Material Requirements Planning - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Material Requirements Planning

Description:

Manufacturing Resource Planning (MRPII) Expanded MRP with and emphasis placed on integration ... Manufacturing. Precursor of ERP. MATERIAL REQUIREMENTS PLANNING ... – PowerPoint PPT presentation

Number of Views:80
Avg rating:3.0/5.0
Slides: 22
Provided by: betha166
Category:

less

Transcript and Presenter's Notes

Title: Material Requirements Planning


1
Chapter 13
  • Material Requirements Planning

2
Materials Requirement Planning (MRP)
  • Computer based information system to handle
    ordering and scheduling of dependent demand items

Product Structure Tree
3
  • Dependent items are needed just prior to when
    they are needed for production
  • Demand is lumpy
  • Little or no safety stock

4
  • MRP converts the production plan for final
    products into requirements for component items
    and raw materials
  • What is needed
  • When is needed
  • How much is needed
  • When should procurement, fabrication assembly
    start for completing end items on time

5
(No Transcript)
6
MRP Inputs
  • Master Schedule Which end items are to be
    produced, when these are needed, and in what
    quantities.
  • The planning horizon is divided into time periods
    called time-buckets (typically weeks)
  • The planning horizon should be long enough to
    cover the cumulative leadtime. (total lead time
    required from ordering of parts or raw materials
    to completion of final assembly)

7
MRP Inputs
  • Bill-of-Materials (BOM) File List of all raw
    materials,parts, subassemblies needed to produce
    the product.
  • Illustrated using a product-structure tree

8
  • End Item final product sold to the customer it
    is a parent, not a component, e.g., C.
  • Intermediate Item has at least one parent and
    one component, e.g., LA, BA.
  • Purchased Item No component but has parent,
    e.g., L, CB, S, SR, BS.

9
MRP Inputs
  • Inventory Records File Info on the inventory
    status of each item by time period.
  • Requirements
  • Scheduled receipts
  • Projected on-hand inventory levels
  • Leadtime information
  • Other details (supplier, lot size etc)
  • Transactions are recorded and updates done every
    time period

10
MRP Processing (Explosion Calculus)
  • Time-phased requirement of all items using BOM
    and leadtimes. For every item and for every time
    period calculate
  • Gross requirements Total demand
  • Scheduled receipts Orders scheduled to arrive at
    the beginning of the period
  • Projected on hand Expected Inventory at the
    beginning of the period
  • Net requirements Actual amount needed
  • Planned-order receipts Quantity expected to be
    received at the beginning of the period
  • Planned-order releases Planned amount to order
    in the period (P.O.R. offset by leadtime)

11
Example (Chair Assembly)
  • Suppose that a 100-unit delivery of chairs is
    scheduled at the start of week 6. Determine the
    size and the timing of back-support parts to meet
    this delivery.
  • The firm has 20 back support units available and
    60 more is scheduled to arrive at the beginning
    of Week 4.

12
(No Transcript)
13
  • Should Net Requirements Planned Order
    Receipts?
  • Lot-for-lot production
  • Other common lot sizing rules
  • Economic Order Quantity (EOQ)
  • Fixed Period Ordering (Order to cover a fixed
    of coming periods)
  • Fixed Multiple batch size
  • Extra production is carried into future periods
    as inventory

14
  • Suppose that the lot-size of back support units
    is 50.
  • Can only produce at multiples of 50.

15
MRP Outputs
  • Planned orders - schedule indicating the amount
    and timing of future orders.
  • Order releases - Authorization for the execution
    of planned orders.
  • Changes - revisions of due dates or order
    quantities, or cancellations of orders.

Secondary Reports
  • Performance-control reports
  • Planning reports
  • Exception reports

16
Capacity Planning
  • How do we ensure that the resulting production
    orders and schedule is feasible (does not exceed
    capacity)?
  • Capacity requirements planning The process of
    determining short-range capacity requirements.
    MRP systems can create
  • Load reports Department or work center reports
    that compare known and expected future capacity
    requirements with projected capacity
    availability.

17
MRP Planning in Practice
18
Benefits of MRP
  • Low levels of in-process inventories
  • Ability to track material requirements
  • Ability to evaluate capacity requirements
  • Means of allocating production time

Requirements of MRP
  • Computer and necessary software
  • Accurate and up-to-date inputs (master
    schedules,BOM,inventory records)
  • Integrity of data

19
Shortcomings of MRP
  • Uncertainty not taken into account
  • Capacity till now mostly uncapacitated
  • Nervousness major changes in production plan due
    to revised schedule

20
Manufacturing Resource Planning (MRPII)
  • Expanded MRP with and emphasis placed on
    integration
  • Financial planning
  • Marketing
  • Engineering
  • Purchasing
  • Manufacturing

Precursor of ERP
21
Master production schedule
Finance
Manufacturing
Marketing
MRP
Adjust master schedule
Capacity planning
Adjust production plan
No
Yes
No
Yes
Problems?
Write a Comment
User Comments (0)
About PowerShow.com