Planning for Material and Resource Requirements - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

Planning for Material and Resource Requirements

Description:

... in the Master schedule row for the week being ... Front Axle Supports. 21. Combining Demand from Multiple Sources and Levels. 22. Manufacturing ... – PowerPoint PPT presentation

Number of Views:57
Avg rating:3.0/5.0
Slides: 23
Provided by: cgrz
Category:

less

Transcript and Presenter's Notes

Title: Planning for Material and Resource Requirements


1
CHAPTER 13

Planning for Material and Resource Requirements
2
Learning Objectives
  • Explain the relationship between the aggregate
    plan and the master production schedule.
  • Given a weekly schedule of forecast demand and
    customer orders booked, calculate projected
    on-hand inventory and determine when to master
    schedule more production.
  • Given a weekly schedule of forecast demand,
    customer orders booked, projected on-hand
    inventory, and master schedule, calculate
    available-to-promise for any week in which
    production is scheduled.
  • Use the method of overall factors to calculate
    capacity requirements.

3
Learning Objectives (contd)
  • Interpret a product structure tree diagram.
  • Given a master schedule and product structure,
    calculate planned order releases for an item at
    any level.
  • Combine requirements from several sources in
    determining gross requirements.
  • Define Manufacturing Resource Planning.

4
Maine Woods Co. Aggregate Plan, Wheel-Goods
Product Group
Regular Over
Forecast Time
Time Inventory
Month Demand Production
Production Beginning Ending Sept.
2,500 2,000
1,000 500 Oct.
2,900 2,000
400 500
0 Nov. 2,400 2,000
400 0
0 Dec. 2,000
2,000
0 0
5
Maine Woods Co. Master Production Schedules,
Wheel-Goods Product Group
6
Maine Woods Co. Master Production Schedule Based
on Demand Forecast and Booked Customer Orders for
Toy Wagons
7
To determine projected inventory on hand for a
specific week, perform the following calculations
  • Add either actual inventory on hand from the
    preceding week or projected on-hand inventory
    from the preceding week to any quantity shown in
    the Master schedule row for the week being
    calculated.
  • Determine the larger of forecast demand or
    customer orders booked.
  • Subtract the amount determined in step 2 from the
    amount in step 1.

8
Calculation of Available-to-Promise for November
and December for Maine Woods Co.
9
Calculation of Total Capacity Requirements for a
Master Schedule
10
Calculation of Total Capacity Requirements for a
Master Schedule
11
Calculation of Total Capacity Requirements for a
Master Schedule
12
Calculation of Estimated Capacity Requirements
for Individual Work Stations
13
Independent vs. Dependent Demand
  • Independent demand items usually include finished
    products, such as the completed tricycle, or
    replacement parts sold to customers.
  • Dependent demand is usually demand for an item
    that is generated by a company's own production
    process.

14
Exploded View ofMaine Woods Tricycle
15
Product Structure Tree Diagram for Maine Woods
Tricycle
16
Table for MRP
Transparency 15.13
(Exhibit 15.16)
17
MRP for Front Assemblies
18
Partially Completed MRPFront Assemblies
19
Completed MRPFront Assemblies
20
MRP for a Level 2 ItemFront Axle Supports
21
Combining Demand from Multiple Sources and Levels
22
Manufacturing Resource Planning (MRP II)
  • Includes requirements for resources other than
    materials (usually financial)
  • Cost Control
  • Simulation
Write a Comment
User Comments (0)
About PowerShow.com