IS 476: Project Management - PowerPoint PPT Presentation

1 / 5
About This Presentation
Title:

IS 476: Project Management

Description:

... period, sum the resources that are being used simultaneously. 11/24/09 ... Answer: Yes! There are two ways to create a smoother distribution of resource usage: ... – PowerPoint PPT presentation

Number of Views:24
Avg rating:3.0/5.0
Slides: 6
Provided by: busine2
Category:

less

Transcript and Presenter's Notes

Title: IS 476: Project Management


1
IS 476 Project Management
  • cle

2
Resource Allocation The Physical Resources
  • Labor
  • Facilities
  • Materials
  • Equipment

3
Two Important Concepts
  • Resource Loading
  • Resource Leveling

4
Resource Loading
  • How much of each type of resource is needed for
    each period in the existing schedule?
  • Answer For each period, sum the resources that
    are being used simultaneously

5
Resource Leveling
  • Is it possible to minimize the period-by-period
    fluctuations in resource loading?
  • Answer Yes! There are two ways to create a
    smoother distribution of resource usage
  • 1. Shift tasks within their slack allowances
  • 2. Extend the duration of the project