contd.)
- Step 2. Make hidden buffers explicit.
Hidden Buffer
50
80
Unused Hidden Buffer is Wasted!
7Why is hidden buffer wasted(1)?
- Origins in workers conflict -
- Want to finish tasks on time
- so need buffers
- Want to be productive (busy)
- need plenty of work, no buffers
- CONFLICT
- solve by taking on more work
8Why is hidden buffer wasted (2)?
Non-critical Jobs
Another Job(Wkr B)
Another Job2(Wkr B)
Job 1(Wkr A)
Job 2(Wkr B)
Job 3(Wkr C)
Job 4(Wkr B)
- Wkr B knows that (s)hes not needed until day 6,
- gt Wkr B keeps busy with other work, and is not
available until day 6 - gt if Wkr A finishes Job1 early, job 2 cant
start anyway - gt Wkr A knows that finishing early wont help
the project - gt rather than finishing early, Wkr A will use
spare time on other tasks
9Hence the schedule rule -
- If estimated durations are correct ON AVERAGE
- THE PROJECT WILL STILL BE LATE!
- Because
- Schedule gains are lost
- Schedule losses are passed on in full
10CCPM Step 3. Buffer Management
- Step 3. Show buffers explicitly
- and pool them
Conventional Project Schedule
Task buffers are hidden
within individual tasks
Job 1
Job 2
Job 3
Job 4
CCPM Schedule
Buffers are pooled,
and made explicit
Project Buffer,
11Feeding Buffers - the same principle, but on
non-critical paths
Project Buffer
Date 2
Date 1
Feeding Buffer
If Slack remains, then schedule as late as
possible
12Resource Buffers - a Wake up call
Feeding Buffer
Critical Chain
Project Buffer
Alert Wkr A
Alert Wkr B
Resource Buffers
Alert Wkr C
- Adds neither Time nor Cost to the Project
13CCPM Project Management (1)
- Focus on the Critical Chain
- Ensure resources give CC tasks priority
- Eliminate multitasking
14CCPM Project Management (2)
Its OK for a task to be late
But not TOO Late
Focus on Buffer Consumption. Should be in
Proportion or better
15Multiple Projects under CCPM
- Resources required to work simultaneously on
several projects should give priority to the task
of the one project that is in the greatest risk
of missing its committed date, as measured by the
remaining fraction of project buffer.
16Section 2. A Critique of CCPM
- Does CCPM deliver?
- Anecdotal evidence suggests Yes
- Closer examination more ambiguous
- There are several points where CCPM assumptions
can be challenged
171/ Hidden buffers may not exist
- CCPM assumes that
- all task owners pad estimates
- the actual duration expands to fill the time
allotted. - This is very Plausible,
- but theres no scientific support
- Research literature contains contrary evidence
Hill et al. (2000) - Personal experience - mixed. Some incorrigible
optimists! - Does reducing task duration reduce commitment?
- Personal experience - little effect, but suspect
that there could be some risk of this - Do we still get safety margin on top of buffer?
- Probably yes.
Parkinsons Law
182/ How big should explicit buffers be?
- CCPM does not provide any scientific or objective
basis for determining the buffer size - Default 1/3 suggested, based on probability
distribution - No empirical basis for using this probability
curve - CCPM uses statistical assumption of independent
values (for task duration and buffer) - NOT TRUE - Experience
- Discuss with task owner, get agreement
- Varies widely
- Optimists, pessimists - estimating errors dont
cancel
193/ CCPM gives incorrect Resource Graph
- When do you need Worker A?
Gantt Chart
Resource Graph. Not this
But This
204/ What if theres insufficient room for feeding
buffer?
Conventional Plan - had free float
Date 2
Date 1
Should excess buffer be added to the critical
chain? Correct answer is NO, but what do you do
with it? (CCPM ignores this problem). Indicates
a near-critical path - could easily become the CP.
215/ The Critical Chain
- How good is the resource-leveled schedule that
serves as the basis for CCPM ? - As good as the algorithm used for its calculation
- The critical chain may change
- Feeding buffer exceeds the free slack of the
feeding chain - During project execution the critical chain may
change as resource availability changes or as
buffers are used - This is true of conventional PM also
- but CCPM may add complexity
226/ Schedule control
- CCPM achieves schedule control by monitoring the
extent of buffer penetration. - The remaining-work estimate is also subjected to
inflation by safety margins. - CCPM assigns priority to the task belonging to
the chain with the highest rate of buffer
penetration. - Ignores other important criteria, such as a
projects strategic or financial impact.
237/ Multi-Project Management
- CCPM staggers the projects around the
constraining resource. - At any given point in time there could be several
constraining resources, each leading to a
different schedule. - The premise that there is a single constraining
resource comes from the steady state of
manufacturing and operations environments. - Consequently we doubt the applicability of the
solution obtained with CCPM.
248/ CCPM Focus
- Project success and project management success
are not equivalent. - Project management success meeting agreed goals
on time and budget. - Project success benefits to customers and
stakeholders - Both conventional and CCPM deal with project
management success rather than project success - but CCPM focuses exclusively on ON TIME
- Focus
- CCPM meeting schedule goals by dealing with
schedule uncertainty - Conventional both cost and schedule.
259/ CCPM is presented as Alternative
- CCPM is presented as a revolutionary concept that
replaces current project management knowledge and
practices - It is not properly integrated with the accepted
body of knowledge and state of the practice. - Dilemma to organizations that are new to project
management choose between CCPM or mainstream
methodologies.
2610/ CCPM may have high Adoption Costs
- Specialized software tool needed
- CCPM presented as a methodology to be adopted as
a whole ?massive re-education - Culture change may be difficult -
- Give up ownership of the task duration
- Rely on common buffers to absorb deviations in
individual task performance. - Replace Due Date by Estimated Completion Date
Range as represented by feeding and project
buffers. - No multi-tasking.
27Section 3. Concluding remarks.
- CCPM has adapted the concepts of bottlenecks and
material buffers from TOC for operations
management, calling them critical chain and
time buffers in projects. - CCPM concepts are not necessarily new
- But does this matter? In our view, NO. CCPM
would be worthy of study even it were only a
packaging of old ideas - and theres more to it than that!
28The Key Question -
- Is CCPM as a methodology indeed superior to the
currently accepted project management
methodologies? - Some dramatic successes have been claimed.
- However, we are not aware of studies comparing
CCPM with a properly-applied conventional project
management methodology. - We DO NOT believe that CCPM is a better
alternative to conventional PM. - We DO believe that CCPM has good ideas which
should be included in conventional PM - PMBOK should take it more seriously
29A Parallel
30Good ideas from CCPM (1)
- Account explicitly for duration uncertainty
- Focus on Project on time, not Task on time
- Always consider resource availability
- What is the shortest realistic plan?
- Critical Chain is a useful term
- Focus on the key tasks and resources
- Reduce or eliminate multitasking
- Management focus
31Good ideas from CCPM (2)
- Constantly monitor the amount of slack (buffer)
in your schedule - Provide flexible advance notice of upcoming work
to critical resources
32Finally, our suggestions
- Incorporate those CCPM elements that are
applicable to your environment within a broader
project management methodology. - Consider the broader context
- Project success vs. meeting due date
- Reducing uncertainty vs. buffer management
- Adopt a comprehensive methodology
- Consider costs and benefits as well as time
33Thank you for Listening