Title: ACHIEVING CAPACITY PLANS: INPUTOUTPUT CONTROL


1
ACHIEVING CAPACITY PLANS INPUT/OUTPUT CONTROL
  • The CRP Connection
  • Planned Input and Planned Output
  • Actual Versus Planned
  • Cumulative Deviations and WIP

2
CORE MRP II
MANUFACTURING RESOURCE PLANNING
3
INPUT/OUTPUT CONTROL THE CRP CONNECTION
  • Capacity requirements planning
  • Estimates capacity needs in each workcenter given
    the material plans
  • Input/output analysis
  • compares actual to planned capacity
  • Manager makes adjustments as necessary

4
INPUT/OUTPUT EXAMPLE
  • Consider the input/output chart for a single
    workcenter
  • 2 workorders, each with a total of 10 DLH run
    setup, are in-process at the workcenter

5
FROM CRP STAFFING PLANS TO PLANNED INPUT
OUTPUT
  • Planned capacity input to the workcenter depends
    on
  • Planned order releases
  • Setup run time needed for material plans
  • Planned capacity output for workcenter is based
    upon
  • Workhours per day workcenter has available

6
INPUT/OUTPUT EXAMPLE
  • 10 workorders, each with 10 DLH of run and setup
    time, are to be released to the workcenter at the
    beginning of the week

7
INPUT/OUTPUT EXAMPLE
  • The staffing plan for the upcoming week calls for
    20 hours of available capacity per day

8
INPUT/OUTPUT EXAMPLE
  • The projected WIP is then readily calculated

9
ACTUAL VERSUS PLANNED
  • What actually happens may differ from the plan
  • Actual input
  • Records actual arrival of workorders throughout
    the week
  • Quantity based on routing's run setup 
  • Actual output
  • Records actual departure of workorders throughout
    the week
  • Quantity based on routing's run setup

10
INPUT/OUTPUT EXAMPLE
  • 4 workorders arrive on schedule, but parts
    shortages and problems in upstream production
    prevent the others from arriving

11
INPUT/OUTPUT EXAMPLE
  • Only 1 workorder is actually completed due to
    unexpected setup problems, but another is started

12
INPUT/OUTPUT EXAMPLE
  • The actual inventory is calculated, in DLH, and
    compared to the plan

13
CUMULATIVE DEVIATIONS
  • If actual wip does not match planned wip, need to
    determine cause of the problem output or input
    deviations?
  • CDt cumulative deviation in period t
  • For input or output deviations,
  • CDt CDt-1 Actualt - Plannedt

14
INPUT/OUTPUT EXAMPLE
  • 0 40 100 - 60

15
INPUT/OUTPUT EXAMPLE
  • 0 10 20 - 10

16
INPUT/OUTPUT EXAMPLE
  • No new jobs arrive on Tuesday, but 3 jobs are
    completed

17
INPUT/OUTPUT EXAMPLE
  • Our WIP is way low whats the problem?

18
INPUT/OUTPUT EXAMPLE
  • Wednesday brings one more workorder

19
INPUT/OUTPUT EXAMPLE
  • Thursday brings another job, but were out of
    WIP

20
INPUT/OUTPUT EXAMPLE
  • Gin rummy time on Friday